Cpm-pert network analysis problem, Computer Networking

Solve the following CPM/PERT Network Analysis problem:

Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 27 days or less.

 

Time Estimates (Days)

Activity

a

m

b

1

5

8

15

2

7

10

12

3

3

5

6

4

1

3

6

5

4

6

7

6

3

3

3

7

3

4

6

1838_CPMPERT Network Analysis.png

Posted Date: 2/28/2013 2:34:48 AM | Location : United States







Related Discussions:- Cpm-pert network analysis problem, Assignment Help, Ask Question on Cpm-pert network analysis problem, Get Answer, Expert's Help, Cpm-pert network analysis problem Discussions

Write discussion on Cpm-pert network analysis problem
Your posts are moderated
Related Questions
Line Layer The line layer provides the synchronization multiplexer, multiplexing and automatic  protection switching for the layer . primary  concerned with the  reliable trans

Q. What is network layer of osi model? - Describe end-to-end delivery of packets. - Defines logical addressing thus that any endpoint can be identified. - Defines how ro

Determine the task which should intranet require Intranet to work smoothly, the following tasks should be properly synchronised: All computers connected together in a n

Explain about the Switches LAN switches are an expansion of the method in LAN bridging, which controls data flow, handles transmission errors, gives physical addressing, and ma

Computer Networks A computer  networks  can be defined as set of computer that  interact  among  the individual  computers sharing  resources or information. Reference models

Fat tree It is a modified version of the tree network. In this group the bandwidth of edge (or the connecting wire among nodes) increases towards the root. It is a more practic

Simplicity The advantage of this approach is the simplicity  of receiver buffering. The  receiver need not  buffer out of  order packets the sender must maintain the upper an

The Network layer is used to route physical data to the destination point, it decides the actual path from where data travels to destination point. The network layer supports both

What is the implication of increasing and decreasing subnet Bits?

Satellite Radio Channels A communication  satellite links two or more  earth  microwave transmitter receiver, know  as ground  stations. The satellite receives transmission on