What is the schedule performance index

Assignment Help Project Management
Reference no: EM13831713

Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

1) Using the 50-50 Rule, what is earned value for this project?

2) Using the 0-100 Rule, what is earned value for this project?

3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.

4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?

5) What is the schedule performance index (SPI)?

6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?

7) What is the cost performance index (CPI)?

8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Reference no: EM13831713

Questions Cloud

The role of water committees in post-civil war ivory coast : Write a single paragraph in which you identify and explain the report's main point concerning the role of water committees in post-civil war Ivory Coast
Form of capital you would rely on for emotional support : Discuss which form of capital you would rely on for emotional support and help through difficult times if abused. Explain your rationale
Law of commercial association : On 1 February 2009, Ajax, Sandra and Tanya entered into a partnership agreement to operate a seafood restaurant situated in a very advantageous position in a large shopping mall in Sydney.  They leased the premises from West Wings Ltd, the shoppin..
9 ground rules for effective groups : Group leader/facilitator how you can use the "9 Ground Rules for Effective Groups"  described in detail to improve the effectiveness of the group
What is the schedule performance index : Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported? What is the schedule performance index (SPI)? Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported
Income statement-statement of retained earnings : The following list, in alphabetical order, shows the various items that regularly appear on the financial statement of Maple Park Theatres Corp. The amounts shown for balance sheet items are balances as of September 30, 2014
Way to identify business ideas : The most common way to identify business ideas quickly is through and Organizational feasibility analysis is conducted to determine whether
Calculate the effect on superego ltds profit : Calculate the total amount allocated to the Audit department and Calculate the total dollar amount of Supervisions cost that would have been allocated to the Shapez product line, if activity-based costing had been used in the last quarter.
Estimate rio required rate of return : 1. Calculate the future sums of the following two schemes. Each makes contributions of $400 per month over 40 years. One is invested in a balanced portfolio that earned on average 7.2% per annum (after fees) and the other is invested in a growth port..

Reviews

Write a Review

 

Project Management Questions & Answers

  Wbs for crm implementation in ms projectsin the past you

wbs for crm implementation in ms projectsin the past you created a work breakdown structure for the entire crm system

  Manage project communications

Manage Project Communications - Explain the tools a project manager may use to control and manage project communications.

  Determine the critical path and project duration in days

Determine the critical path and project duration in days and given that each resource is assigned 100% to each task, identify the resource constraints.

  Country is the phillipines

Country is the Phillipines

  Communication in the workplacehow do leaders use

communication in the workplacehow do leaders use communication to influence and persuade others and think of someone

  Determine when it is time to re-evaluate the usefulness

To determine when it is time to re-evaluate the usefulness of the exponential smoothing model you compute tracking signals. What is the tracking signal? What does the tracking signal tells you?

  Accounting project - financial analysis real life

accounting project - financial analysis real life decisionwe must come up with a real life financial situation and

  Show the issue of us health care labor shortages

Show the issue of US health care labor shortages, socio-demographics changes (e.g. aging of America), and their impact on access to quality care.

  Outline the seven sources of conflict arise during a project

Outline the seven sources of conflict that can arise during a project. Discuss the five approaches that people typically use to deal with conflict.

  You are preparing a project to lay fiber optic cableyou are

you are preparing a project to lay fiber optic cable...you are preparing a project to lay fiber optic cable. the first

  Nowadays many business organizations adopt

nowadays many business organizations adopt management-by-project approach to manage their business. for an

  Project threatswhat evaluates the likelihood of occurrence

project threatswhat evaluates the likelihood of occurrence on projects and what gives a risk high priority status and

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd