Suppose a project team has arrived at the following time estimates for an activity: a = 3 days, m = 6 days, and b = 8 days. What is the variance involved in this activity?

a.
0.694

b.
0.111

c.
0.250


d.
0.833

 

 

Reference no: EM13221535

Questions Cloud

Why countries will agree to lower the price of oil : If a few oil-producing countries in the Middle East decide to jointly limit the production of oil, how they will agree to lower the price of oil in order to increase their profits. they are forming a cartel. they would like the price of oil to be ..
What are the legal obligations : What are the legal obligations if any under the lease contract?
Explain the isothermal compressibility of graphite : The isothermal compressibility of graphite is 1.56 × 10-7 bar-1. At what pressure is density equal to density of diamond?
What is the z value for the target completion time : Analysis of the activity network reveals an estimated project completion time of 145 working days with a project variance of 400. What is the z value for the target completion time of 180 working days? Find the closest value.
What is the variance involved in this activity : Suppose a project team has arrived at the following time estimates for an activity: a = 3 days, m = 6 days, and b = 8 days. What is the variance involved in this activity?
Define concisely why carbon has two electrons in different : Explain concisely why carbon has two electrons in different p orbitals with parallel spins rather than other possible arrangements.
Write an essay to explain why best buy have failed overseas : Write an essay to explain why Best Buy have failed overseas.
How many units will the firm produce in the short-run : Given below are the cost schedules for a perfectly competitive firm. Average Average Variable Total Marginal Quantity Cost Cost Cost 1 $ 50 $ 90 $ 50 2 45 65 40 3 40 53 30 4 35 45 20 5 34 42 30 6 35 41 40 7 37 43 50 8 40 45 60
Explain preferable to use a metal ion buffer to achieve : Why is it preferable to use a metal ion buffer to achieve pM = 7, rather than just dissolving enough M to give a 10-7 M solution?

Reviews

Write a Review

Operation Management Questions & Answers

  Implementation of such systems have a high rate of failure

Although ERP (Enterprise Resource Planning) Systems are a great concept. Implementation of such systems have a high rate of failure and often after such systems are installed the results may not be as desired

  Illustrate what is probability which both are defective

Compute forecast for 11th month using Exponential Smoothing Method in case smoothing component, α=0.20. illustrate what is probability which both are defective.

  Discuss the common sources of risk on information technology

Discuss the common sources of risk on information technology projects and suggestions for managing them. Which suggestions do you find most useful?

  How mnc managers manage conflict

How do MNC managers manage conflict? Compare or contrast managing conflict resolutions using the instrumental-oriented conflict approach and the expressive-oriented conflict approach

  Explain how can organisations strike a balance

Explain how can organisations strike a balance among respecting and meeting the needs of a diverse workforce and shaping a high-performance corporate culture where shared values contribute to the accomplishment of strategic goals.

  Compute average utilization of the employee

Assume a drive-up window at a fast food restaurant. The exact interarrival time and service time distributions are not known, but the average and std deviation has been measured.

  Team leader under your supervision has made a mistake

You're a manager in Japan, and you've just discovered that a team leader under your supervision has made a mistake that will result in a quality problem. How will you handle this mistake?

  Punch multiple parts from a sheet of aluminum

You punch multiple parts from a sheet of Aluminum. The sheet is a 1728 square-inches rectangle and you get 18 parts that are 70 square-inches each.

  What is the average time between orders

Calculate the item's EOQ. What is the average time between orders, find the safety stock and reorder point that provide a 95% customer service level

  Explain a participative approach to safety improve

Explain however, a participative approach to safety improvement means employees time away from their duties and decreased productivity. Do you think the trade-off may worth it. Why or why not.

  Evaluate the challenges that for-profit public companies

Evaluate the challenges that for-profit public companies face from recurrent scandals, political attacks and alternative corporate structures such as the B-corp

  Creating 95 percent confidence interval

A study was done to examine whether the perception of service quality at hotels differed by gender. Hotels were randomly selected to rate service items on a 50point scale.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd