At Ionic, a large retailer of popular electronics, demand is constant at 32,000 devices per year. The cost of placing an order to replenish stock is $10, and annual cost of holding a device is $4 per device. Stock is received 5 working days after an order has been placed. No backordering is allowed. Assume 300 working days a year.
a. What is Ionic's optimal order quantity?
b. What is the optimal number of orders per year?
c. What is the optimal interval (in working days) between orders?
d. What is demand during the lead time?
e. What is the reorder point?
f. What is the inventory position immediately after an order has been placed?
Illustrate what is a vehicle for communicating proprietary information with authorized users outside organizational boundaries.
Apply critical path method and probability analysis to the case study. Identify critical activity and critical path and find the minimum project completion time.
Analyze the environment, processes, and procedures at your work or school to determine which aspects can be controlled and which cannot be controlled. Explain your rationale.
Products range from small portable high-pressure washers to large industrial installations for snow removal from vehicles stored.
Is it ethical to use design elements also special effects to persuade an audience. Explain why or explain why not. Please feel free to use an example.
Compute the probability of four or more students being in line or being served. Before a test the arrival of students increases to six per hour on the average. Illustrate what does this do to the average length of the line.
Formulate and solve, by hand, using the Simplex method the above as a Linear Programming problem in order to maximise profit for the restaurant.
Illustrate what a manager can do to diagnose also improve motivation. Consider when a group or team is involved explain how this differs from when just individuals are involved.
When applied to non-management employees, which of these has a relatively WEAK connection between the reward and individual effort?
Estimated time for critical path is 120 days. Sum of all activities variances is 64, while sum of variances along activities path is 36. Probability which project will be completed among 108 also 120 is?
Technology has changed the role and some functions of HR. Have these changes resulted in HR losing sight of its role towards employee relations and support?
Describe at least one advantage or disadvantage of the LLC form for the company.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd