Calculate the cost to finance the construction project, Civil Engineering

Assignment Help:

A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of 14-months. The Contractor secured a bank loan with an interest rate of 1% per month on the outstanding balance. The Contractor will borrow $100,000 per month to reconcile costs at the end of months 1 through 12. Calculate the cost to finance the project that will be included as part of the bid.

Solution: At the end of month 12, the contractor will have borrowed 12 payments of $100,000 each.  The owner is scheduled to pay the contractor at the end of month 14 at which time the contractor will repay the bank.  Use the following equation to calculate the future value then extract the cost of financing the project:  

F = $100,000 (F/A, 1%, 12) (F/P, 1%, 2)   = $1,293,700

                                         Amount Borrowed =$1,200,000

                                    Amount of interest =$     93,700


Related Discussions:- Calculate the cost to finance the construction project

Show the silt curtain touching seabed, Q. Show the Silt curtain touching se...

Q. Show the Silt curtain touching seabed? Silt curtains are impermeable vertical barriers extending from seawater surface to their designed depths. Curtains are held in a verti

Fillet welding, Strength of member when fillet welded

Strength of member when fillet welded

Assignment, information of cement types

information of cement types

Diffrence between rowe cell and oedometer apparatus, Q. Diffrence between R...

Q. Diffrence between Rowe cell and Oedometer apparatus? The benefits of using Rowe cell over oedometer apparatus are:  (i)  It possesses control facilities for drainage and

State the term - relaxation of stress in steel, State the term - Relaxation...

State the term - Relaxation of Stress in Steel If we keep a high-tensile steel wire stretched and maintained at a constant strain, the value of the force in the wire does not

Explain the perception reaction time, Explain the Perception Reaction Time ...

Explain the Perception Reaction Time A significant variable in the successful processing and use of information is the speed with which this is done. Perception-Reaction Time (

Weigh batching, measurement of gauge box for sand ?

measurement of gauge box for sand ?

Tremie pipes are normally used with aid of hoppers, Question For underw...

Question For underwater concreting, tremie pipes are normally used with aid of hoppers. From time to time tubes are put in inside the hoppers and with reasons? Answer

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd