Calculate the total labor cost per cubic yard, Civil Engineering

Assignment Help:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placement is to use a crane and a 2-cubic-yard bucket. To perform the task efficiently, five Union laborers are needed - one at the concrete truck, three at the point of placement, and one on the portable internal vibrator. The wage rate for laborers is $22.00/hr (Union overtime rate is 1.5 times the wage rate after 8-hour day). Time needed for the operation is: Setup: 15-min; Cycle time consists of Load = 3-min., plus Swing, dump and return = 6-min. which allows a total cycle time = 9-min; Demobilize operation, 10-min. Supervision is done by the superintendent. Allow a 10% factor for inefficiencies during the cycle time. Crane rental cost is $1,800 per 8-hr day. The total labor cost per cubic yard for the concrete crane placement of the 90 cubic yards is most nearly:

Solution:

Identify (by underlining) relevant cost items and calculate summary quantities.

No. of cycles 90-CY/2-CY/Bucket = 45 cycles

Total cycle time 45-cycles x 9-min/cycle = 405 min

Inefficiency(labor,delays,etc.)10%of cycle time = 41-min

Setup and demobilize: Sub-total = 25 min

Total operation time: 405 + 41 + 25 = 471-min or 7.85-hrs

Amount of time needed (adjusted to workday) = 8 hr Laborers - five for 8 hours at $22.00/hr = $880.00

Total labor cost per 90-yd3 = $880.00

Cost per cubic yard $880/90-yd3 = $9.78/yd3


Related Discussions:- Calculate the total labor cost per cubic yard

Mensuration, My team has to construct a swimming pool at the back of the ho...

My team has to construct a swimming pool at the back of the house. It’s interior dimensions are 10M x 3M and 1M at the shallow end and 2.5M at the deep end. The walls and the bas

Principal stresses and strains, Principal Stresses and Strains: Princi...

Principal Stresses and Strains: Principal Stresses and Strains is a very important link in the analysis of solids so as to make sure safe design of different components of str

Principles and Practices of Management, How Will You Influence People to St...

How Will You Influence People to Strive Willingly for Group Objectives in Your Organization (Target Based Industry)? Apply Your Interpersonal Influence Through Communication Proces

Light and rapid rail transit, Light Rail Transit (LRT) Light Rail Tra...

Light Rail Transit (LRT) Light Rail Transit is also known by the name train. LRT can be run on the surface if road space is available (as in Kolkata) or as elevated, with pil

Sea breeze and land breeze, Explain the following: (a) Sea breeze and L...

Explain the following: (a) Sea breeze and Land breeze (b) What is Thermal comfort (c) What is Global wind pattern and Coriolis effect (d) How wind affects the tempe

How do we calculate absolute pressure, Absolute is equivalent to gauge pres...

Absolute is equivalent to gauge pressure plus atmospheric.

Calculate the parameters for setting out curve, Q For a curve of 50, apex ...

Q For a curve of 50, apex angle of 900 and transition length of 60m, calculate the parameters for setting out curve by a Theodolite for TTP, mid point of transition, CTP and a p

Raft and beam foundation, why is weight of raft not considered in structura...

why is weight of raft not considered in structural design of raft and beam

Estimation specification and costing, Estimate the single room of size 3m x...

Estimate the single room of size 3m x 4m x height 3m using individual wall method?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd