Define the term - Clamp splice

In a Clamp splice, bolts and nuts alongwith clamp plates are used. Tendons are held in-between the clamp plates and these clamp plates are tightened with the help of bolts and nuts, as shown in Figure There is a considerable reduction in the tensile strength of tendons (say, utpo 50%) due to the use of this splice. This is why, the use of this type of splice is recommended in locations where the prestressing force may be sufficiently reduced, e.g. due to the curvature of tendons.

1796_Clamp splice.png


Related Discussions:- Define the term - clamp splice

State the design process of prestressed concrete, State the Design process ...

State the Design process of Prestressed Concrete Most of the times, the design process is an interactive and trial procedure in which the cycle of analysis - design - analysis

Define the impact damage - underwater inspection of bridge, Define the Impa...

Define the Impact Damage - underwater inspection of bridge? Impact from moving vessels or logs carried during the floods can inflict damage to the structure. The impact or coll

Pumping for concreting works, Question What are the key problems if use pu...

Question What are the key problems if use pumping for concreting works ? Answer In pumping operation , force exerted by pumps have to overcome friction involving concrete an

Surveying, length of the line measured with 20m chain found to be 250m.calc...

length of the line measured with 20m chain found to be 250m.calculate true length if the chain was 10cm long

Product layout, Product Layout: Imagine a factory manufactures taps, d...

Product Layout: Imagine a factory manufactures taps, drills, reamers and cutters. The production of each of these items needs different machines which may be placed in differe

Investigation scour for underwater inspection of bridge, Define Investigati...

Define Investigation Scour for Underwater Inspection of Bridge? Investigation Scour is probably the most critical item to be aware of when performing an underwater inspection o

Duration activity for cast-in-place foundation formwork, A concrete contrac...

A concrete contractor historical records show that the construction duration for a cast-in-place foundation formwork is 1,000-SF/crew-day. Determine the number of days a 200,000-SF

Indicate quality of rock foundation, Question During piling works, norm...

Question During piling works, normally founding levels of bored piles are definite by using total core recovery or rock quality designation (RQD). Are there any problems by

Enumerate the variation in tendon stress, Enumerate the Variation in tendon...

Enumerate the Variation in tendon stress In post-tensioned construction, several tendons are simultaneously stretched and anchored at the ends. It is assumed that all tendons

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd