Activities to Preparing Long-term Plans

1. Data collection regarding existing loads, forecast of expected loads, operating conditions, and etc. from Grid substation up to consumer level.

2. Mapping of existing system.

3. Analysis   of   existing   system.

(Voltage regulation, T&D losses in existing system, Adequacy of backup system)

4. Load forecast.

5. Plan for upgrading the network.

6. Technology options involving integration of characteristics for modernization of system.

7. Evaluation of several alternatives for least cost optimal solution.

8. Firming up of scope of works.

9. Preparation of cost estimates.

10. Phasing of their cost and works.

11. Financial analysis.

Posted Date: 2/6/2013 6:26:37 AM | Location : United States







Related Discussions:- Activities to preparing long-term plans, Assignment Help, Ask Question on Activities to preparing long-term plans, Get Answer, Expert's Help, Activities to preparing long-term plans Discussions

Write discussion on Activities to preparing long-term plans
Your posts are moderated
Related Questions
Q. Illustrates typical thermal noise waveform? In general, any physical resistor or lossy device can be modeled by a noise source in series with a noiseless resistor, as shown


What is hall effect?

Complete Instruction Set of 8085 Microprocessor There are  total 256 instructions in  8085 microprocessor. These instructions are classified  into  seven categories  according

Q. The voltage across a parallel combination of a 100- resistor and a 0.1-µF capacitor is 10 cos(5000t +30°) V. Determine the admittance of the parallel combination and find the c

Q. The coil is placed so that its axis of revolution is perpendicular to a uniform field, as shown in Figure If the flux per pole is 0.02 Wb, and the coil, consisting of 2 turns, i

Cross Section of NMOS with Channel Formed: ON state A metal-oxide-semiconductor field-effect transistor (MOSFET) is based upon the modulation of charge concentration through a

Prepayment Meters Usage of prepayment meters will extensively improve the revenue collection of the utilities. There are a number of ways in that prepayment assures revenue pr

GAS HAZARDS IN THE LABORATORY : As mentioned in the introduction of this unit, the gas hazards in a laboratory arise from LPG and other compressed gases. Though the use of gas for

A single phase line has an impedance of 8.4 + j11.2 Ω. The line feeds a load consisting of a resistor and an inductor connected in parallel as shown in Figure 1. The load is absorb