Control and flexibility in contracts, Other Management

Control and Flexibility in Contracts

Contracts form the backbone of project management today. Project management techniques have developed in response to severe pressures such as unfavourable economic factors, inflation, uncertainties in the magnitude and duration of construction projects, and often unpredictable regulatory and environmental requirements. Executive control of a project can therefore be achieved only by controlling the progress of  contracts entered into for the project.

Major projects involving substantial construction are exceptional, one-time or at least infrequent. The popular mode is that you invest in capital works and execute the project through a single entity created for the implementation of the specific project.

The single entity is the project team, which in turn is led by a designated project manager dedicated to the project. This team should be established early in the development of the project concept and be given responsibility for  the  complete  project  life  cycle  from feasibility;  through  schematics, design, and procurement. In this way, managerial unity is established early in the project.

The single entity model can be achieved in three different ways, each way being a contracting mode for an entire project:

1. Award of a single contract (either Lump sum Fixed price or Engineering Procurement Construction (EPC), for the implementation of the project after the basic design of the project is finalised.

2. D-B (Design and Build) mode of contracting 

3. D-B-B (Design, Bid and Build) mode of contracting 

Posted Date: 9/28/2012 2:15:50 AM | Location : United States







Related Discussions:- Control and flexibility in contracts, Assignment Help, Ask Question on Control and flexibility in contracts, Get Answer, Expert's Help, Control and flexibility in contracts Discussions

Write discussion on Control and flexibility in contracts
Your posts are moderated
Related Questions
Types of Reference work: a) The conservative approach is based on the fact that the users should be instructed on how to use books and libraries rather than on delivery of inf

Total Marks – 40 (Note: The information for this question is based on the material contained in Hopkins, Andrew (1999) Managing major hazards: the lessons of the Moura Mine Disast

QUESTION (A) Define learning (B) Playing on a backyard one day, three-year-old Albert is on a swing when a rabbit suddenly appears out of the bushes and startles him. He sli

PERIODICALS PROCUREMENT: We have dealt with the selection of periodicals. Logically, the next step is procurement of the selected periodicals.  Hence,  this section is devoted

Primary Sources These are materials, which are the most authentic and original. They usually take the form of a a monograph, journal article, dissertation, report or a paten

QUESTION 1 Discuss the strategic decision making process. Support your answer with examples from an industry of your choice QUESTION 2 a) What are SBUs and how effectiv

Please quote on 5 case study questions and 6 sub questions

Punctuated Equilibrium Model Connie Gersick's model of group development challenges the traditional forming/norming/storming/performing view of group development. The rese

Question 1 Discuss the various activities carried out by commercial banks these days that are common to clients of both commercial banks and development banks Question 2 What

What are the characteristics of centralised purchasing?