Cutbacks and emulsions, Civil Engineering

Cutbacks And Emulsions:

Cutbacks

A cutback is a bitumen whose viscosity has been reduced by adding a diluent such as naphtha or kerosene. The use of cut-back is not favoured as the diluents may find their way to water bodies and cause environmental problems.

Posted Date: 1/22/2013 3:12:23 AM | Location : United States







Related Discussions:- Cutbacks and emulsions, Assignment Help, Ask Question on Cutbacks and emulsions, Get Answer, Expert's Help, Cutbacks and emulsions Discussions

Write discussion on Cutbacks and emulsions
Your posts are moderated
Related Questions
Please advise what is the proportion of mix to achieve 45N/sq. mm compressive strength with 370Kg.SR cement per cubic meter and 35N/Sq.mm strength with OPC cement 330 kg per cubic

A continuous footing of width 2.5 m rests 1.5 m below the ground surface in clay. The unconfined compressive strength of the clay is 150 kN/m 2 . Measure the ultimate bearing ca

Using Matlab/ Simulink software to model the overall building fabric heat transmit characteristics, in order to estimate the maximum rate of heat loss (kW) from the building under

Question In designing of corbel beams in a pump station , why are shear links designed in top 2/3 of section? What is general advice on designing? Answer Corbel

Explain Critical factor in Design of shock transmission unit? (a) STUs are unidirectional devices for load transmission. If out of plane forces will be acting on the STU, the a

Question What is key disparity between working stress approach and limit state approach ? Answer Working stress approach, service loads are used in whole plan and st

plane table surveying is used commonly to survey small areas because

A square pile group of 9 piles passes by a recently filled up material of 4.5 m depth. The diameter of the pile is 30 cm and pile spacing is 90 cm centre to centre. If the unconfin

Q. What do you mean by Geotextile filter? Geosynthetics is a collective term applied to thin, flexible sheets incorporated in or about soil to enhance its engineering performan

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most near