Which tasks are on the critical path of the pert chart above

Assignment Help Other Subject
Reference no: EM131016624

Problem SpecificationConsider the following network schedule:Table 1: Network Schedule of an Accounts Payable SystemActivity Description OptimisticDuration(days)Most LikelyDuration(days)PessimisticDuration(days)Predecessor1 Accounts Payable System2 Planning meetings 1 1 23 Team assignments 3 4 5 24 Program specification5 Customer requirements 8 10 12 36 Feasibility study 3 5 7 57 Systems Analysis 6 8 10 58 Prelim budget & schedule 1 2 3 79 Functional specification 3 5 7 710 Prelim design 10 12 14 911 Configuration &performance needs3 4 5 1012 Hardware requirements 4 6 8 1113 Systems specification 5 7 9 1014 Detailed design 12 14 16 12,1315 Program specification 8 10 12 1416 Programming - first phase 27 32 37 1517 Documentation 14 16 18 1518 Prototype19 Development 5 7 9 1620 User testing & feedback 12 14 16 1921 Programming - second phase 10 12 14 1622 Beta testing 18 20 22 2123 Final documentation package 9 10 11 17,2024 Training package 4 5 6 21SS,2325 Product release 3 5 7 22,23,24SS - Start to start lagNotes:? A working day is Monday, Tuesday, Wednesday, Thursday and Friday (8am - 4pm).? Staff works Mondays through Friday.? Project start date is 1st April, 2016.? The last Friday of every month is a sports day for the company. No work is done on this day.? The following holidays are observed in a year.o January 1 - Another Wacky Year Dayo Second Monday in January, March, May, June, August, October, December is Eat-All-You-Can dayo April 10 - Plagiarism Dayo May 24 - National Panic Dayo June 18 - Love Your Neighbor Dayo August 15 - National Rocky Road Day o December 20th - Blame Someone Else Dayo If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.Given the information provided in Table 1 and key notes, answer the following.

Required:

i. Using an appropriate approach to building a Work Breakdown Structure (WBS), develop a graphical WBS for this project.

ii. Using the 3-point technique, calculate the activity durations (round to nearest whole number).

iii. You are tasked to draw using appropriate software an AOA PERT chart for the above project; assuming a finish-start (FS) relationship between activities. (The length of the arrows must be indicative of the duration).

iv. How long will this project take? What is the completion date?

v. List all the distinct paths in the project along with their durations.

vi. Which tasks are on the critical path of the PERT chart above?

vii. Identify all Activities in the above project that have a slack and the amount of slack.

viii. You have discovered that the competing accounting package (with significant improvements) is scheduled for delivery in approximately 144 days. Based on your original schedule above, would you beat this delivery time? If not, what actions would you take?

ix. One of your two critical systems analysts might be leaving the firm sighting critical family reasons. What actions would you take to ensure the original delivery time is still met?

x. The person working on activity 15 informs you he can't start work until two days after the scheduled starting date. What impact would this have on the completion date of the project?

xi. By how many days can activity 17 be delayed before it becomes critical?

xii. If activity 19 is delayed by 4 days what will be the new project duration? If there is no effect, state ‘No change in duration'.

xiii. Convert the above AOA Chart to an AON Chart (also known as Project Network Diagram) clearly stating the ES, EF, LS, and LF for each of the activities. Use the following node style for your AON diagram. Consider the SS relation between activities 21 and 24.

xiv. Create a Gantt chart for the above network schedule using project management software.

xv. Complicating the issue is the concern about the project meeting the promised delivery dates. How could the project manager convince their clients that they should wait for this product rather than jump to a package provided by a new entrant in the business?

Reference no: EM131016624

Questions Cloud

Construct a graph of a social network : IS679: Social Network Application and Analytics - Determine whether the graph/network is directed or undirected. If directed, transform it into undirected graph/network - Prepare an input file to Gephi based on the above undirected graph/network.
Problem regarding the required rate of return : Sunshine has the cash available to make an immediate cash payment for the property. Assuming a 10% required rate of return, at what price would Sunshine be required pay to in order to match LDI's offer?
Explain the price point on which you will focus : In the introduction to your risk analysis, be sure to explain the price point on which you will focus and why you chose the product attributes that you want to acquire
Differences between job order costing and process costing : Explain the similarities and differences between job order costing and process costing.
Which tasks are on the critical path of the pert chart above : One of your two critical systems analysts might be leaving the firm sighting critical family reasons. What actions would you take to ensure the original delivery time is still met?
Problem regarding the dividend income : West Wind Tours stock is currently selling for $48 a share. The stock has a dividend yield of 3.2 percent. How much dividend income will you receive per year if you purchase 200 shares of this stock?
How today customer relationship era differs from prior eras : Describe how today's customer relationship era differs from prior eras. The goal-setting step in the planning phase of the strategic marketing process sets quantified objectives for use in the evaluation phase. What does a manager do if measured re..
Why are some of these costs allocated to the product : Explain how these costs are associated with the manufactured product. Why are some of these costs allocated to the product through costing methods such as job order costing or process costing?
Swott analysis of the organization : Develop a 800 word SWOTT analysis of the organization and offering Product that was approved was: Our new product, a longer lasting eye shadow that comes in different botanical garden and fruit fragrances was and our organization is Too Faced

Reviews

Write a Review

Other Subject Questions & Answers

  Write about africa health delivery system

write about africa's health delivery system. Your final paper must 8 pages long. It should demonstrate a strong thesis statement supported by research from at least 5 different sources. Include both in text citations and a References page in APA f..

  Explain how and why each source is valuable and useful

Explain how and why each source is valuable and useful - Identify any quantitative or qualitative forecasting factors contained in the sources.

  Types of management styles

Discuss these three types of management styles (Scientific Management, Human Relations Management, and Systems Management).

  Indirect costs often depend on some or all of direct costs

Do you agree or disagree with the following statement: Indirect costs often depend on some or all of the direct costs, such as direct labor, direct material, or both.

  What the costume design tells viewer about that character

For this Journal Assignment - find an image or link of a play, film or television show, select a character and discuss what the costume design tells the viewer about that character

  Deifne the concept and provide examples

Assign an appropriate concept to explain/describe the behavior. Be sure to deifne the concept and provide examples to illustrate the concept.

  Political and societal issues surrounding drilling for oil

What are some political/societal issues surrounding drilling for oil in the Gulf of Mexico or other places off the coasts of the US? Please provide any references used.

  Report on feudalims in the history of france england or

report on feudalims in the history of france england or germany include approximate years when feudalism began and

  Recognize types of control mechanisms-microsoft organization

Recognize four types of control mechanisms (ways controls are applied) used in Microsoft organization. Distniguish these control mechanisms.

  Safety in the early childhood issues

Describe two to three strategies to support nutritional choices and possible food allergies in children.

  Public health services

Find out what programs are available through public health services, local hospitals or other clinics. Discuss the scope of these services. Are these services well known? How many women take advantage of these services?

  Describe eliminative materialism

Describe eliminative materialism and it's role with folk psychology based on Churchland's view. State and discuss Churchlands three arguments to supprot his claim. How does he respond to problems of eliminativism and what are the consequences for ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd