Concrete cracking, Civil Engineering

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.

Posted Date: 2/19/2013 2:55:35 AM | Location : United States







Related Discussions:- Concrete cracking, Assignment Help, Ask Question on Concrete cracking, Get Answer, Expert's Help, Concrete cracking Discussions

Write discussion on Concrete cracking
Your posts are moderated
Related Questions
Example. With a surveyor compass the angles observed in traversing the lines AB, BC, CD, DE and EF are  as. Compute the included angles and indicate them in a neat sketch.

what is the purpose of 6mm ms sheet for staining in various conditions at inner &outer of well

Ground settlement occurs when pipe-jacking machine enters mixed ground with soils and boulders? The rate of cutting through soils is faster than cutting through boulders for pi

Determine the types of untensioned Reinforcement  Reinforcement used as untensioned steel should be one of the following types : (a)  Mild steel and medium tensile steel bar

Q. Show the Functions of wet wells? Wetwells are designed to store provisionallysewage/water before it is pumped out. They are generally provided for sewage and stormwater pump

Define Vertical Curves  - Transportation 1) Vertical curves are used to change the grade of a highway. 2) Most vertical curves take the shape of an equal-tangent parabola.

free body diagram of a walk bridge

Q. How can you design Side Slope of bank? Angle of bank should be flatter than angle of repose of pitching material. Angle of repose of sand is 2:1 while that of stone is about

Question In designig of watermains, how to decide usage of double air valves and single air valves ? Answer Single air control device let squeezing air out of p

Explain the Primary Treatment for Wastewater Primary Treatment: to remove the pollutants that floats or settles. Typically 60% of suspended solids and 35% of BOD 5 are removed