Critical path analysis, Computer Engineering

  1. Given the information provided in Table 1:
    1. Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool);
    2. Prepare a table of the possible activity paths and identify the critical path;
    3. Assume that adding an additional person to the project allows the project manager to reduce any task under PM control that is 4 or more days long by one day (tasks P, Q, and R are external and cannot be changed). How does this affect the critical path, and what is the duration of the project with the added resource?

Important Note:  Be sure to take into consideration any special dependencies indicated in the chart (e.g., start-to-start, finish-to-finish) when calculating durations, slack, critical path, etc.  The normal dependency unless otherwise stated is finish-to-start. If there is a delay between two activities, it is shown as a plus or minus offset.  For example, a start-to-start + 5 dependency means the dependent task is planned to start 5 days after the start of the predecessor task.  Any special dependencies shown only apply to the immediate task listed to the left, not to the other tasks in the list.

Table.  Desktop Installation Project

Activity

Description

Estimated Duration (Days)

Predecessor

A

Determine workstation applications

5

-

B

Determine hardware specifications

5

A

C

Determine image configurations

3

B

D

Purchase evaluation workstation

5

B

E

Purchase workstation software

5

C

F

Create image

2

D, E

G

Test image

2

F

H

Customer acceptance testing of image

3

G

I

Prepare purchase order

3

A, B, H (Finish to Finish)

J

Acquire workstations

8

I

K

Install image on workstations

8

J

L

Install workstations on site

6

Q, K (Start to Start + 4)

M

Connect workstations to network

6

P, L (Start to Start +2)

N

Test workstations

6

M (Start to Start +2)

O

Prepare closeout report

3

N

P

Test network connections

6

B

Q

Install furniture

10

R

R

Acquire furniture

16

B

Posted Date: 3/19/2013 3:01:32 AM | Location : United States







Related Discussions:- Critical path analysis, Assignment Help, Ask Question on Critical path analysis, Get Answer, Expert's Help, Critical path analysis Discussions

Write discussion on Critical path analysis
Your posts are moderated
Related Questions
Q. When an object travels with constant velocity does its average velocity during any time interval differ from its instantaneous velocity at any instant? Answer:- No It i

Q. Illustrate Arithmetic shifts with example? Arithmetic shifts ARITHMETIC SHIFT LEFT and ARITHMETIC SHIFT RIGHT are same as LOGICAL SHIFT LEFT and LOGICAL SHIFT RIGHTexcept th

The year is 2199. For many generations, the robotic Cyleth have faithfully served humanity. However, under the direction of the computerized superintelligence Skyweb, they have tur

Objectives After going through this unit, you should be able to: Describe the diffrent criteria on which classification of parallel computers are based; Examine the

Q. Explain Basic working of Mainframes? Mainframe computers are normally 32-bit machines or higher. These are suited to large organizations, to manage high volume applications.

Q. Illustrate Clock signals of clock pulse generator? Synchronization in a sequential circuit is attained by a clock pulse generator that gives continuous clock pulse.  Figure

find the minimum total number of shelves including the loading process

Classify computer systems according to capacity. How they are different from computers according to the classification of technology. Provide comparative study also.

In a national transmission system, the characteristic impedances of the 4-wire circuit and the 2-wire circuit are 1200 ? and 1000 ? respectively. The average phase velocity of the

Define the Pulse-Triggered (Master-Slave) Flip-flops? The term pulse-triggered signify that data are entered into the flip-flop on the rising edge of the clock pulse, though th