Critical path analysis, Computer Engineering

  1. Given the information provided in Table 1:
    1. Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool);
    2. Prepare a table of the possible activity paths and identify the critical path;
    3. Assume that adding an additional person to the project allows the project manager to reduce any task under PM control that is 4 or more days long by one day (tasks P, Q, and R are external and cannot be changed). How does this affect the critical path, and what is the duration of the project with the added resource?

Important Note:  Be sure to take into consideration any special dependencies indicated in the chart (e.g., start-to-start, finish-to-finish) when calculating durations, slack, critical path, etc.  The normal dependency unless otherwise stated is finish-to-start. If there is a delay between two activities, it is shown as a plus or minus offset.  For example, a start-to-start + 5 dependency means the dependent task is planned to start 5 days after the start of the predecessor task.  Any special dependencies shown only apply to the immediate task listed to the left, not to the other tasks in the list.

Table.  Desktop Installation Project

Activity

Description

Estimated Duration (Days)

Predecessor

A

Determine workstation applications

5

-

B

Determine hardware specifications

5

A

C

Determine image configurations

3

B

D

Purchase evaluation workstation

5

B

E

Purchase workstation software

5

C

F

Create image

2

D, E

G

Test image

2

F

H

Customer acceptance testing of image

3

G

I

Prepare purchase order

3

A, B, H (Finish to Finish)

J

Acquire workstations

8

I

K

Install image on workstations

8

J

L

Install workstations on site

6

Q, K (Start to Start + 4)

M

Connect workstations to network

6

P, L (Start to Start +2)

N

Test workstations

6

M (Start to Start +2)

O

Prepare closeout report

3

N

P

Test network connections

6

B

Q

Install furniture

10

R

R

Acquire furniture

16

B

Posted Date: 3/19/2013 3:01:32 AM | Location : United States







Related Discussions:- Critical path analysis, Assignment Help, Ask Question on Critical path analysis, Get Answer, Expert's Help, Critical path analysis Discussions

Write discussion on Critical path analysis
Your posts are moderated
Related Questions
What is the protocol used by SAP Gateway process? The SAP Gateway method communicates with the clients based on the TCP/IP Protocol.

What is page fault? Its types? Page fault refers to the situation of not having a page in the major memory when any process references it. There are two kinds of page fault :

The general method for constructing the parameters of the RSA cryptosystem can be described as follows: Select two primes p and q Let N = pq and determine ∅ (N) = (p - 1

Determine the Framed data including a parity bit   For illustration when even parity is chosen, parity bit is transmitted with a value of 0 if the number of preceding

Conclusion - artificial intelligence : If we can determine what the exactly state of the world will be after an agent's action, so we can say the environment is deterministic.

what are the different techniques of biasing a transistor?

What is mother board? Mother Board is a main system printed circuit board which having the processor. It will occupy an unacceptably large amount of space on the board.

What are threaded binary trees? A Threaded Binary Tree is a binary tree in which each node that does not have a right child has a THREAD (in real sense, a link) to its INORDER

Instruction Cycle The instruction cycle consists of a series of steps needed for the implementation of an instruction in a program. A typical instruction in a program is descri

This unit starts by discussing the importance of involving users in the interaction design process, explaining the reasons why user involvement can be useful, the different degrees