ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Decision analysis, a question was given but i cannot identify the alternati...

a question was given but i cannot identify the alternatives and i do not know how to calculate the right amount of payoff.what are the right ways to calculate the payoff table.

Research methodology, In research methodology we not only discuss the res...

In research methodology we not only discuss the research methods but also consider the logic behind the method we use in the context of our research study and explain wh

Compute the joining, The Best Corporation is considering making either mino...

The Best Corporation is considering making either minor or major repairs to a malfunctioning production process.  When the process is malfunctioning, the percentage of defective it

Liner programming problem, A constraints in an LPP restricts? (Value of obj...

A constraints in an LPP restricts? (Value of objective function,Value of decision variable,Use of available resources, uncertainty of optimum value) please help me to find out righ

Scope, explain the significant and scope of operation research in scientifi...

explain the significant and scope of operation research in scientific management

Problem, A paper mill produces two grades of paper viz., X and Y. Because o...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of

Disadvantages of mean deviation - measure of dispersion, Disadvantages of ...

Disadvantages of Mean Deviation a.Mean deviation ignores  the algebraic  signs of the deviations and  such it is  not capable  of further algebraic  treatment. b.It is  no

Data management, Data Management As your  research project progresses ...

Data Management As your  research project progresses you will  quickly  gather more  and more  data. These need  to be managed in such  a way that they  can be  accesses and

Simple size -sampling decisions, simple Size When a survey  is underta...

simple Size When a survey  is undertaken and  it is not  possible  to cover  the entire population, the marketing  researcher has to  answer a basic  question  - how  large  s

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd