Concrete cracking, Civil Engineering

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.

Posted Date: 2/19/2013 2:55:35 AM | Location : United States







Related Discussions:- Concrete cracking, Assignment Help, Ask Question on Concrete cracking, Get Answer, Expert's Help, Concrete cracking Discussions

Write discussion on Concrete cracking
Your posts are moderated
Related Questions
Define Design Aspects of Pot Bearing? Basic elements of a POT bearing are: - POT or a shallow cylinder - An elastomeric pad - A set of sealing rings - A piston P

Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3.   Design flow (Q) = 6.3 MGD = 6.3x106 gpd =

Q. Explain about Best hydraulic section? The best hydraulic section of an open channel is considered by provision of maximum discharge with a given cross sectional area. Chann


Ask questapplication of physics in civil engineering ion #Minimum 100 words accepted#


State the term - constant eccentricity A pre-stressed concrete beam has a width of 300 mm and an overall depth of 450 mm. The permissible stresses in tension and compression du

metal sizes required and adopted question #Minimum 100 words accepted#

who to we calculate the RL at first point.

Mechanism of taking up loads for concrete paving blocks  Paving for concrete blocks comprises closely packed paving blocks in pre-determined patterns and tiny joint spaces bet