Cost variance and schedule variance, Cost Accounting

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?

Posted Date: 3/6/2013 4:20:29 AM | Location : United States







Related Discussions:- Cost variance and schedule variance, Assignment Help, Ask Question on Cost variance and schedule variance, Get Answer, Expert's Help, Cost variance and schedule variance Discussions

Write discussion on Cost variance and schedule variance
Your posts are moderated
Related Questions
Tony Allan Inc is a small manufacturer of metal products in Toronto.  The company rents its factory building.  It uses a job order costing system because it has a wide variety of p

Overhead Absorption Absorption of overheads refers to the sharing out of overhead costs to the some cost centers such used the overheads. This is utilized when the overheads c

Why is it important for financial statements and other external reports to be based on generally accepted accounting principles?

Mrs. M. Botham is a sole trader, selling a variety of fashionable clothing materials. Her business year end is 31 December 2011. You have been given the following trial balance

The sale turnover and profit during two period were as following Period 1=Sales Rs.20 Laks, and Profit Rs.2 Laks Period 2=Sales Rs.30 Laks, and Profit Rs.4.Laks Calculate P/V Ratio

Total costs include both variable costs and fixed costs. Variable costs are costs which can beeasily identified or related to a cost per unit or activity level of some kind for exa

Presented below is a list of terms relating to cost behavior, followed by definitions of those terms: a. Rent on a factory building b. Engineering approach c. Fixed cost

Amy earns $35,000 working part time. Consequently, she is not eligible to participate in her employer's retirement plan or health insurance program. Amy's expenses are summarized a

on june 2005 20 units of the product in stock the following is extracted from the companys books direct material-200 per unit,direct labour 150 per unit, variable production overhe

The next year's budget for Benny, Inc., is given below: Product 1 & 2 Sales $945,000 & 688500 Variable costs 459,900 & 297,000 Fixed costs 300