Which activity has the greatest amount of slack

Assignment Help Project Management
Reference no: EM13846363

Project

The ARC Company specializes in developing_ and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC's president. Robin Lane. is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

The Project Priority Matrix for the Red Zuma Project is:

 

Time

Scope

Cost

Constrain

 

X

 

Enhance

X

 

 

Accept

 

 

X

Part 1

Abu are a member of a project team assigned to develop the new razor scooter code named "Red Zuma." Table 1 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

I. The project be6ns January 2. 2015.

2. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January). Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September). Thanksgiving Day (4th Thursday in November). December 25.

3. If a holiday falls on a Saturday. Then Friday will he given as an extra day off, and if it falls on a Sunday. Then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not he given a day off.

4. The project team works eight-hour days. Monday through Friday.

TABLE 1: Red Zuma: 'Project Schedule.

ID

Task Name

Duration

Predecessors

1

1 Red Zuma Project

260 days

 

2 1,1 Market Analysis 25 days  

3

1.2 Product Design

30 days

2

4

1.3 Manufacturing Study

20 days

2

5

1.4 Product Design Selection

10 days

3,4

6

1.5 Detailed Marketing Plan

15 days

5

7

1.6 Manufacturing Process

30 days

5

8

1,7 Detailed Product Design

45 days

5

9

1,8 guild Prototypes

25 days

8

10

1.9 Lab Test Prototypes

10 days

9

11

1.10 Field Test Prototypes

15 days

9

12

1,11 Finalized Product Design

20 days

7,10,11

13

1.12 Final Manufacturing Process

10 days

12

14

1.13 Order Components

7 days

12

15

1.14 Order Production Equipment

14 days

13

16

1.15 Install Production Equipment

35 days

14FS+20 days,15FS+30 days

17

1.16 Celebrate

1 days

6, 16

Note: ES refers to a Finish-to-Start lag.                                                                  

Construct a network schedule for this project and prepare a memo that answers the following questions:

1. When is the project estimated to be completed? How long will the project take?

2. What is the critical path for the project?

3. Which activity has the greatest amount of slack?

4. How sensitive is this network?

5. Identify two sensible milestones and explain your choices.

Include the following printouts:

A Gantt chart.

A network diagram highlighting the critical path.

A schedule table reporting ES, LS, EF, LF, and slack for each activity.

Part 2

The following personnel have been assigned full-time to the Red Zuma project team:

4 marketing specialists 4 design engineers

4 development engineers 4 industrial engineers

4 test riders

2 purchasing agent

Use the file from Part 1 and the information contained in Tables 2 and 3 to assign resources to the project schedule.

TABLE 2: Red Zuma Project Resources

Task Name

Resource Names

Red Zuma Project

 

Market Analysis

Marketing Specialist 1400%1

Product Design

Marketing Specialist Design Engineer [400%), Development Engineer 19))0%1, Industrial Engineer, Purchasing Agent

Manufacturing Study

Industrial Engineer [400%], Development Engineer [200%]

Product Design Selection

Marketing Specialist [1200%], Design Engineer [300%], Development Engineer WAJ, Industrial Engineer [200%], Purchasing Agent [25%]

Detailed Marketing Plan

Marketing Specialist [400%]

Manufacturing Process

Design Engineer, Development Engineer 1200%1, Industrial Engineer 1300%]

Detailed Product Design

Marketing Specialist [200%], Design Engineer [400%], Development Engineer 12101/41, Industrial Engineer [200%], Purchasing Agent [25%]

Build Prototypes

Design Engineer [200%], Development Engineer [200%], Industrial Engineer [400%]

Lab Test Prototypes

Design Engineer [200%], Development Engineer [200%], Test Rider

Field Tests

Marketing Specialist, Design Engineer [200%], Development Engineer, Industrial Engineer, Test Rider [300%]

Finalized Product Design

 

Marketing Specialist [200%], Design Engineer [300%], Development Engineer [300%], Industrial Engineer [200%], Purchasing Agent [25%]

Final Manufacturing Process

Industrial Engineer 1300%), Design Engineer, Purchasing Agent [25%]

Order Components

Purchasing Agent

Order Production Equipment

Purchasing Agent

Install Production Equipment

Design Engineer, Development Engineer 1300%), Industrial Engineer [400%]

Celebration

Design Engineer [400%], Development Engineer [400%], Industrial Engineer [400%], Marketing Specialist [400%], Purchasing Agent [200%]

Part A

Prepare a memo that addresses the following questions;

1. Which if any of the resources are over allocated?

2 Assume that the projects are time constrained and try to resolve any over allocation problems by leveling within slack. What happens?

3. What is the impact of leveling within slack on the sensitivity of the network?

 Include a Gantt chart with the schedule table after leveling within slack.

4. Assume that the project resource constrained ad no additional personnel are available. How long, Will the project take give the resource assigned?

5. How does the new duration compare with the estimated completion date generated from Part ? What does this tell you about the impact resources can have on a schedule?

Part B

Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC Will begin production in time for the major trade show in Las Vegas on January 22, 11)16, which minis the project needs to be completed by January 17, 2016. She has authorized working the first available Saturday of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 12 13 days.

After talking to the engineers, everyone agrees t hat they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start .10 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product design.

Dewey Martin, director of product development, is also willing to add personnel to the project, He is willing to make available at least one more Development. Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the deadline. Your objective is to develop a schedule which will satisfy the deadline with minimum additional resource usage.

Prepare a memo that addresses the following questions:

1. What was the impact of introducing Start-to-Start lags to the schedule and budget?

2. Which, if any additional personnel assignments, would you choose to complete the project before the January I 7th deadline? Fxpl tin your choices as well as the reasons Ibr not choosing other options.

3. How have these changes affected the sensitivity of the network and the critical path?

Include a Gantt chant with a schedule table displaying free and total lack for the new schedule.

Note: Do not assign new personnel to specific tasks, simply add them to the Resource Sheet. All new personnel are available kill time (100").

At first glance -this appears to be. Very complicated, difficult assignment, but it you enter the information correctly, the computer is able to generate the answers with a levy simple clicks.

Part 3

Top management has accepted the schedule created at the end of Part 2. Prepare a brief memo that addresses the 1011owing questions:

1. How much will the project cost? What is the most expensive 'activity?

2. What does the cash how statement tells you about how costs are distributed over the life span of the project?

Include a monthly cash flow liar the project.

Once you are confident that you have the final schedule, save the file as a baseline. Hint: Save a backup file just in case without baseline!

Part 4

Part A

Today's date is July 8, 2015, the milestone date for the completion of the Prototype.  You are charged with preparing a status report for top management. Table A2.8 summarizes progress on the Red Zuma project:

Submit a professional status report to Robin Lane that addresses the fo11owing questions:

1. How is the project progressing in terms of cost and schedule?

2. What activities have gone well? What activities have not gone well?

3. HOW much of the project has been accomplished (PCI13)?

4. What is the forecasted cost at completion (EACf)?

5. What is the estimated completion date?

6. How is the project doing in terms of priorities (see Part 1)?

Report and interpret relevant Earned Value metrics in your report.

Include a Tracking Gantt chart as well as an Earned Value Table with your memo.

TABLE 3: Red Zuma Project Update

 

Task Name

Act. Start

Act. Finish

Comp.

Phys. %
Comp.

Act. Our.

Rem. Dur.

1

1 Red Zuma

Fri 1/9/15

NA

46%

0%

125.85 days

146.4 days

2

1.1 Market Analysis

Fri 1/9/15

Thu 2/12/15

100%

0%

25 days

0 days

3

1.2 Product Design

Fri 2/13/15

Wed 4/1/15

100%

0%

35 days

0 days

4

1.3 Manufacturing Study

Fri 2/13/15

Fri 3/6/15

100%

0%

16 days

0 days

5

1.4 Product Design Selection

Thu 4/2/15

Fri 4/17/15

100%

0%

13 days

0 days

6

1.5 Detailed Marketing Plan

NA

NA

0%

0%

0 days

15 days

7

1.6 Manufacturing Process

NA

NA

0%

0%

0 days

30 days

8

1.7 Detailed Product Design

Mon 4/20/15

Wed 6/24/15

100%

0%

49 days

0 days

9

1.8 Build Prototypes

Wed 6/10/15

NA

39%

0%

9 days

14 days

10

1.9 Lab Test Prototypes

NA

NA

0%

0%

0 days

10 days

11

1.10 Field Test Prototypes

NA

NA

0%

0%

0 days

15 days

12

1.11 Finalized Product Design

NA

NA

0%

0%

0 days

20 days

13

1.12 Final Manufacturing Process

NA

NA

0%

0%

0 days

10 days

14 1.13 Order Components NA NA 0% 0% 0 days 7 days
15 1.14 Order Production Equipment NA NA 0% 0% 0 days 14 days
16 1.15 Install Production Equipment NA NA 0% 0% 0 days 35 days
17 1.16 Celebrate NA NA 0% 0% 0 days 1 days

Part B

You have told Robin Lane that based on what you know now you need to revise the estimates for some of the remaining activities. Detailed Product Design is expected to take 3 days longer than planned. Build Prototypes is expected to take 2 days less than planned and Finalized Product Design is expected to take 3 days longer than planned. Final Manufacturing Process is expected to take 2 days less than planned, while Install Production Equipment is now expected to take only 30 days. You also report that Detailed Marketing plan will be completed before the end of the New Year. She is in-sisting that the project be completed by January 17th in order to be ready for the Las Vegas show. She is willing to spend $50,000 from Management Reserves to expedite shipping if necessary. $25,000 would reduce the shipping of components by 5 days and/or $25,000 would reduce the shipping of manufacturing parts by 5 days (Hint: Adjust lag). Prepare a memo to Robin that addresses the following questions:

1. What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost?

2. Would you recommend authorizing the expenditure of $50,000? Explain.

3. What, if any other recommendations, would you make so that the project can achieve Robin's deadline? Justify your recommendations.

Include a Tracking Gantt chart with variance schedule that depicts your final recommendations and revised schedule.

Hint: After adjusting the Installation of Production Equipment and Finalized Prod¬uct Design, level outside of slack to eliminate any resource over allocation problems.

Reference no: EM13846363

Questions Cloud

Real interest rates are generally higher than nominal rate : On average, a coupon bond will increase in value as it approaches maturity. A bond with a coupon rate higher than its yield is worth more than its par value. Real interest rates are generally higher than nominal interest rates.
Case study from the perspective of the christian worldview : After an appropriate introductory paragraph with thesis statement, in which you name the scenario you are choosing, address each of the following six sections with at least one paragraph each. Use the underlined titles for each of your heading.
How are morality ethics faith and religion intertwined : The topic of the essay will be on How are morality, ethics, faith and religion intertwined?(e.g. What does it mean to be good?)
The yield curve almost always slopes upward : Over the last 5 years, the Russell small stock index has consistently out-performed the Russell large stock index. The S&P400 index is composed of the 400 largest stocks in the S&P500. The yield curve almost always slopes upward. An asset that last y..
Which activity has the greatest amount of slack : Which activity has the greatest amount of slack? How sensitive is this network? Identify two sensible milestones and explain your choices.
More preferred stock issues than common stock issues : Over the last decade, in the U.S., there were more preferred stock issues than common stock issues. The yield curve almost always slopes upward. An asset that last year had a Sharpe ratio = 0 would have had acceptable performance. An equity that last..
The current ratio of a firm would be increased : The current ratio of a firm would be increased by which of the following?
Current production levels : A mine is for sale. A mining engineer estimates that, at the current production levels, the mine will yield an annual net income of $100,000 for 20 years, after which the mineral will be exhausted. If an investor’s minimum acceptable rate of return i..
What is the equivalent present value : What is the equivalent present value of the following series of payments: $10,000 the first year, $11,000 the second year and $12,000 the third year? Consider 4% interest, compounded annually.

Reviews

Write a Review

Project Management Questions & Answers

  Determine the expected activity times

Determine the expected activity times - Develop an activity on arrow network diagram (AOA)

  The beauty of a woman is not in a facial mode but the true

the beauty of a woman is not in a facial mode but the true beauty in a woman is reflected in her soul. it is the caring

  A manager of a shoe manufacturing plant

1. Assume that a manager of a shoe manufacturing plant wants to practice management by exception. What are some types of reports that would be helpful? 2. Of the six systems elements that you can form the basis for system control design, which one do..

  1 a project scope statement is used to define the end

1. a project scope statement is used to define the end result of a project. its purpose is to define as clearly as

  Schedule and cost control presentation

Prepare a presentation comparing several different project management models, such as project management mutuality model, hybrid models, and future models.

  Project managementassume that an activity has a normal tune

project managementassume that an activity has a normal tune of 20 weeks a normal cost of 72000 a crash time of 16 weeks

  Calculating pv ev and ac

With the Cost one calculates PV EV and AC.

  What are the main reasons for it project failure and what

what are the main reasons for it project failure and what is the most important thing that management can do to

  Issues when there is no follow-on project

What problems may occur if the project manager does not have a follow-on project when the current project nears termination?

  Project management techniques for big data management

Write a report of 2500 words on one of the listed Statements - Topics. The report should demonstrate that the team has thoroughly researched the keywords and the key issues of their selected statement/topic including any existing arguments.

  Role of it management in organizations

Write a statement of what you perceive the role of IT management in organizations and address the IT management challenges that e-business brings.

  Improving communication in organizationsone of the most

improving communication in organizationsone of the most effective ways that we can improve our communication within the

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd