Critical path analysis, Computer Engineering

  1. Given the information provided in Table 1:
    1. Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool);
    2. Prepare a table of the possible activity paths and identify the critical path;
    3. Assume that adding an additional person to the project allows the project manager to reduce any task under PM control that is 4 or more days long by one day (tasks P, Q, and R are external and cannot be changed). How does this affect the critical path, and what is the duration of the project with the added resource?

Important Note:  Be sure to take into consideration any special dependencies indicated in the chart (e.g., start-to-start, finish-to-finish) when calculating durations, slack, critical path, etc.  The normal dependency unless otherwise stated is finish-to-start. If there is a delay between two activities, it is shown as a plus or minus offset.  For example, a start-to-start + 5 dependency means the dependent task is planned to start 5 days after the start of the predecessor task.  Any special dependencies shown only apply to the immediate task listed to the left, not to the other tasks in the list.

Table.  Desktop Installation Project

Activity

Description

Estimated Duration (Days)

Predecessor

A

Determine workstation applications

5

-

B

Determine hardware specifications

5

A

C

Determine image configurations

3

B

D

Purchase evaluation workstation

5

B

E

Purchase workstation software

5

C

F

Create image

2

D, E

G

Test image

2

F

H

Customer acceptance testing of image

3

G

I

Prepare purchase order

3

A, B, H (Finish to Finish)

J

Acquire workstations

8

I

K

Install image on workstations

8

J

L

Install workstations on site

6

Q, K (Start to Start + 4)

M

Connect workstations to network

6

P, L (Start to Start +2)

N

Test workstations

6

M (Start to Start +2)

O

Prepare closeout report

3

N

P

Test network connections

6

B

Q

Install furniture

10

R

R

Acquire furniture

16

B

Posted Date: 3/19/2013 3:01:32 AM | Location : United States







Related Discussions:- Critical path analysis, Assignment Help, Ask Question on Critical path analysis, Get Answer, Expert's Help, Critical path analysis Discussions

Write discussion on Critical path analysis
Your posts are moderated
Related Questions
Illustrate the following list of consideration of laptop computers The following is a list for consideration: -  The processor must consume as little power as possible thus

Q. Program for interchanging the values of two Memory locations? Program for interchanging the values of two Memory locations  ; input: Two memory variables of same size:

Explain the term- Signals -  Signals are used for communication between components -  Signals can be seen as real, physical signals -  Some delay should be incurred in a

(a) What is Grid computing? (b) What are the key distinctions between conventional distributed computing and Grid computing? (b) Describe how five features of Grid Computi

What is a Spool request? Spool requests are formed during dialog or background processing and placed in the spool database with information about the printer and print format.

Explain the Main characteristics of semiconductor memory Memory, with regard to computers, most commonly signifies to semiconductor devices whose contents can be accessed (whic

Specify the default alignment for the following field types: 'D' - Left, 'F'-Right, 'N'-Left, 'I'-Right, 'T'-Left.

Explain FIFO Page replacement algorithm. FIFO policy: This policy only removes pages in the order they entered in the main memory. By using this policy we simply eliminate a

Currently microcontrollers are embedded within most products, typical uses are in Camera's for auto focus and display drivers, Laser printers to compute fonts and control printing.

Can you give an example of when it would be appropriate to use a web service as opposed to a non-serviced .NET component? A web service has the following characteristics:  1