What pump power is required and what is the discharge

Assignment Help Civil Engineering
Reference no: EM13562528

1.A river flows towards a lake with a velocity of 3 m/s and rate of 500 m3/s at a location of 90 m above the lake surface. Determine the total power generation potential of the river at that location.

2.A fireboat draws seawater with density 1030 kg/m3 through a 20 cm diameter inlet pipe at a rate of 0.1 m3/s. It discharges through a nozzle of 5 cm diameter that is 4 m above sea level. If the head loss is 3m and the pump is 70 % efficient, what pump power is required and what is the discharge velocity.

3.A hydroelectric plant passes 8 million gal/min across a head of 600 ft. If the turbine is 80 % efficient and head loss in the system is 200 feet. What is the power output?

Reference no: EM13562528

Questions Cloud

What is the rate of water to be added to the tank : A hole at the bottom of a fish tank releases water at a rate given by the free jet equation. The hole at the bottom has a .5" diameter. If the water level is desired to be at 2' high and be at steady state, what is the rate of water to be added to th..
Calculate rate of change of water mass in the segment : The segment of river shown has a rectangular cross-section, with width 50 ft. The river bed is at angle ?=100 from horizontal. The average velocity is 2 ft/s at the upstream end (point 1), and 3 ft/s at the downstream end .The vertical depths are as ..
What values of a and b will minimize the variance of s : What values of a and b will minimize the variance of S? The answer to this question will take the from a equals a specific number and b equals a specific number.
Compute the maximum likelihood estimate of the probability : The article "Statistical Evidence of Discrimination" (Journal of the American Statistical Association, 1982, pp.773-783) reported that, prior to 1965 in a southern state, 25% of those eligible to serve on a grand jury were black
What pump power is required and what is the discharge : A hydroelectric plant passes 8 million gal/min across a head of 600 ft. If the turbine is 80 % efficient and head loss in the system is 200 feet. What is the power output?
Calculate the ground velocity of the plain : the air speed of a plane is 320km/h. A wind is blowing fromthe southeast at 129km/h. the piolet wishes to fly directly west. calculate the ground velocity of the plain
What is the discharge from the pipe : Flow occur  throught a sand-filled pipe with a cross-sectional area of 60 cm^2. If K is 10^-3 cm/s and the gradient is 0.01, what is the discharge from the pipe ?
Estimate the change in the internal energy of the water : One gram of water changes from liquid to solid at a constantpressure of 1.00 atm and a constant temperature of 0°C.  Find the change in the internal energy of the water
What is the hydraulic conductivity of the material between : Water seeps vertically downward from the bottom of a lake through a uniform material to an aquifer below. The discharge is 0.005 ft^3/s through a 1 ft^2 area of the lake bottom.

Reviews

Write a Review

 

Civil Engineering Questions & Answers

  What is the pm concentration in micrometers per dcsm

The total gas volume that flowed through the dry gas meter was 2.785 cubic meters (at T = 60 deg F and P = 800 mm Hg). The mass of PM (particulate matter) was 1.50 g. Also, 72.0 g of H20 was collected in impingers.

  Determine the minimum required vehicle frequency

A light rail route has 2 terminals and 4 intermediate stations. The demand (passengers/hr) for morning peak hour is: North Terminal Station 1 Station 2 Station 3 Station 4 South Terminal

  Calculate the saturated surface-dry bulk specific gravity

the weight of a sample of coarse aggregate was measured under various conditions with the following results: oven-dry weight in air 1076.3 g air-dry weight in air 1083.3 gsaturated-surface-dry weight in air 1089.2 g

  What is the change in internal energy of the system

What is the change in internal energy of the system? Assume the displacement work in a (fully resisted) constant pressure process is given by (*sub 12 means from stage 1 to 2) Wsub12=p(Vsub2-Vsub1).

  Determine vertical stress increment due to the strip load

Soil with a unit weight of 19.65 kN/m^3 is loaded on the ground surface by a strip load of 1.5 m wide. The strip load is 365 kN/m of wall length. Determine the vertical stress increment due to the strip load and the total pressure

  Comparative analysis of the types of safeguards

Provide a comparative analysis of the types of safeguards would you suggest for the company's information system.

  Determine the governing load combination for both moments

A beam that is part of a rigid frame has end moments and mid-span moments for dead, live, and earthquake loads. Determine the governing load combination for both negative and positive moments at the ends and mid-span of the beam.

  Find the horizontal and vertical components of reaction at a

The three hinged arch is composed of segments of a circle. Support points A and D are not at the same level. Determine (a) the horizontal and vertical components of reaction at A and D. (b) the shear, thrust, and moment in the arch at point C.

  Determine the streamlines for this flow plot streamlines

Consider the two-dimensional steady flow where the velocity field is given by V=Vo/L(-xi+yj) . Determine the streamlines for this flow. Plot streamlines for x> or =0

  Find the angle of rotation of the free end of the shaft

The solid compound shaft, made of three di¤erent materials, carries the two torques shown. (a) Calculate the maximum shear stress in each material. (b) Find the angle of rotation of the free end of the shaft.

  Three cylinders from the same mix were tested

Three cylinders from the same mix were tested for strenght.  Cylinders A and B were cast in 4x8 molds while cylinder C was cast in a 6x12 mold.  The total loads were as follows; cylinder A= 65,200 lbs.,  cylinder B= 68,550 lbs., cylinder C= 151,190 l..

  Determine the critical path-starting and finishing times

Activity Description Duration Immediate Predecessors ST Start milestone - Activity Description duration Inmdiate predesesor ST Start milestone - - A excavate st. 1 4 ST B Order & steel del. work 7 ST C Formwork st.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd