Calculate the probable wall thickness of the tank, Mechanical Engineering

The background for the oil storage tank failure is as follows: the tank involved was a four million gallon circular tank that was built in 1940 for Ashland Oil Company in Cleveland, Ohio. Beginning in 1940, the tank was operated for many years in what was believed to have been heated oil service. It is unclear as to how many years the tank was not used, but in 1986 it was disassembled by cutting it apart into sections. Using oxy-acetylene torches the "old welds" were left in place as the tank was cut apart and the sections were moved to an Ashland Oil facility near Pittsburgh, Pennsylvania. Using shielded metal arc welding, the tank was reassembled in 1987 and placed in a tank farm with many other similar tanks near the Monongahela River. When reassembled, the tank joints were x-rayed and leak tested. Test results indicated that none of the welds required rework. The reassembled tank was 50 feet high and approximately 130 feet in diameter. A dike was built around the tank that would hold 150 percent of the tank capacity.

The tank was partially filled with diesel fuel in August 1987. On January 2, 1988, during its initial filling to capacity after reconstruction, the tank failed catastrophically creating a tidal wave of oil that sent nearly 4,000,000 gallons of diesel fuel into the Monongahela River causing a major environmental problem. The problem was so severe that the entire water supply for all of South Pittsburgh had to be shutdown for two weeks. In addition to spilling thousands of gallons of oil in the river, the tidal wave of oil from the tank damaged other nearby tanks and structures as well. "A small, uncemented cinderblock shed about 120 feet distant had its walls literally swept away... leaving its roof lying neatly on the slab floor. "

Answer the following questions:

1.  Decide what material composition was most likely used for the tank wall, document the properties of the material and then decide the most likely processing history for the manufacture and construction of the storage tank.  Discuss these issues as the initial paragraph(s) of your report.

2.  Calculate the probable wall thickness of the tank.

3.  If a 3/8" thick plate was used, calculate the exact flaw size that caused the brittle failure of the tank.

4.  Use your calculations as a basis for a one or two paragraph discussion of the tank failure. 

5.  By calculation and design assumptions, determine if any of the following materials could be used for this tank, given the (improbable) assumption that all manufacturing and joining problems are solvable for the particular material.

PMMA 2024-T4

Aluminum Ti-6AL-4V

Aluminum Oxide Glass

Posted Date: 3/21/2013 1:48:53 AM | Location : United States







Related Discussions:- Calculate the probable wall thickness of the tank, Assignment Help, Ask Question on Calculate the probable wall thickness of the tank, Get Answer, Expert's Help, Calculate the probable wall thickness of the tank Discussions

Write discussion on Calculate the probable wall thickness of the tank
Your posts are moderated
Related Questions
Motion of connected bodies: Analyze motion of connected bodies that is connected by pulleys. Sol: The given figure shows a light and inextensible string passing over sm

diference between thermal and thermodynamic equallibrim

A 4 cylinder petrol engine operates on the 4-stroke cycle. The bore of each cylinder is 70mm and stroke 100mm. The clearance volume per cylinder is 60cm3. At a speed of 4000rpm, th

Consider the power system as designed below. The duty fluid is water, and has a mass flow 0.75 kg/ s and all piping through which the liquid flows has diameter 1'', while the steam

A long cylinder of radius 2 m hinged at point A is used as an automatic gate. When the water level reaches 15 m the gate automatically opens. Determine the magnitude of the net hyd

Q. Show the Geometric Similarity? When model is required to provide an aid merely for visualisation, scaler reproduction of form is sufficient which is termed Geometric Similar

Explain Clamping Devices A clamp is a device that holds the work piece firmly against the locators provided and also resists all forces generated by the cutting action of

Working of boiler : Water is filled in boiler shell through the feed valve up to 2/3 rd of shell. Water flows down through the down take header by means of descending wa


Calculate the Actual Machining Time Estimate the actual machining time required for the component of diameter 42 mm and length 120 mm. The available speeds are 70, 110, 176, 2