Calculate the peak manning and average rate of software, Software Engineering

Assignment Help:

Q. A software project is planned to cost 95PY in a period of 1 year and 9 months. Calculate the peak manning and average rate of software them build up.

Ans. Software project cost                               K=95PY

Peak development time                        td=1.75years

Peak manning                                      =mo=K/td√e

95/(1.75 *1.648) = 32.94=33persons

Average rate of software team build up

=mo/td=33/1.75=18.8 person/ year or 1.56 person / month.


Related Discussions:- Calculate the peak manning and average rate of software

What is system testing, What is System Testing System Testing : This t...

What is System Testing System Testing : This testing focuses on validating the product with respect to software specification Document. Methods like function testing (using Bl

Define the stress testing, Define the Stress testing: - It checks the r...

Define the Stress testing: - It checks the robustness of application. - It verifies that application consistently gives satisfactory performance under unfavorable and extrem

Explain acceptance testing and beta testing, Explain acceptance testing and...

Explain acceptance testing and beta testing.  Acceptance Testing and Beta testing : System tests are designed to validate a fully developed system to make sure that it meets

Explain how to define severity rating in your project, Explain how to defin...

Explain how to define Severity Rating in your project. Severity rating is a combination of three factors: - The frequency of the problem occurrence. It could be common / ra

Differentiate between failures and faults, Differentiate between failures a...

Differentiate between failures and faults.   Failure:- Failure is the departure of external results of program operation from requirements. So failure is dynamic. Failure can

How does the risk factor affect the spiral model, Q. How does the risk fact...

Q. How does the risk factor affect the spiral model of software development? Ans: Risk Analysis phase is the most vital part of Spiral Model. In this phase all probable (and

Identify all activity dependencies in the project, Question: The activi...

Question: The activities in a project are given the PERT chart below: a) Identify all activity dependencies in the project. b) Clearly distinguish between critical

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd