Carry out resource levelling for equipment resource, Operation Research

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)

Posted Date: 3/13/2013 7:35:47 AM | Location : United States







Related Discussions:- Carry out resource levelling for equipment resource, Assignment Help, Ask Question on Carry out resource levelling for equipment resource, Get Answer, Expert's Help, Carry out resource levelling for equipment resource Discussions

Write discussion on Carry out resource levelling for equipment resource
Your posts are moderated
Related Questions
User Groups: The next step would be to identify more specifically the potential user groups. This may be done on the basis of interviews, questionnaires, study of organisation


a)Draw a network for the project. b)Determine the critical path. Activity Duration Activity Duration 1-2 15 5-10 22 1-3 13 6-9 33 1-4 1

Normal 0 false false false EN-IN X-NONE X-NONE

Operation research is only a Tool of Analysis and Not the Complete Decision making Process: It should always be kept in mind that O. R alone cannot make the final decision . it

can u send me some assigment problems

Problem What are important objectives of strategic management and the causes for failure t of strategic management Objectives To keep pace with the changing business e

Question A - Linear Programming is most widely used technique for large number of applications in business industry as well as in various other fields. Describe in brief the steps

. Explain in brief the phases of Operations Research. 5 +5 = 10 marks (200 - 250 words each) Q3. Solve the following Linear Programming Problem using Simple method. Maximize Z= 3

EXPLAIN THE CONCEPT OF DUALITY IN LPP THROUGH A LIFE SITUATION