Write a memo to george readymix outlining

Assignment Help Project Management
Reference no: EM13838941

Assessment Part A

For part A of the assessment you must complete the following tasks and questions. Read all the questions before you commence the tasks. The schedule is to be developed in an appropriately named Microsoft Project 2013 file (see below) and the questions are to be answered in a Word document.

As stated above, any assumptions must also be listed at the beginning of the Word document.

1. You have been asked by Billy the Banker at ANZ , to use Microsoft Project to develop the project schedule. Note that he has also asked you to include the milestones at the end of the task list in your schedule. These will be used for monitoring the cash flow of the project.

Based on the information in the case study description above, use Microsoft Project 2013 to produce a "Part A" schedule. Make sure that you:

a) Include the milestones grouped together at the end of the task list.

b) Include the resource allocation details on the schedule.

c) Have the project name (CQConstruction Supplier's Business upgrade) as the top of the task list and have all other tasks and summary tasks indented according to the given WBS.

d) Make sure that the holidays described in the "additional information" are not included in the available working days for your project.

e) Use the Microsoft Project software to make sure that the critical path(s) are automatically displayed in red on the bars of the Gantt chart view of you schedule.

At this point there may be resource over allocation issues. Do not attempt to resolve these before answering question 2. Save this version of your schedule in ms project file called CQContructionSupplysPartA1.mpp. You will be required to submit this file as part of your assignment submission.

2. At this point ignore any resource over allocations. Based on your CQContructionSupplysPartA1.mpp schedule (and assuming that you would have no resource constraints):

a) How long would the project take?

b) What are the start and finish dates of the project?

c) List all the tasks that are on the critical path.

d) Did the annual holidays make any difference to the end date of your project? Explain why/why not.

e) If you were asked to complete the project 3 weeks earlier by reducing the duration of some of the tasks in the project, what tasks would you target for reduction and why? In your answer, include specific suggestions about how you could reduce the duration of those tasks.

3. Create a copy of CQContructionSupplysPartA1.mpp in another file called CQContructionSupplysA2.mpp. If there were any resource over-allocation issues resolve these in this new CQControllerSupplysPartA2.mpp without adding any additional resources. Save the "modified" version of CQContructionSupplysPartA2.mpp.

a) Describe how you used/would use Microsoft Project to resolve any resource over allocation issues?

b) In your Word document, list the tasks that are now displayed as "critical".

c) Do the resource constraints have any impact on your project duration and end date? Explain.

d) Sometimes it is possible to resolve resource over-allocation issues by levelling within available slack. What impact does this have on your project schedule? (Hint: consider both the advantages and disadvantages in your answer.)

4. CQContruction Supply's Purchasing department require 6 clear working days notice to authorise any purchase over $10,000 dollars. You have four such purchases that will require such notification falling within the project period. Answer the following questions based on your CQContructionSupplysPartA2.mpp schedule:

a) List the dates you expect to require the Delivery of robotic arms, Delivery of hydraulics, Geo Logistics Mapping Hardware and Software purchase for work on the project.

b) Add a "milestone" as a reminder of the last date you need to give notice to the Purchasing department for each of these acquisitions. Add this at the start of your list of milestones and highlight the milestone in the task list using the "background colour" icon on the task ribbon. This will make it easier for your marker to check your work.

c) According to your schedule, when is the last date you need to give notice to the purchasing for material for the project?

5. Write a memo to George Readymix outlining:

a) the expected completion date of the project, assuming it commences at M1 (5/10/15);

b) the total duration of the project;

c) an explanation of the main factors that cause the project to require that length of time and any recommendations that you might make if time was a priority for the project;

d) The estimated direct labour cost of the project (excluding the cost of your project management consultancy. Present the costs in a table showing the costs for the following:

Assume that you will send the project schedule (CQContructionSupplysPartA2.mpp) as an attachment to the memo. The information in the memo should correspond to the attached schedule.

6. You have summarised the direct labour costs and some of the key hardware and software costs in question 5. What additional costs are associated with this project? Be as specific as possible in your answer.

7. Are there any other project related supporting activities, plans, events or tasks that your team might have overlooked? If they were overlooked describe how this could impact on the project. (Aim to identify and discuss at least two.)

Assessment Part B

Your project has now travelled forward in time and the project has now been underway for 2 months. To achieve this time travel in MS Project you must first set a baseline for the day of the Kick-off meeting and set a Status Date to 23/11/2015

Additional settings should be made under MS project Options as shown below.

You are required to update your project plan in accordance with the progress the project has made in the first 2 months. You contact all the key stakeholders and receive the following status update information for the tasks completed and those currently in progress up to the 23/11/2015.

1 a. Update the project file and Save this version of your schedule in CQontructionSupplysPartB1.mpp. You will also be required to submit this file (CQontructionSupplysPartB1.mp) as part of your assignment submission.

b. Describe the impact the delays in the schedule has had on your project.

c. Based on the progress as of 23/11/2015 calculate the CV, SV, SPI and CPI for the project.

d. Using CPI and SPI explain how the project is progressing

e. Give a forecast for the estimated completion cost of the project. Explain how you arrived at your forecast figure.

You have been advised by Ang Jolli the Business Analyst with VAR's r US that there will be a delay in the delivery of the requirements for the CRM system. She cites the belligerence of CQConstuctions Operation Manager as the cause. TASK 1.3.1.2.2 Final Process Confirmation is to be delayed one week. Ang Jolli has informed you that she has the backing of her management in insisting that all blue print tasks are too double in duration to relieve pressure on the project and to compensate for the stand idle time. Around this time you pick up an answer phone message from Gloria Jeans saying she needs to schedule a 2 day software upgrade before CRM integration testing can be conducted.

2. Create a copy of CQontructionSupplysPartB1.mpp in another file called CQontructionSupplysPartB2.mpp. Amend the project schedule in CQontructionSupplysPartB2.mpp incorporating the requested changes from Ang and Gloria Highlight all the changes (including changes to predecessor relationships in other tasks).

This is to aid your marker.

If necessary, resolve any resource over-allocation. You will also be required to submit this file (CQontructionSupplysPartB2.mp) as part of your assignment submission.

3. Describe the impacts of each the following on the project schedule:

a. The delay in Final Process Confirmation.
b. The change in duration of the Blue Print Tasks.
c. The requirement for the software upgrade.

Explain your answers.

4. Describe the impacts of each the following on the project budget:

a. The delay in Final Process Confirmation.
b. The change in duration of the Blue Print Tasks.
c. The requirement for the software upgrade.

Explain your answers.

Assessment Part C

Concerned that the Customer mobile portal may become the critical bottle neck in the delivery of the project, your team investigate options for crashing that section of the project. Following a series of meetings with the mobile portal developers Bret Whitelee and Dot Perkins of "Web Moves" your team has ascertained that it is possible to crash the mobile portal deliverable portion of the project.

As well as the following information about each task and the cost of assigning extra resources you have been informed that Web Moves will apply an indirect cost per day for their services for the duration of their contract. That is charged at $500 per working day.

You may have used difference durations in Part and A and B to represent work effort of the tasks and derive a different critical path. For the purpose of this exercise use those discussed with Web Moves here.

1. Develop a table of costs for each task showing the slope. Then list the tasks in order that you would crash showing the total actual cost after any savings for each task crashed

2. State what duration you would choose for this deliverable and explain your answer.

3. Complete the stakeholder analysis template for each of the projects stakeholders adding any you feel may have been missed. Draw a Interest / Power grid matrix for these stakeholders.

4. Write a report, seeking approval to crash this part of the project, to those stakeholders you think need to be informed. Mark it clearly for their attention. Explain the reason for crashing and sell the financial and non-financial benefits of your recommendation. Address the potential individual concerns of your stakeholders.

Attachment:- Management.rar

Reference no: EM13838941

Questions Cloud

How much kinetic energy does coaster have : How much energy is required to lift a 9 kg (20 lb) bag of rice from the floor to the trunk of your car located 0.9 meters above the ground and What kind of energy does the rice have when it is sitting in your trunk?
Operating system supported : To learn more about e-mail client programs, perform the following actives: Open a browser and search the Web for free E-mail client programs. Visit several of the home pages associated with these programs and make note of the following informatio..
Discuss whether fred is a resident of australia for taxation : Discuss whether Fred is a resident of Australia for taxation purposes. Explain why the receipts in Egerton-Warburton & Ors v DFC of T (1934) 51 CLR 568 were assessable, but the receipts in IRC v Ramsay (1935) 1 All ER 847 were treated as capital amou..
Explain discovered about the laws of abortion : explains what you discovered about the laws of abortion in your state (Louisiana) or country and why this information might be shared with clients. Further, explain your personal stance on abortion and how your ethical entanglements might impact y..
Write a memo to george readymix outlining : Write a memo to George Readymix outlining - You have summarised the direct labour costs and some of the key hardware and software costs in question - What additional costs are associated with this project? Be as specific as possible in your answer.
Financial fact sheet for scarlett company : Before you start: Study the Financial Fact Sheet for Scarlett Company and Gable Company.
How to draw up longitudinal sections for drainage lines : How to draw up longitudinal sections for drainage lines. The design flow for each box gutter and downpipe based on an ARI of 100 years.
Where you see yourself within these social constructs : Individuals seldom use these terms to describe themselves or others. However, oppression and privilege impact every aspect of people's lives. As you consider your own place in society, consider your emotional attachment to where you see yourself w..
Statements into the balance sheet : The balance sheet pulls pieces of the other financial statements into its layout. What are those pieces and do they pull the focus from the other statements into the balance sheet? Anyone else have thoughts on this--how do the statements interact ..

Reviews

Write a Review

Project Management Questions & Answers

  Cost benefits analysiswhen performing a cost benefits

cost benefits analysis.when performing a cost benefits analysis cba cba how do you validate assumptions and apply

  Forecasting using excel hi dearplease answer all of the

hi dear ltbrgtplease answer all of the questions in the paper and write a summary of your answers for all questions .

  Evaluate and choose alternatives make sure to identify any

business problem the order fulfillment team has been using several legacy technology systems to manage inventory and

  Management is considering a new project

Management is considering a new project for your organization

  Integrate project goals to the organization''s objectives

Explain why is it important to integrate project goals to the organization's strategic objectives and why is setting specific project goals essential to the successful outcome of a project?

  Statistical critical thinking and application skills

Statistical Critical Thinking and Application Skills,  Discuss the research paper. Design and perform an experiment to answer the questions:

  Project managemet work break down structureyour next step

project managemet work break down structureyour next step in the project management process is to create a work

  Adjunct professor teaching project management

What five essential theoretical lessons would you share with your students that you feel are the most important in assuring professional success as a project manager?

  Explaining six barriers for project success

What are the six barriers for project success? Give examples of how these barriers might hamper a project.

  Using the assembly-line balancing procedure

Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job

  Pmi and it project team roles are notedif a person has been

pmi and it project team roles are noted.if a person has been certified by the pmi but has never been on an it project

  Why the family is in need of the project

Briefly explain why the family is in need of the project and show the expected benefits that are motivating the family to commission this project.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd