Calculate the percent change in load on the wall form tie, Civil Engineering

Assignment Help:

A concrete wall form tie with an ultimate strength capacity of 2,400-lbs is designed for use in a concrete wall form with an 18-in center to center spacing. During formwork inspection it was discovered that the actual spacing is 24-in center to center. Using the actual spacing, the percent change in load on the wall form tie is most nearly: 

765_Calculate the Percent Change in Load on the Wall form Tie.png

Solution:

Determine design tributary area: 1.5-ft x 1.5-ft = 2.25-ft2

Determine actual tributary area: 2-ft x 2-ft = 4-ft2

Determine design ft2 load:    2400-lbs / 2.25-ft2 = 1066.67-lbs/ft2

Determine actual load on 4-ft2:  1066.67- lbs/ft2 x 4-ft2 = 4266.68-lbs

Increase in load is:  4266.68-lbs - 2400-lbs = 1866.68-lbs

Calculate % change = 1 - (4266.68-lbs / 2400-lbs) = 78%

The load increase is 78% on the wall form tie.

 


Related Discussions:- Calculate the percent change in load on the wall form tie

Surveying, describe two fundamentals purposes of surveying.

describe two fundamentals purposes of surveying.

Traffic surveys, Traffic Surveys: The following traffic surveys are n...

Traffic Surveys: The following traffic surveys are needed for preparing a good road project: Classified Volume Counts This survey is normally carried out for 7 days,

Fathometer, define Fathometer in civil engineering field #Minimum 100 words...

define Fathometer in civil engineering field #Minimum 100 words accepted#

Define the predominant factor in atmospheric corrosion, Define the Predomin...

Define the Predominant factor in atmospheric corrosion? The predominant factor in atmospheric corrosion in areas located above splash zone is moisture as there is an excess ava

Define the meaning of tensile stresses, Tensile stresses It has been po...

Tensile stresses It has been possible to introduce tensile stresses of upto 850 N/mm 2 in tendons with the use of this method. But the method is not suited in situations where

Remedial measures for problems in turbid water - absorption, Define Remedia...

Define Remedial measures for Problems in Turbid Water - Absorption? The process of absorption of light can be overcome by using higher powered lighting, or by using more light

Define air chamber and surge tank, Q. Air chamber vs. surge tank in pressur...

Q. Air chamber vs. surge tank in pressurized pipelines? Air chambers and surge tanks are generally installed in water main to ease the stress on the system when valves or pumps

Define rotation - actions in pot bearings, Define Rotation - Actions in POT...

Define Rotation - Actions in POT Bearings? POT bearings are associated with large rotations which are accommodated by the deformation of elastomeric pad. Large cyclic rotations

Energy equation, find the pressure head at 2-2 if the rate of flow in pipe ...

find the pressure head at 2-2 if the rate of flow in pipe is 0.36m^3/s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd