Concrete cracking, Civil Engineering

Attached information shows construction details of a water tank. The slab was poured in one pour and the walls (incl. Baffles) were poured in two even sections. Forms were stripped 3 days after pouring walls. The weather on these pour days was not extreme. The difference between the minimum to maximum temperatures were only 5 or 6 degrees. The cracking was identified through most holes allowed for formwork ties perpendicular to the wall thickness.

The cracks were in vertical direction originating from the base to nearly half way of the height of the external walls. The cracks appear to be wider near the base and narrowing with the height. The cracks appeared within the first week after the concrete placement, first noticed as soon as the formwork was removed.

The following are events:

1. Tank Base poured (Temperature min 9.3, max 16.5°C)

2. North side of structure poured (including north wall, ½ east wall, ½ west wall & intermediate baffle) (Temperature min 17.4°C, max 30.6°C)

3. Formwork stripped (first sign of cracking through formwork tie bars)

4. South side of structure poured (including south wall, ½ east wall, ½ west wall, intermediate baffle & overflow weir) (Temperature min 14.1°C, max 22.5° C)

5. Formwork stripped (similar cracks to first pour noticed)

6. Water testing commenced and leakages detected.

Photograph of the cracks in concrete and water leakage are shown in pictures attached.

Drawings are also attached.

Your assignment is to identify the type of cracks and convince the reader of your report the conclusions that you have reached in your report.

(1) List all the possible type of reasons that may have caused these cracks

(2) Discuss the reasons for and against each type of cracks mentioned above;

(3) Arrive at a conclusion backed by logical arguments that the type of crack you consider is the most likely cause of the cracks found.

(4) Present calculations to back up your argument if possible.

(5) Having identified the type of cracks above, now discuss the how these types of cracks can be avoided in future in the same type of situations.

Posted Date: 2/19/2013 2:55:35 AM | Location : United States

Related Discussions:- Concrete cracking, Assignment Help, Ask Question on Concrete cracking, Get Answer, Expert's Help, Concrete cracking Discussions

Write discussion on Concrete cracking
Your posts are moderated
Related Questions

slabs and beam formwork

Question What is function of longitudinal joints in concrete road pavements ? Answer A longitudinal joint consists of a tie bar located at mid-depth of a concrete pav

Define the term - pre- tensioning It is a method of prestressing in which tendons are placed, inside ducts or passages provided in concrete, after concrete gains sufficient str

Q. Explain P Trap? Trap is a depressed or bent sanitary fittings which always remains full of water it is water seal. Its functions are to prevent passage of foul air or gas

Binomial Distribution - exact probability: For the binomial distribution having n = 10, y = 0.4, find p (X ≤ 4) using equations and verify that equation gives a better approxi

Question In designing of service reservoirs, how should reservoir floors be designed to avoid leakage of water because of seasonal and shrinkage movements ? Answer I

A load of 3000 kN is being taken by a square column footing. Side of the column is 3 m, footing rests on a silty soil with a Poisson's ratio = 0.3. Modulus of elasticity of the soi

Explain is Vadose Zone - Ground water In an unconfined aquifer, it is the area located above the water table and aquifer, where the soil and rock are not saturated with water.