Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Compute prevention costs-appraisal costs-internal failure , Question: A...

Question: At the beginning of the year, Asquith Company Ltd initiated a quality improvement program. The program was successful in reducing scrap and rework costs. To help asse

Labour cost, labour cost related case study with solution

labour cost related case study with solution

Mathematical derivation of eoq, Mathematical Derivation of EOQ Let cos...

Mathematical Derivation of EOQ Let cost per order is represented via Co. it is the cost incurred every instance one order is placed. Let the economic quantity purchase ever

Analysis of prime cost and overhead variances, You are required to conduct ...

You are required to conduct a detailed analysis of all the prime cost and overhead variances. You must create a fictitious company (and a fictitious cost object) which has at least

Purpose of cost estimation, Purpose of Cost Estimation In estimating i...

Purpose of Cost Estimation In estimating it assists the future expenditure as cost prediction like the expenditure will depend upon the cost of the respective activities a)

Standard cost and standard costing, Standard Cost and Standard Costing ...

Standard Cost and Standard Costing To effectively control the costs of a certain organization, we require a yard stick to measure the real performance against. Traditionally,

Calculate the cumulative cash flows, Assume that you are the purchaser of t...

Assume that you are the purchaser of the building at the end of the construction period, and you have paid the developer an amount which gives you a 7% annual return on net revenue

Job costing, XYZ Company is a family-owned bicycle manufacturing company lo...

XYZ Company is a family-owned bicycle manufacturing company located in Stow, Ohio. Until recently,it had maintained slow but steady growth in producing and marketing its only prod

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd