Concrete cracking, Civil Engineering

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.

Posted Date: 2/19/2013 2:55:35 AM | Location : United States







Related Discussions:- Concrete cracking, Assignment Help, Ask Question on Concrete cracking, Get Answer, Expert's Help, Concrete cracking Discussions

Write discussion on Concrete cracking
Your posts are moderated
Related Questions

High temperature in laying bituminous pavement Generally bituminous materials are also broadly categorized into two types viz bitumen McAdamsand hot-rolled asphalts. At the ti

Example of Foundation depth and arrangement: For example, if the maximum discharge of a river is 1000 cu m per sec, and the silt factor is 0.60, the maximum scour depth is :

Q. Discontinuity of joint – position of bearing? Expansion joints in a bridge structures cater for movements inlongitudinal, transverse, vertical and rotational forms. Layout a

Q. Velocity distribution and flow formulae? Variation in velocity along a vertical in channel cross section is known to follow logarithmic distribution, maximum velocity being

design a 3-meter cantilever slab to carry a uniform total dead load of 8.2KN/m^2 and a concentrated live load at the free end of 30 KN/m. f''c=28Mpa fy=420Mpa.

calculate the support reaction as shown in figure;

Explain the Dynamic or Vibration Tests Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and

1. Domes - You are a construction manager in the UAE in charge of a project that involves constructing domes.  Discuss briefly, giving examples, a range of different types of dome

Question It should be necessary that raking piles of a bridge abutment be placed under an embankment ? Answer For a bridge abutment to be supported on raking piles with dive