Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
Which of the four types of costs would include a CEO's salary? A. Unit-Level B. Batch-Level C. Product Sustaining D. Facility Sustaining

(a) Calculate Mexico's producer surplus and consumer surplus in autarky. (b) Calculate the number of Mexican imports with as well as without the Tarriff. (c) Calculate Mexico

Assume that Banc One receives a primary deposit of $1 million. The bank must keep reserves of 20 percent against its deposits. Prepare a simple balance sheet of assets and liabilit

tell me about debentures

A Government issued a number of index-linked bonds on 1 June 2000 which were redeemed on 1 June 2002.  Each bond had a nominal coupon rate of 3% per annum, payable half yearly in a

Labour Costs and Overhead costs Labour Costs Labour costs can be indirect or direct labour costs. Direct labour cost refers to wages paid to workers who such are directly

Shubenacadie Inc. is currently considering a project with a 5-year life that it believes has the potential to return the company to profitability. Based on the results from a marke

diff between cost estimation and cost accounting

Your client has asked you to evaluate an investment project for her using what you have learned in school regarding the net present value method. The project will run for eight yea

Small Steps sells step stools. Their budget information is shown below. selling price: $40 per stool Variable expense:$30 per stool Fixed Expense:$24,000 use the above inform