Amount of borrow needed to bring area to elevation of 90-ft, Civil Engineering

Assignment Help:

Surveyed elevations are shown in Figure for a 50' x 50' grid at a proposed parking lot location. The amount of borrow needed to bring the area to an elevation of 90-ft is most nearly:

967_amount of borrow needed to bring the area to an elevation.png

Solution:  

Find the average elevation:  

Average   = 87.6-ft + 87.6-ft + 87.6-ft + 88.6-ft / 4                  

Average =   87.85-ft  

Change = 90-ft - 87.85-ft

   in elevation  = 2.15-ft

 Fill Required   = 2.15-ft   x 50-ft x 50-ft

      = 199-yd3


Related Discussions:- Amount of borrow needed to bring area to elevation of 90-ft

Define inspection of pier or abutment, Define Inspection of Pier or Abutmen...

Define Inspection of Pier or Abutment? Inspection of pier/abutment may then be carried out as under: i. Conduct visual inspection of the entire surface using up and down swe

Free- fall concrete placement in bored piles, Q. Free- fall concrete placem...

Q. Free- fall concrete placement in bored piles? Based on the research by STS Consultants Ltd it was found that concrete placed by free falling below 120 feet will not suffer f

Properties of stones, Properties of Stones The following properties of ...

Properties of Stones The following properties of the stones should betake into account before choosing them for engineering works: Structure: The structure of the stone ca

Pipelines, Pipelines: Use of Pipelines in Transport Pipelines...

Pipelines: Use of Pipelines in Transport Pipelines are used for transporting liquids (petroleum products for example), gases and solids in slurry form (for example ir

Main function of followers in driven h-piles, Question What is main fun...

Question What is main function of followers in driven H-piles ? Answer A follower is an extension between pile head and hammers which transfers blow to pile in which

Dry process of cement, i want a complete flow chart of dry process of cemen...

i want a complete flow chart of dry process of cement

Asphalt mix design – durability and stability, Q. Asphalt mix design - dura...

Q. Asphalt mix design - durability vs. stability? The main aim of asphalt mix design is to achieve a mix with economical blending of aggregates with asphalt to achieve the foll

Wet mix macadam - road pavements, Wet Mix Macadam: For heavily traffi...

Wet Mix Macadam: For heavily trafficked highways, the granular bases are constructed using Wet Mix Macadam (WMM). The WMM is a specification in which well graded aggregate is

Flooring, construction detail of all types of flooring

construction detail of all types of flooring

What to do to improve the reliability of the test results, Explain clearly ...

Explain clearly with a neat sketch how you will verify the coefficient of permeability of a clay sample in the laboratory and derive the expression used to compute the permeability

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd