Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
responsibility of director of finance and logistics

what is the classification of cost & how it is done?

Chrome-It, Inc., manufactures special chromed parts made to the order and specifications of the customer.  It has two production departments, stamping and plating, and two service

Q. Given the below information, what is the dollar amount that the LIFO liquidation added to gross margin?   Number of Units Price per Unit

The government of a small South Pacific island is considering whether to allow development of a small but valuable deposit of phosphate rock. Not having the resources to develop an

Igor and Angela were married in 2005, separated in 2011, and divorced recently. At the time of marriage, each had some investments and personal assets. They both worked during the


Direct and Indirect costs Recall such direct costs are costs which can be traced particularly to the end product of the production procedure while indirect costs cannot be so

Role of Cost Accounting in Organization Like part of their jobs, such cost accountants interpret results, and then report them to management and give analysis such assist deci

Prime Essentials Limited is a small private corporation. The owner plans to approach the bank for an additional loan or a line of credit to facilitate expansion. The company bookke