Carry out resource levelling for equipment resource, Operation Research

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)

Posted Date: 3/13/2013 7:35:47 AM | Location : United States







Related Discussions:- Carry out resource levelling for equipment resource, Assignment Help, Ask Question on Carry out resource levelling for equipment resource, Get Answer, Expert's Help, Carry out resource levelling for equipment resource Discussions

Write discussion on Carry out resource levelling for equipment resource
Your posts are moderated
Related Questions
if the year or age is given from 0 how to solve then?

A PAPER MILL PRODUCES TWO GRADES OF PAPER VIZ, X AND Y. BECAUSE OF RAW MATERIALS RESTRICTIONS, IT CANNOT PRODUCE MORE THAN 400 TONS OF GRADE X PAPER AND 300 TONS OF GRADE Y PAPER I

Normal 0 false false false EN-IN X-NONE X-NONE

Non-Documentary Sources: On the other hand, non-documentary sources are institutional and human resources, both of which are important links in the information-transfer chain.

undertake the proposed research investigation in accordance with the agreed specification and procedures

A certain type of machine breaks down at an average rate of 5/hour. the break down is in accordance with Poisson process.cost of idle machine hour is $15/hour. 2 repairmen Peter an

Royce A. Singleton and Bruce C. Straits have said that scientific social research consists of the process of formulating and seeking answers to question about the social wor

This method is more  systematic and orderly than least cost method. Here penalties for each column and row of the transportation table are determined, and the row  or  column with

What is the role of decision making in OR

Choose a publicly traded company (NYSE, AMX, or OTC) that interests you. If you don't know how to choose a company, think of IBM, DELL computer, Nike, Apple computer, GM, Ford, Nok