Accuracy and range - angle measurement, Civil Engineering

Accuracy and Range - Angle measurement:

Accuracy and Range:-Angle measurement:-Most modern total station instruments measure angles by means of electro-optical scanning of extremely precise digital bar-codes etched on rotating glass cylinders or discs within the instrument. The best quality total stations are capable of measuring angles to 0.5 arc-second. Inexpensive "construction grade" total stations can generally measure angles to 5 or 10 arc-seconds.

Distance measurement:-Measurement of distance is accomplished with a modulated microwave or infrared carrier signal, generated by a small solid-state emitter within the instrument's optical path, and reflected by a prism reflector or the object under survey. The modulation pattern in the returning signal is read and interpreted by the computer in the total station. The distance is determined by emitting and receiving multiple frequencies, and determining the integer number of wavelengths to the target for each frequency. Most total stations use purpose-built glass corner cube prism reflectors for the EDM signal. A typical total station can measure distances with an accuracy of about 1.5 millimetres (0.0049 ft) + 2 parts per million over a distance of up to 1,500 metres (4,900 ft).

Reflectorless total stations can measure distances to any object that is reasonably light in color, up to a few hundred meters.

Posted Date: 2/11/2013 5:18:46 AM | Location : United States







Related Discussions:- Accuracy and range - angle measurement, Assignment Help, Ask Question on Accuracy and range - angle measurement, Get Answer, Expert's Help, Accuracy and range - angle measurement Discussions

Write discussion on Accuracy and range - angle measurement
Your posts are moderated
Related Questions
Stabilised Pavement Layers: Soil stabilisation is the process of treating a soil in such a manner as to alter and improve its properties for use as a pavement layer on sub-gr


The local survey crew measures a distance of 1,135 ft of new drainage pipe that is required for the new road construction. The beginning point for the drainage is located at statio

describe abot the michelson interfrance

what is the importance of plagiarism in civil Engeneering


expressions for calculating corrections for earth curvature

Question In soil compaction test , if test result exceeds 100%, should engineers accept result? Answer Soil compaction is method of increasing soil density by re

Explain Fluid Mechanics or Properties – Viscosity A measure of a fluid's resistance to flow when acted upon by an external force such as pressure or gravity. Also termed, "Abso

Autocad-Introduction Learning to use a CAD system is similar to learning a new language. It is necessary tobegin with the basic alphabet and learn how to use it correctly and