Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions

Build-Rite construction has received favorable publicity from guest appearances on a public TV home improvement program. Public TV programming decisions seem to be unpredictable, s

Tyler's Consulting Company has purchased a new $15,000 copier. This overhead cost will be shared by the purchasing, accounting, and information technology departments since those a


Q. Show the Break-even charts? Refers graphically profit and losses at different levels of sales volume achieved. When sales revenue is greater than total cost it m

Give Annual report project: You will pick a publically trade company to do the analysis on with approval of the professor . the following is an outline of what should be in th

In the beach city of Santa Barbara, California, there are seven bathing suit stores, each with the same schedule of costs and each facing an identical demand curve. Swim N Style is

A job order cost sheet for Lowery Company is shown below Date Direct Materials Direct Labor Manufacturing overhead Beg Bal Jan 1 5,000 6,000 5,100 8 6,000 12 8,000 6,400 25 2,000 2

Place a prepared slide of Trypunosoma under tlic microscope and focus it under low power, You will observe large number of tiny spindle-shaped trypanosomes lying in the plasma alll

how do you calculate estimating cost for the last of the year based on activity during the first half of the year