Calculate the probable wall thickness of the tank, Mechanical Engineering

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland, Ohio. Beginning in 1940, the tank was operated for many years in what was believed to have been heated oil service. It is unclear as to how many years the tank was not used, but in 1986 it was disassembled by cutting it apart into sections. Using oxy-acetylene torches the "old welds" were left in place as the tank was cut apart and the sections were moved to an Ashland Oil facility near Pittsburgh, Pennsylvania. Using shielded metal arc welding, the tank was reassembled in 1987 and placed in a tank farm with many other similar tanks near the Monongahela River. When reassembled, the tank joints were x-rayed and leak tested. Test results indicated that none of the welds required rework. The reassembled tank was 50 feet high and approximately 130 feet in diameter. A dike was built around the tank that would hold 150 percent of the tank capacity.

The tank was partially filled with diesel fuel in August 1987. On January 2, 1988, during its initial filling to capacity after reconstruction, the tank failed catastrophically creating a tidal wave of oil that sent nearly 4,000,000 gallons of diesel fuel into the Monongahela River causing a major environmental problem. The problem was so severe that the entire water supply for all of South Pittsburgh had to be shutdown for two weeks. In addition to spilling thousands of gallons of oil in the river, the tidal wave of oil from the tank damaged other nearby tanks and structures as well. "A small, uncemented cinderblock shed about 120 feet distant had its walls literally swept away... leaving its roof lying neatly on the slab floor. "

Answer the following questions:

1.  Decide what material composition was most likely used for the tank wall, document the properties of the material and then decide the most likely processing history for the manufacture and construction of the storage tank.  Discuss these issues as the initial paragraph(s) of your report.

2.  Calculate the probable wall thickness of the tank.

3.  If a 3/8" thick plate was used, calculate the exact flaw size that caused the brittle failure of the tank.

4.  Use your calculations as a basis for a one or two paragraph discussion of the tank failure. 

5.  By calculation and design assumptions, determine if any of the following materials could be used for this tank, given the (improbable) assumption that all manufacturing and joining problems are solvable for the particular material.

PMMA 2024-T4

Aluminum Ti-6AL-4V

Aluminum Oxide Glass

Posted Date: 3/21/2013 1:48:53 AM | Location : United States







Related Discussions:- Calculate the probable wall thickness of the tank, Assignment Help, Ask Question on Calculate the probable wall thickness of the tank, Get Answer, Expert's Help, Calculate the probable wall thickness of the tank Discussions

Write discussion on Calculate the probable wall thickness of the tank
Your posts are moderated
Related Questions
Copper Alloys Some alloys of copper are employed in industry for varying causes. Copper forms alloys along with zinc or the brasses, tin or the bronzes, along with tin and pho

In an orthogonal cutting process, following data were taken. Chip length of 80mm was obtained with an uncut chip length of 200mm and the rake angle used was20 degrees and depth of

Q. Basic type of Polymer? Polymer can be divided into three broad divisions: plastics, fibers, and elastomers. Synthetic resins are usually referred to as plastics. Plastic der

The tapered, two-cell beam is subjected to a pure torque of 50,000 in-lb counter clockwise. The length of the beam (normal to the figure) is 100 in. The flange areas are 1 sq in an

TYPES OF ELECTRON BEAM WELDING GUN   Diode (Cathode - anode) Gun : In this gun, the beam shaping electrode and the emitter are both at the same electrical potentials. These

Fluid Friction: Fluid friction manifests when the lubricating fluid is introduced between contact surfaces of the two bodies. If thickness of lubricant or oil between the m

Edge joints: The flanged edge joint is suit- able for plate 1/4 inch or less in thickness and can only sustain light loads. Edge preparation for this joint may be done.

Construction of Railway Line: Earthwork Earthwork in embankment is made up of soil from nearby borrowpits. The soil is deposited in layers of 25 cm and compacted at o

Stone Slab Culverts with Abutments and Piers: Where good quality stone slabs are available like granite slabs, they can be used for superstructure of culverts, with suitable

Applications with Medium Laser Power   Several laser welding applications have recently evolved in this power range of 1 to 10 kW. Because, the laser provides a basis for co