datawarehousing, Computer Engineering

) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.



Posted Date: 3/28/2013 7:49:26 PM | Location : USA







Related Discussions:- datawarehousing, Assignment Help, Ask Question on datawarehousing, Get Answer, Expert's Help, datawarehousing Discussions

Write discussion on datawarehousing
Your posts are moderated
Related Questions

What do you mean by underflow and overflow of data? Underflow and overflow of data: When the value of the variable is either too long or too small for the data type to hold,


Flynn's Classification  This classification was early proposed and studied by Michael Flynn in 1972. Flynn did not believe the machine architecture for organization of parallel

What is store program control (SPC)? Within stored program control systems, a program or set of instructions for the computer that is stored in its memory and the instructions

What is the draw back of micro programmed control? It leads to a slower operating speed because of the time it takes to fetch microinstructions from the control store.


What is CTS and CLS? CLS stands for common language specification CTS stands for common type system.

Q. Show the Programmes for Parallel Systems? Adding elements of an array using two processor      int sum, A[ n] ;  //shared variables

Q. Register-to-register operands in RISC? Register-to-register operands: In RISC machines operation which access memories are LOAD and STORE. All other operands are kept in reg