A production line has three machines A, B, and C, with reliabilities of 0.99, 0.96, and 0.93, respectively. The machines are arranged so that if one breaks down, the others must shut down. Engineers are weighing two alternative designs for increasing the line’s reliability. Plan 1 involves adding an identical backup line, and Plan 2 involves providing a backup for each machine. In either case, three machines (A, B, and C) would be used with reliabilities equal to the original three.
Which plan will provide the higher reliability?
Explain why the two reliabilities are not the same.
What other factors might enter into the decision of which plan to adopt?
The Human Factors Analysis and Classification System (HFACS), SHELL or the 5M are often applied in a reactive manner.
A planned effort to influence public opinion is one of the strongest definitions of Public Relations we know. Planning is a management necessity in successful corporations, with most businesses routinely assembling five-year plans, including support ..
If off-the-job stress and dissatisfaction begin to create on-the-job problems,
The park commissioner would like to open the park to the public within six months from the time the work on the project is started. Does this opening date appear to be feasible? Explain.
What are a company’s total social responsibilities? Please explain it with some cases. Do you know anything about social response, and what is the difference between social response and social responsibility?
What is scope creep and why should a project manager be concerned about it?b Identify and briefly describe the five most common classifications for the way that projects end.
You and your fellow operations department teammates have been debating which companies are the best examples of applying supply chain management.
Is the process of hazard control a proactive, predictive, or a reactive process?
Investigate the costs of 3 different technologies which could be integrated into your company,
it has done in the past without opening itself up to the possibility of insolvency or a significant loss of surplus.”
Explain the process, purpose and importance of stakeholder assessments. Conduct a stakeholder assessment of a project you have worked on in the past. If you do not have project experience, you may use a well-known project from the media.
The objective of this exercise is to aid understanding of the dimensions of channel selection and their possible relationships with channel conflict.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd