1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.
Posted Date: 4/2/2013 12:07:13 PM | Location : USA







Related Discussions:- Datawarehouse, Assignment Help, Ask Question on Datawarehouse, Get Answer, Expert's Help, Datawarehouse Discussions

Write discussion on Datawarehouse
Your posts are moderated
Related Questions
The Database Approach In order to overcome the limits of a file system, a new approach was needed. Hence a database approach emerged. A database is a persistent collection of

Project Description: I am updating my Javascript + HTML website with five domains for the same website I would like to know if I want to create site map and submit it in all the

Database design Database tables will be created for you on the Technology web server. The schema will be as follows. Please note that this is a simplified database structure, d

how to prepare a data dictionary for online examination system for certified courses?

Update or Modify operation alters the existing values. If these operations alter the value that is the foreign key also, the only check need is the similar as that of the Insert op

Write short notes on relational model   The  relational  model  uses a  collection of  tables  to show  both data  and the relationships between those  data.  The relational mo

What is a candidate key? Minimal super keys are known as candidate keys.

In Database software have only pure security or some dis secured by administrator?

List and also explain the dissimilar stages of DDLC ?

What is the disadvantage of a call by reference? During a call by reference damage or loss of data is not restricted to the subroutine, but will instantly lead to alters to th