Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States

Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
Activity Based Costing or ABC Absorption costing shows to be relatively straightforward way of adding overhead costs to units of production utilizing, more often than not, a v

The Integrated Management Project is to be based on an organisation, a strategic business unit, or profit centre that has good potential for growth and development. The brief is to

You have recently graduated from VU and are now working for a small accounting firm. The firm recently purchases MYOB software for internal use. Upon learning that you had learnt M

Importance of Variance Analysis Variance analysis is aimed at getting practical pointers to the purposes of off-the -standard performance hence management can improve operatio

Critical Thinking about Cost Flow It is simple to overlook an important aspect of cost flow within a manufacturing operation. If you see that have taken note of an important co

#ques Case Study Electron Control, Inc., sells voltage regulators to other manufacturers, who then customize and distribute the products to quality assurance labs for

In January, 2008, Sanford Corporation purchased a patent for a new product for $1,200,000. The patent was valid for fifteen years but it was estimated to have a useful life of ten

Determine Equivalent Units of the Product Let assume there are 4,000 units of a product in ending inventory out of that 60 percent are fully complete whereas the remaining are

Capability Maturity Model Integration (CMMI) is a process development approach that gives organizations with the essential elements of effective processes. It can be used to gui