data warehouse, Database Management System

#queDefine a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run togetherstion..
Posted Date: 3/30/2013 2:12:41 AM | Location :







Related Discussions:- data warehouse, Assignment Help, Ask Question on data warehouse, Get Answer, Expert's Help, data warehouse Discussions

Write discussion on data warehouse
Your posts are moderated
Related Questions
Differentiate between strict two-phase and rigorous two-phase with conversion protocol Ans:  Strict two-phase locking holds all its exclusive that is write locks until commit t

Distributed Control and Data sharing: The geographical distribution of an organization can be showed in the distribution of the data; if a number of different sites are linked to e

State the Design of Associations Before designing associations, it is essential to know the way they are used. For this, analysis of association traversals is required. It is

In case of entity integrity, the primary key may be declared? In a case of entity integrity primary key may be not Null.

What is the difference between SQL Server 2000 complete and differential backups? A complete backup makes a copy of the whole database. A differential backup creates a copy of

Should I select imaging software that allows changes? An imaging system should not give features to edit or alter images. Images generally are formed as safe and secure records


what is check point in database management system

sql is relationally complete-justify

What is RDBMS terminology for a row? A tuple is a RDBMS terminology for a row