Datawarehouse, Database Management System

How to define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.
Posted Date: 4/2/2013 8:42:47 AM | Location : USA







Related Discussions:- Datawarehouse, Assignment Help, Ask Question on Datawarehouse, Get Answer, Expert's Help, Datawarehouse Discussions

Write discussion on Datawarehouse
Your posts are moderated
Related Questions
Explain the challenges before an E-business management.

Determine the Derived attribute to avoid re-computation Each class box consists of an ordered list of attributes and operations, each represented as a next string. We can find

What is OLTP (Online Transaction Processing)? In OLTP - online transaction processing systems relational database design use the discipline of data modeling and generally follo

Explain Authorization and Integrity Manager ? Authorization and Integrity Manager: Tests for the satisfaction of integrity constraints and checks the authority of users to acce

Define the Attribute Inheritance The attributes of a higher level entity set are inherited through a lower level entity set made by specialization-generalization hierarchy. Nam

(a) Design a query plan for the following distributed query: An application at site B wants to compute a join of STUDENT ? Id=StudId TRANSCRIPT where STUDENT (Id,Major) is at site

Define the term Domain. For each n every attribute there is a set of permitted values known as the domain of that attribute.

Consider the relations described below: PHYSICIAN (regno, name, telno, city) PATIENT (pname, street, city) VISIT (pname, regno, date_of_visit, fee) Where the regno and pname ide

Our company hires independent contractors to install equipment at precise locations across North America. We want to track the installation data and generate reports. The compan

Serialisability: Any schedule that makes the similar results as a serial schedule is known as a serialisable schedule. But how can a schedule are determined to be serialisable or n