What power output may be expected from the turbine

Assignment Help Civil Engineering
Reference no: EM13540145

If the discharge is 500cfs, what power output may be expected from the turbine? Assume that the turbine efficiency is 90% and that the overall head loss is 1.5V 2/2g, where V is the velocity in the 7 ft penstock. Assume a=1.0 at all locations.

D=7ft diameter of pipe

30 ft to water surface in tank from datum

5 ft to water surface below where turbine is releasing water into from datum

Reference no: EM13540145

Questions Cloud

What do they estimate thhe acceleration due to gravity to be : In an experiment to estimate the acceleration due to gravity,a student drops a ball at a distance of 1m above the floor. His labpartner measures the time it takes to fall and obtains an estimateof 0.46s.
How long does it take to reach an altitude of 3000m : Missiles designed for defense against ballistic missiles haveattained accelerations in excess of 100g's or 100 times theacceleration due to gravity. Suppose that the missile
How many hours should it take an articulated wheel loader : How many hours should it take an articulated wheel loader equipped with a 4 yd bucket to load 3000 cu yd of gravel from a stockpike into rail cars
What will be the discharge : A concrete sewer pipe 1m in diameter is laid so it has a drop in elevation of 30cm per 300m of length. If sewage (assume the properties are the same as those of water) flows at a depth of 50cm in the pipe, what will be the discharge?
What power output may be expected from the turbine : If the discharge is 500cfs, what power output may be expected from the turbine? Assume that the turbine efficiency is 90% and that the overall head loss is 1.5V 2/2g, where V is the velocity in the 7 ft penstock. Assume a=1.0 at all locations.
The ratio of volumetric strain to diametral strain is : A w24x192 of a242 steel is to be used as a beam. what are the values of yield stress Fy ultimate tensile stees Fu and modulus of elasticity E for this beam?
What are the possible water levels in the tank at the end of : A cylindrical tank is used to store water for a town. on any given day, the water supply inflow per day may fill the tank with additional 6, 7, or 8ft of water
Find the stress in the cable when the truck comes : A tow truck is using a cable to pull a car up a 15 degree hill. If the car weighs 4000 lbs and the cable has a diameter of .75 inches, find the stress in the cable when the truck comes to a stop while on the hill. Ignore friction between the car and ..
Will the pesticides threaten the fish population during the : In the summer, the density at the top of the lake is 997 kg/m3, and at the bottom is 1000 kg/m3. Would you predict stratification to be present, and if so assume an epilimnion depth of 4m. Will the pesticides threaten the fish population during the s..

Reviews

Write a Review

 

Civil Engineering Questions & Answers

  What is the maximum height

The height (in meters) of a projectile shot vertically upward from a point 2 m above ground level with an initial velocity of 24.5 m/s is h2+24.5t-4.9t^2 after t seconds. a) When does the projectile reach its maximum height? b) What is the maximum..

  What is the highest possible design speed for the curve

design a horizontal curve for a two-lane road. The road has 12-ft. lanes. Due to expansive excavation, it is determined that a maximum of 34 ft. can be cleared from the road's centerline toward the inside lane to provide for stopping sight distanc..

  Four-lane highway for adequate ssd

A horizontal curve was designed for a four-lane highway for adequate SSD. Lane widths are 12 feet, and the superelevation is 0.06 and was set assuming maximum fx.

  Determine what was the distance between the markers

A 100 ft cut steel tape was used to measure between two property markers. The rear surveyor held 93 ft, while the head surveyor cut .67ft. What was the distance between the markers

  Determine the required length of superelevation runoff

A simple highway curve is planned to connect two horizontal tangents that intersect at sta. 2500+00.00 at an external angle of 52°. For a design speed of 60 mi/h and a curve radius of about 1.25 times the minimum allowable

  Calculate the maximum tensile load in n

Consider a cold worked C11000 copper alloy rod 21 mm in diameter and 250 mm in length. Calculate (a) the maximum tensile load, in N, and (b) the maximum length, in mm, to which the rod may be stretched without plastic deformation.

  What are the total heads given by piezometers b and c

The total heads given by piezometers A and D are 98.9 cm and 3.6 cm, respectively. What are the total heads given by piezometers B and C?

  Determine kinetic energy after the stream has slowed down

A section view of a dam shown and water is stored at an elevation of 6 m above the base. the water flows through the dam in a concreate opening 2m high and 3 m wide. there are no losses or friction.

  What is the change in it internal energy

A gas is compressed at a constant pressure of 0.800 atm from 9.00L tp 2.00L. in the process, 400J of energy leave the gas by heat. (a) What is the work done on the gas? (b) What is the change in it internal energy?

  Describe why materials such as aluminum-steel and basswood

1. Describe why materials such as aluminum, steel, basswood, and Polystyrene Plastic and structures are important in our everyday lives. 2.Write a paragraph to explain to a lay person a few of the important factors

  Define materials to construct an industrial building

Materials To Construct An Industrial Building, A small building can be constructed of steel or wood framing. A decision is made to use steel for fire resistance.

  Compute the elastic modulus and the shear modulus

a cylindrical specimen of a metal alloyed in stressed in compression. If its original and final diameters are 40.00 and 40.10 mm, respectively , and its final length is 120.00 mm, compute its original length(L0)

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd