assignment, Operation Research

Q2.Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignment?
JOBS
OPERATORS 1 2 3 4 5

1
2
3
4
5
6
6 2 5 2 6
2 5 8 7 7
7 8 6 9 8
6 2 3 4 5
9 3 8 9 7
4 7 4 6 8

Posted Date: 4/20/2013 2:53:50 AM | Location : USA







Related Discussions:- assignment, Assignment Help, Ask Question on assignment, Get Answer, Expert's Help, assignment Discussions

Write discussion on assignment
Your posts are moderated
Related Questions
Periodical Article A periodical is a publication that is  published  periodically like  a newspaper a magazine  and a journal. Usually  periodicals have  volume numbers  and n


b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Knowledge: The dictionary definition of knowledge is 'organised body of information or the comprehension and understanding, consequent on having acquired an organised body of

Case Study - Research Process Tomzak  and Hale  inc was a medium sized  marketing  research firm  located  in a large mind western  city. Bob Lynn a marketing  vice president

Demerits  of Range a.It gives  importance  to the  two  extreme  values and is very much affected by the extreme items. b.The range  provides  no information  about the  st

Assignments should be submitted via FLO by the above deadline. Penalties for late submission are as set out in the topic SAM on FLO. Extensions can be granted in line with standard

Anthology or Book with Articles  or Works by Many Authors   The name  of the person  compiling the book  will be  given  followed  by the  word editor. For more  than one  edit

Six Operators are to be assigned to five jobs with the cost of assignment in Rs. given in the matrix below. Determine the optimal assignment. Which operator will have no assignment

a)Draw a network for the project. b)Determine the critical path. Activity Duration Activity Duration 1-2 15 5-10 22 1-3 13 6-9 33 1-4 1