Concrete cracking, Civil Engineering

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.

Posted Date: 2/19/2013 2:55:35 AM | Location : United States







Related Discussions:- Concrete cracking, Assignment Help, Ask Question on Concrete cracking, Get Answer, Expert's Help, Concrete cracking Discussions

Write discussion on Concrete cracking
Your posts are moderated
Related Questions
In order to make wise investments in a marketplace experiencing enhancing levels of risk, companies are turning to feasibility studies to verify if they should offer new products,

Determine the Depth of Exploration The depth of exploration depends on the following factors: i) Size, type of the structure and loading intensity. ii) Design considerati

Quality Control in Flexible Pavements: The quality control needed for Flexible Pavements covers the following tests : (a) Density and Moisture content of sub-grade. (b)

Question What is key meaning of excellence of bentonite slurry in construction of diaphragm walls? Answer Quality of slurry plays a significant role in quality of di

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla


Q. Illustrate Weld Failures in Track? These are failures occurring to defects in welding the joint. These defects are either because of improper composition of thermit metal or

Question Is it resourceful that engineers rely solely on Hiley's formula in designing of H-piles? Answer About 90 percent of H-piles accept Hiley's formula for desig

Explain Rebound Hammer - Underwater non-destructive testing? The underwater rebound hammer system is a surface hardness tester which can be employed to acquire a general condit

What do you understand by Pressure line If we determine the locations of resultant force at various sections of a pre-stressed beam, as in Example, we can draw a curve showing