Construction of embankment, Civil Engineering

Construction of Embankment:

The following steps describe embankment construction :

(a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed.

(b) The original ground, if loose, is compacted by loosening the soil, adding water and rolling.

(c) The embankment soil is deposited in layers of about 25 cm loose thickness so as to get a compacted thickness of not higher than 15 cm.

(d) The moisture content in the soil should be brought to the optimum, by adding extra water or allowing the moist soil to aerate.

(e) Rolling is done by a road roller giving sufficient number of passes such that the desired density is achieved.

(f) The alignment, cross-section and levels are controlled by previously set temporary Bench Mark pillars and pegs.

(g) It is a good practice to construct the layers of the embankment also to the final camber/cross-slope of the pavement.

(h) The top 300-500 mm of the embankment, known as the sub-grade, is generally made up with soils which are better than that used in the body of the embankment. The density to which the sub-grade soil is compacted is also higher than in the rest of the embankment.

Posted Date: 1/22/2013 4:31:07 AM | Location : United States







Related Discussions:- Construction of embankment, Assignment Help, Ask Question on Construction of embankment, Get Answer, Expert's Help, Construction of embankment Discussions

Write discussion on Construction of embankment
Your posts are moderated
Related Questions
difference between delievery and suction pipe?

advantage of concrete floor

Problem (a) Briefly explain the concept of wind-driven ventilation and outlines its benefits over mechanical/electrical means of ventilation. (b) Various factors and guidel

Q. Which type of pile cap transfers loads equally to piles, flexible pile cap orrigid pile cap? Loads from columns transferring to pile cap persuade tensile forces at the bott

A concrete wall form tie with an ultimate strength capacity of 2,400-lbs is designed for use in a concrete wall form with an 18-in center to center spacing. During formwork inspect

Sketch a curve showing the relation among dry density and moisture content for Standard Proctor test and indicate the salient features of the curve. Describe why soils are compacte

Example for Productivity Analysis and Improvement An excavator with a bucket capacity of 3-yd 3 has a standard production rate of 2,160-yd 3 for an 8-hour day.  The job site

batching by volume

haw do you salve a supple supported beam with a spring balance

what are the uses of retaining wall?!