Construction of embankment, Civil Engineering

Construction of Embankment:

The following steps describe embankment construction :

(a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed.

(b) The original ground, if loose, is compacted by loosening the soil, adding water and rolling.

(c) The embankment soil is deposited in layers of about 25 cm loose thickness so as to get a compacted thickness of not higher than 15 cm.

(d) The moisture content in the soil should be brought to the optimum, by adding extra water or allowing the moist soil to aerate.

(e) Rolling is done by a road roller giving sufficient number of passes such that the desired density is achieved.

(f) The alignment, cross-section and levels are controlled by previously set temporary Bench Mark pillars and pegs.

(g) It is a good practice to construct the layers of the embankment also to the final camber/cross-slope of the pavement.

(h) The top 300-500 mm of the embankment, known as the sub-grade, is generally made up with soils which are better than that used in the body of the embankment. The density to which the sub-grade soil is compacted is also higher than in the rest of the embankment.

Posted Date: 1/22/2013 4:31:07 AM | Location : United States







Related Discussions:- Construction of embankment, Assignment Help, Ask Question on Construction of embankment, Get Answer, Expert's Help, Construction of embankment Discussions

Write discussion on Construction of embankment
Your posts are moderated
Related Questions

derive the expression for stress in arbitrary plane in a body subjected to bi axial stress condition

Q. Afflux in rivers with non scourable bed? Afflux is defined as rise of flood level of the river upstream of a bridge as a result of the obstruction to natural flow caused by

find the pressure head at 2-2 if the rate of flow in pipe is 0.36m^3/s

What are beneficial points of assigning central pier and abutment as fixed piers ?

You are aware that construction of any type of structure takes sometime. Pressure due to the building will be applied gradually and not instantaneously. Excavation for the construc

Design a sewer network

Concrete surround is generally adopted for rigid drainage pipes to resist high traffic loads (for instance under shallow covers) and to allow for using pipes with lower strength. F

A trapezoidal masonry retaining wall 1 m wide at top and 3 m wide at its bottom is 4 m high. The vertical face is retaining soil (φ = 30°) at a surcharge angle of 20° with the hori

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate