Question:

This activity will provide you with an opportunity to engage in discussion on a project management topic that was covered in this module.

The class interaction will foster a learning environment in which you will learn from each other's experiences and opinions. In addition, you will practice speaking the project management lingo and expressing your opinions in a professional manner.

Before you begin this discussion, be sure to complete the following:

Read the following:

. Gido, J., & Clements, J. P. (2012). Successful project management. Mason, OH: South-Western Cengage Learning.

o Chapter 9: Closing the Project

View the following:

. PowerPoint presentation:

o Chapter 9: Closing the Project

Read the following scenario:

You have been assigned to manage a project that has been in progress for a few months. The original project manager has now left the organization.

After taking a look at the project budget and utilizing the Earned Value Management metrics, you've determined that the project is behind schedule and will have a cost overrun at completion. The previous project manager never reported the project delays or expected cost overruns, so this bad news will be a surprise to the project sponsors and stakeholders.

This is a high-profile project and you are excited to have an opportunity to show off your newly acquired project management skills. However, this project is currently on a losing trajectory!

Now, respond to the following questions:

. What will be your next steps in order to re-route the project for success?

. What do you think will be your challenges and risks?

. How would your strategy change if you had strong reasons to believe that this news would cause the project sponsors to terminate the project?

Answered:-

Verified Expert


Preview Container content

The role of a project manager is tough with so many moving parts and numerous people invested in success of the project. The project manager has to stay a step ahead of the game. The project is on a losing trajectory at present. I will manage some measure in order to re-route the project for the success. They are discussed beneath:
1. At first I will get team buy-in to restart the project. I am not the one to set the schedules, costs, estimates and project scope. There are different groups who determine business cases and the proposals.
2. In order to make the project successful, buy-in isn’t enough, since The Executive who is sponsoring the project wholeheartedly
3. I will schedule the meeting on regular basis and actually hold them
I will re-examine the scope and include the specific tasks




Put your comment
 
Minimize


Ask Question & Get Answers from Experts
Browse some more (Project Management) Materials
BMGT 365- Discuss how Dunn should address cultural diversity within the organization; Discuss the areas in the original plan that would require change to accommodate Dunn's ro
Developing and implementing the policies and procedures you have decided to develop a project plan, which will assist you with planning, monitoring and implementing your pro
Assignment - Creating a WBS for the Construction of a House. Using Microsoft Word, create a work breakdown structure for the house build that contains at least three levels o
A company rewards its production department employees for meeting budgeted cost levels by giving out bonuses. If the department's costs exceed the budget, employees do not g
Project summary regarding opening a new division office in Scottsdale, Arizona. This new office will serve as a regional headquarters for Arizona, Nevada, Colorado, New Mexi
Microsoft Project is powerful but expensive. - Assume you are in charge of researching and purchasing a project management application.  - Would you select Microsoft Project?
Be sure to clearly define your approach for obtaining estimates for the 10 vendors that may be used on the project. Remember that you have not selected the vendors yet, but
SIT374 / SIT764: Project Management Assignment. What is the planned value of the project? What is the rate of performance (RP) for each task? Using the RPs obtained, calculat