What type of negative risk response strategy is this

Assignment Help Project Management
Reference no: EM13886903

Question 1: According to the textbook, risk management plans address 8 topics. Which of the following is not one of these topics?

a. Roles and responsibilities

b. Work breakdown structure

c. Budget and schedule

d. Tracking

Question 2: Many tools and techniques have been developed to help identify project risks. The US Government has appointed an independent experts group to anonymously provide their opinion on what may happen in future. What is the tool/technique adopted?

a. Brainstorming

b. Delphi technique

c. SWOT analysis

d. Interviewing

Question 3: The executive management of your organization has asked you, the project manager, for a periodic review of the project risks. Which risk analysis tool will you use that will help in monitoring the risks throughout the project life?

a. Top ten risk item tracking

b. Probability/impact matrix

c. Risk breakdown structure

d. Risk ranking chart

Question 4: People's attitudes towards risk vary. Some derive a high degree of satisfaction only from high stake risks whereas others are happy only when the stakes are low. What is the term for the measure of this satisfaction?

a. Risk reward

b. Risk gratification

c. Risk appetite

d. Risk utility

Question 5: You are tasked with preparing the risk breakdown structure for a project. After a thorough investigation you find that the responsibilities of each project team member have not been clearly defined. Which knowledge area of project management is this associated with?

a. Human resources

b. Scope

c. Communications

d. Integration

Question 6: An organization is evaluating the risks involved in implementing a sales force automation solution. It has been evaluated that the organization can save a lot of money. At this stage it is important to understand if the sales team will use this system. What category of risk needs to be assessed?

a. Financial risk

b. People risk

c. Process risk

d. Market risk

Question 7: Risks are controlled in two ways. It is essential to raise risk awareness and make it an ongoing activity for all project team members. In addition, risk events should trigger the execution of the risk management plan in order to control the risk. A number of tools and techniques are available to control risk. Which of the following is not one of the techniques for risk control?

a. Risk reassessment

b. Variance and trend analysis

c. Periodic risk reviews

d. Budget preparation

Question 8: Risk can be mitigated by reducing the probability of it happening. If project managers use established processes then some of the risk can be mitigated. The triple constraint of scope, cost and time are affected by technical, cost and schedule risks respectively. Which risk mitigation strategy helps lower the probability of all three risks?

a. Use WBS and CPM

b. Increase project manager authority

c. Improve problem handling

d. Emphasize team support

Question 9: Negative risks are potential hurdles to the execution of a project as per plan. Positive risks are those that impact the plan in the opposite direction of negative risks. Each, negative and positive risks, have suitable basic risk response strategies. Which one of the following strategies is applicable for both types of risks?

a. Risk mitigation

b. Risk acceptance

c. Risk transference

d. Risk sharing

Question 10: Project managers must treat risk management as an investment which increases the chances of success. Under which of the following circumstances would project risk management make financial sense?

a. Never makes financial sense

b. Only when the cost of risk management is lower than the expected benefits

c. Only when the cost of risk management is higher than the expected benefits

d. Always makes financial sense

Question 11: A project manager feels elated when a proposal to build a new product gets accepted even though it could make or break one's career. What is this person's approach to risk?

a. Risk-seeking

b. Risk-neutral

c. Risk-tolerant

d. Risk-averse

Question 12: A project manager has successfully identified risks and put in place suitable risk response strategies. However, these strategies have created new risks. What is the term for these risks?

a. Residual risks

b. Enhanced risks

c. Secondary risks

d. Unknown risks

Question 13: Calculate the expected monetary value (EMV) of a project that has a 95% chance of yielding $500,000 and a 5% chance of losing $200,000?

a. $455,000

b. $465,000

c. $475,000

d. $485,000

Question 14: Historically, organizations have not given importance to identify and manage risks. Now, risk management is being recognized and valued. It takes knowledge and talent to identify and manage project risks. Which activity below is not a part of project risk management?

a. Identifying the skills required for the project

b. Recognizing the shortage of a required skill

c. Preparing staffing plans to overcome the skill shortage

d. Analyzing the impact on project budget due to skill shortage

Question 15: An organization is planning to enter a new market with weak competition. Even though the organization is confident that it has made the right bet, a high degree of uncertainty exists. What is this organization's approach to risk?

a. It has a high risk tolerance

b. It has a high risk acceptance

c. It has a high risk appetite

d. It has a high risk utility

Question 16: Some members of your project team work in an area where the electricity supply is not stable. You have drafted a plan to order a power backup. What type of plan is this?

a. Fallback plans

b. Contingency reserves

c. Contingency plans

d. Management reserves

Question 17: As the project manager of an information technology project you evaluate the chance of any key employee leaving the project and whether that will have any impact on the schedule. What risk management process have you utilized?

a. Identifying risks

b. Planning risk management

c. Performing quantitative risk analysis

d. Performing qualitative risk analysis

Question 18: A project manager is preparing the risk register and is looking for any leading indicators of potential risk. What is the term for these indicators?

a. Switches

b. Checklists

c. Triggers

d. Watch list items

Question 19: Quantitative risk analysis involves numerically estimating the effects of risks on project objectives. Which one of the following is not a technique for quantitative risk analysis?

a. Decision tree

b. Simulation

c. Probability/impact chart

d. Sensitivity analysis

Question 20: The project manager decides to not upgrade to the new, unfamiliar operating system until the ongoing IT project is completed. What type of negative risk response strategy is this?

a. Risk mitigation

b. Risk transference

c. Risk acceptance

d. Risk avoidance

Reference no: EM13886903

Questions Cloud

Write the introduction section of your research proposal : How might these methodological considerations affect the research findings and the conclusions drawn from them and how does this article fit in with your paper? How did it influence your own ideas about your paper?
Find the probability that the opposing player : Rock Paper Scissors is a simple game in which two players compete by simultaneously choosing rock, paper, or scissors.
Sketch the mohr strain circle diagram : A solid is deformed under plane-strain conditions (εz = 0). The strains in the x-y plane are εx = 0.010, εy = 0.005, and γ xy = 0.007. A. Sketch the Mohr's strain circle diagram.
Describe the ethical environment that led to the fraud : Briefly describe the ethical environment that led to the fraud
What type of negative risk response strategy is this : The project manager decides to not upgrade to the new, unfamiliar operating system until the ongoing IT project is completed. What type of negative risk response strategy is this
Find the center mass : A thin rod sits along thexaxis with one end atx= -aand the other end atx=a, wherea=2.4m. The rod has anon-uniform densitygiven by(x+a)2, where=1.7kg/m3. I already got the total Mass= 62.669, but now I need to find the Center Mass.
Sketch the mohr circle diagram : A body is loaded under a stress state σx = 400, σy = 100, τ xy = 120, τ yz = τ zx = o z = 0. A. Sketch the Mohr's circle diagram.
What aspects of the process should the auditor understand : When testing accounts that are based on management estimates. As part of obtaining that understanding, what aspects of the process should the auditor understand?
Explain the role of professional skepticism in the context : Explain the role of professional skepticism in the context of evaluating management's explanations for their accounting for reserves in this context.

Reviews

Write a Review

Project Management Questions & Answers

  Aggregate planning for a bottling company

Aggregate Planning for a Bottling Company

  This assignment consists of two 2 sections an

this assignment consists of two 2 sections an infrastructure document and a revised gantt chart or project plan. you

  Show the project charter importance

How does a strong project sponsor and clear project scope apply to the overall success of a project?

  Distribution strategy and project management

Distribution strategy and project management

  Implementation of good disaster prevention procedures

A business disaster takes place when, despite the implementation of good disaster prevention procedures, normal business operations stop.

  Construct the network diagram

Construct the network diagram and find each activity's EST, EFT, LST adn LFT

  Prepare reflection report of entrepreneurship

You need to prepare reflection report of entrepreneurship - Reflection report is generally written to share the experience with others about a project, event, scene or interaction.We usually write about our experience & what we learned with the pro..

  Importance breakdown schedule in project management activity

Create the diagram, Create a work breakdown schedule and explain the importance within a project management activity.

  Why executives still seemed apprehensive after presentation

Discuss the main reasons why the executives still seemed apprehensive even after the consultant's presentation.

  Idenitfy an it project

Idenitfy an IT project that failed. Using the IT project risk framework, identify at least four explicit or implicit risks that may have impacted the project. For each of the risks you identify, provide an analysis of the risk, assign one of the Risk..

  A new medical office building using the lift slab process

Your company is building a new medical office building using the lift slab process. Using the lesson material and the OSHA website, describe four key elements with this process and the safety significance of the professional engineering.

  Extimate project effort

Explain how to estimate effort. Discuss why it is so important to estimate projects correctly, and why overestimating projects can be just as detrimental as underestimating them.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd