Critical path analysis, Computer Engineering

  1. Given the information provided in Table 1:
    1. Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool);
    2. Prepare a table of the possible activity paths and identify the critical path;
    3. Assume that adding an additional person to the project allows the project manager to reduce any task under PM control that is 4 or more days long by one day (tasks P, Q, and R are external and cannot be changed). How does this affect the critical path, and what is the duration of the project with the added resource?

Important Note:  Be sure to take into consideration any special dependencies indicated in the chart (e.g., start-to-start, finish-to-finish) when calculating durations, slack, critical path, etc.  The normal dependency unless otherwise stated is finish-to-start. If there is a delay between two activities, it is shown as a plus or minus offset.  For example, a start-to-start + 5 dependency means the dependent task is planned to start 5 days after the start of the predecessor task.  Any special dependencies shown only apply to the immediate task listed to the left, not to the other tasks in the list.

Table.  Desktop Installation Project

Activity

Description

Estimated Duration (Days)

Predecessor

A

Determine workstation applications

5

-

B

Determine hardware specifications

5

A

C

Determine image configurations

3

B

D

Purchase evaluation workstation

5

B

E

Purchase workstation software

5

C

F

Create image

2

D, E

G

Test image

2

F

H

Customer acceptance testing of image

3

G

I

Prepare purchase order

3

A, B, H (Finish to Finish)

J

Acquire workstations

8

I

K

Install image on workstations

8

J

L

Install workstations on site

6

Q, K (Start to Start + 4)

M

Connect workstations to network

6

P, L (Start to Start +2)

N

Test workstations

6

M (Start to Start +2)

O

Prepare closeout report

3

N

P

Test network connections

6

B

Q

Install furniture

10

R

R

Acquire furniture

16

B

Posted Date: 3/19/2013 3:01:32 AM | Location : United States







Related Discussions:- Critical path analysis, Assignment Help, Ask Question on Critical path analysis, Get Answer, Expert's Help, Critical path analysis Discussions

Write discussion on Critical path analysis
Your posts are moderated
Related Questions
Advantages of MPI: Every process has its own local variables It can be used on a broader range of problems than OpenMP It runs on either distributed or shared memor

What is the main problem with segmentation? Problem with segmentation (i) Is with paging, such mapping needs two memory references per logical address that slows down the

What is cache memory? The small and fast RAM units are known as caches. When the implementation of an instruction calls for data located in main memory, the data are obtained a

A critical section is a program segment? Ans. A critical section is a program segment where shared resources are accessed.

Explain Circular Dependencies. Circular Dependencies: To know the problem of circular dependencies consider a file server which uses a timeserver to acquire the current

Q. Illustrate Minimization of Gates? The generalization of Boolean expression is much useful for combinational circuit design. The subsequent three techniques are used for this

The Need Of Parallel Computation With the advancement of computer science (CS), computational speed of the processors has also improved many a time. Moreover, there is certain

Examples of artificial neural networks: Now here as an example consider a ANN that has been trained to learn the following rule categorising the brightness of 2x2 black and wh

The reason is, LINQ is used with C# or other programming languages, which needs all the variables to be declared first. From clause of LINQ query just describes the range or condit

Q. Explain working of Direct Memory Access? In both programmed I/O and interrupt-driven processor is busy with executing input/output instructions and I/O transfer rate is limi