Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
What are the reasons of preparing income statement?

Reasons for Overhead Variances Useful for Control Reasons Overhead variances are essentially a book balancing exercising giving an arithmetic reconciliation between the actual

Bases of Cost Classification These various bases of cost classification are summarized in the diagram underneath as: Here, we will usually refer to either of these ter

Storage and Issue of Material A number of questions are relevant in this control of materials throughout storage and question of materials. These are as: a) Stock control r


SALES REVENUE VARIANCE (SRV) The word 'Sales Variance' is indicated by the expression 'operating profit variance due to sales' by ICMA.  It is described as 'the difference betw

Pauline's Pastry Shop decides to remodel its offices this year. As part of the remodeling, Pauline's trades furniture with a cost of $12,000 that had been expensed in the year of p

1.    Provide at least three characteristics of a corporation (in your own words).   2.   The date on which a cash dividend becomes a binding legal obligation is known

MARGINAL COSTING Vs DIRECT COSTING Direct costing is the method where only direct costs are measured while calculating the cost of the product. Indirect costs are met in opposi

Describe the concept of full cost recovery with illustrative examples.