Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
Time Rate System - Labour Remuneration It may be a high day rate or a flat time rate. Under flat time rate, all worker is paid for the time spend without considering the vol

This task involves the recording of non-current asset information in the general (nominal, main) ledger and other non-current asset matters. You are assisting in preparing the a

Single Limiting Factor Where a single limiting factor exists for the decision making sequence may be implemented given as:- - Compute the contribution per unit of limiting

Tyler's Consulting Company has purchased a new $15,000 copier. This overhead cost will be shared by the purchasing, accounting, and information technology departments since those a

Standards and Budgets Budgets like you recall from the previous section, are simply plans for expected future performance expressed in quantified monetary terms. Therefore the

responsibility of director of finance and logistics

what is cost

Advantages and Disadvantages of Group Bonus Plan Benefits associated along with group bonus schemes involve i. It encourages teamwork and cooperation among workers ii.

Banana Corporation had the following transactions relating to a patent: January 1, 2010: Purchased patent for $2,000,000. The patent had fifteen years remainnig although Banan

A firm's fixed costs for 0 units of output and its average total cost of producing different output levels are summarized in the table below. Complete the table to find the fixed c