Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
LIMITATIONS OF COST ACCOUNTING Cost Accounting similar to additional branches of accountancy is not an precise science although is an art which was developed throughout theorie

Comparison between Marginal Costing and Absorption Costing There are accountants who favour all costing method. Arguments in favour about absorption costing are specified a

Approach in Cost Accounting Cost accounting is based on the framework or concept of cost centers that is all the costs incurred throughout the production process contain to be

Question The statements of comprehensive income for three entities for the year ended 30 September 2009 are presented below: SOT PB UV

Relevant Costs and Decision-Making The relevance of costs will depend upon the purpose for that they are being utilized. Relevance is related to future decisions. The relevanc

Labour Variances From our basic data, we can calculate the labour variances as given as: i. Labour Rate Variance = (AH x AR) - (AH  x SR)

1. Single product or single mix of products 2. Variable cost, fixed cost and selling price are constant 3. The level of production will equal the level of sales Example:

Stages of Implementation of Zero Based Budgeting 1. Definition of decision package. It is the comprehensive description of the organizations activities or functions.

Hello, I''m currently doing a research on a company and planning an Activity Based Costing system since the company is using Traditional Costing system to allocate the overhead to

Determine Cost per Unit By Using Marginal and Absorption Costing The given information was extracted from the book of a company for the year ended on date 31/12/2001. Outpu