Critical path analysis, Computer Engineering

  1. Given the information provided in Table 1:
    1. Prepare an Activity on the Node (AON) Network Diagram ( I recommend you  use MS Project or any drawing tool);
    2. Prepare a table of the possible activity paths and identify the critical path;
    3. Assume that adding an additional person to the project allows the project manager to reduce any task under PM control that is 4 or more days long by one day (tasks P, Q, and R are external and cannot be changed). How does this affect the critical path, and what is the duration of the project with the added resource?

Important Note:  Be sure to take into consideration any special dependencies indicated in the chart (e.g., start-to-start, finish-to-finish) when calculating durations, slack, critical path, etc.  The normal dependency unless otherwise stated is finish-to-start. If there is a delay between two activities, it is shown as a plus or minus offset.  For example, a start-to-start + 5 dependency means the dependent task is planned to start 5 days after the start of the predecessor task.  Any special dependencies shown only apply to the immediate task listed to the left, not to the other tasks in the list.

Table.  Desktop Installation Project

Activity

Description

Estimated Duration (Days)

Predecessor

A

Determine workstation applications

5

-

B

Determine hardware specifications

5

A

C

Determine image configurations

3

B

D

Purchase evaluation workstation

5

B

E

Purchase workstation software

5

C

F

Create image

2

D, E

G

Test image

2

F

H

Customer acceptance testing of image

3

G

I

Prepare purchase order

3

A, B, H (Finish to Finish)

J

Acquire workstations

8

I

K

Install image on workstations

8

J

L

Install workstations on site

6

Q, K (Start to Start + 4)

M

Connect workstations to network

6

P, L (Start to Start +2)

N

Test workstations

6

M (Start to Start +2)

O

Prepare closeout report

3

N

P

Test network connections

6

B

Q

Install furniture

10

R

R

Acquire furniture

16

B

Posted Date: 3/19/2013 3:01:32 AM | Location : United States







Related Discussions:- Critical path analysis, Assignment Help, Ask Question on Critical path analysis, Get Answer, Expert's Help, Critical path analysis Discussions

Write discussion on Critical path analysis
Your posts are moderated
Related Questions
What is the application of E-Commerce in Home Shopping? Application of E-Commerce in Home Shopping: Television broadcast of goods for purchase sent it directly to a viewe

Q. Instruction Issue degree in superscalar processing? The major concept in superscalar processing is how many instructions we are able to issue per cycle. If we are able to is

Describe the Hardwired control method for generating the control signals Hard-wired control can be explained as sequential logic circuit that generates particular sequences of

It takes away two constraints which were holding back Web developments: 1. Dependence on a one, inflexible document type (HTML) which was being much abused for tasks it was neve

Time synchronization is necessary in? Time synchronization is essential in TDM.

is a technique of temporarily removing inactive programs from the memory of computer system? Swapping is a technique of temporarily eliminating inactive programs from the memor

a program to find the area under the curve y = f(x) between x = a and x = b, integrate y = f(x) between the limits of a and b. The area under a curve between two points can be foun

With the increasing use of more and higher level languages manufacturers had offered more powerful instructions to support them. It was claimed that a stronger instruction set will

In what way the protection fault handler concludes? After finishing the implementation of the fault handler, it sets the change and protection bits and clears the copy on write

Explain Common Control. Common Control: Those systems wherein the control subsystem is outside the switching network are termed as common control switching system. Therefore,