What is the remaining duration for the project overall

Assignment Help Operation Management
Reference no: EM131036950

1. Determining Critical Path and Activity Slack

Assume we have a set of activities, their expected durations, and immediate predecessors. Enter this information using MS Project to produce a Gantt chart - enable project summary.

(a) Identify the critical path.

(b) Identify activity slack times that are non-zero and record in the table below.

Activity

Duration
(days)

Predecessors

Free Slack

Total Slack

A

6

....

 

 

B

7

 

 

 

C

5

A

 

 

D

3

A, B

 

 

E

4

C

 

 

F

5

D

 

 

G

8

E, F

 

 

H

3

F, G

 

 

Now, now assume that activity C has taken 8 days past its anticipated duration to complete.

(c) How does the project's schedule duration change?

(d) Why does the duration change?

(e) Is there a new critical path? If so, what is it?

2. Refer to the task/activity table shown here.Enter this information using MS Project to produce a Gantt chart - enable project summary. Assume that each resource has been assigned to the project activity on a full-time basis.

Construct System 20 days Design System Harry Smith, Biil Plant
Test System 10dyas Gather Requirements, Construct System (FS with minus 10 day lag/lead) Kate Stone, Bill Plant
Revise System from Test 5days Test system Harry Smith, Biil Plant
Deploy System s days Revise system from test Ryan Burns

(a) Using the above information, produce a resource usage sheet identifying the total number of hours and daily commitments of each project team member. Record the total hours for each resource.

Resource

Hours

Bill Plant

 

Harry Smith

 

Kate Stone

 

Ryan Burns

 

Sue Peterson

 

(b) Identify any members of the project team who have been overassigned.

(c) Determine and record the specific dates when there is a conflict in the resource assignment schedule.

(d) Using the information above, describe how you could level the resource load to remove conflicts? What is affected by the change? What assumptions are made?

3. Use the following information to construct a tracking Gantt chart using MS Project - enable project summary.

Activities Duration Preceding Activites  Percent Complete
A 2 days None 100%
B 4 days A 100%
C 6days B 35%
D 3days B,C 0%
E 4 days B 0%
F 5 days C,E 0%

(a) What is the total % complete for the project overall?

(b) What is the Actual Duration for the project overall?

(c) What is the Remaining Duration for the project overall?

4. Assume you have collected the following data for your project. The roject budget is $90,000 and it is planned to last a total of 120 workdays. After collecting status partway through the project., you have collected the following status information,

PV = $100,000

EV = $80,000

AC = $65,500

Schedule Performance Index(SPI)
Estimated Time to Completion

Cost Performance Index(CPI)
Estimated Cost to Completion

Based on these values, estimate the time and budget necessary to complete the project.

(a) Describe how would you evaluate these findings? Are they good news or bad news?

(b) What could possibly cause this situation to occur? Be specific with examples.

Reference no: EM131036950

Questions Cloud

Discuss whether assets should be measured at historical cost : In answering the following questions, choose either property, plant and equipment or financial assets- With reference to the article discuss whether assets should be measured at historical cost or fair value
Determine the magnitude of the total velocity of b : Assume that the cable between B and the pulley remains vertical and solve for a given value of x.
Analyze local impact of global public administration policy : Analyze the local impact of global public administration policies and relationships. Analyze the core controversies, theories and rationale surrounding global public administration.
Determine the velocity v when the acceleration is 3 m/s2 : The position s of a particle along a straight line is given by where s is in meters and t is the time in seconds. Determine the velocity v when the acceleration is 3 m/s2
What is the remaining duration for the project overall : Based on these values, estimate the time and budget necessary to complete the project. Describe how would you evaluate these findings? Are they good news or bad news? What could possibly cause this situation to occur? Be specific with examples.
What is the absolute speed of the ball : The speed of the ball relative to the quarterback is 60 ft/sec. What is the absolute speed of the ball? Treat the problem as two-dimensional.
Creative thinking skills and achievement in e-learning : My Research topic is: The Impact of Flipped Classroom via Edmodo Platforms on Increasing Student's Creative Thinking Skills and Achievement in E-Learning Course at Jeddah University.
Determine the coordinates of the point : A golfer is out of bounds and in a gulley. For the initial conditions shown, determine the coordinates of the point of first impact of the golf ball. The camera platform B is in the plane of the trajectory.
What is the legal affect of stamping the specifications : CSM8003 & CMS800003 - CONSTRUCTION LAW. In the case can the specifications in the contract vary the written terms of the contract Describe the Legal Principles applicable and the hierarchy of contract documentation. What is the legal affect of st..

Reviews

Write a Review

Operation Management Questions & Answers

  Decision based on an expected monetary value criterion

What is the best decision based on an expected monetary value criterion? (Note: You want the lowest EMV because we are dealing with costs in this problem.)

  Miracle energy supplement attached is the full infor

Miracle Energy Supplement Attached is the full information. All that is needed is atleast 3 paragraph Based on your research, understanding, and the scenario, answer the following questions: What violations has Mega Beverage Company committed in its ..

  Why is it difficult for labor negotiators to switch

Why is it difficult for labor negotiators to switch from traditional to integrative bargaining? What recommendations would you make for negotiators trying to make this switch

  Teamwork and taskwork

Teamwork and Taskwork: Explain how and with whom you would like to discuss your performance and progress toward achieving goals in the workplace. Explain with whom you would like to coordinate and integrate your work efforts in an organization and wh..

  How much a company pay to keep specially skilled worker

How much should a company pay to keep a specially-skilled worker? Why? How would you determine the amount to pay to keep such a worker?

  Calculating number of vats

A machine cell uses 242 pounds of a certain material each day. Material is transported in vats that hold 12 pounds each. Cycle time for the vats is about two hours.

  Unrelated product diversification

Unrelated product diversification (conglomeration) is widely discredited in developed economies; however, in some cases it appears to add value in emerging economies. Is this interest in conglomeration likely to hold or decrease in emerging economies..

  Your uncle promises to give you 550 per quarter for the

your uncle promises to give you 550 per quarter for the next five years starting today. how much is his promise worth

  Why was there conflict when these cultures interacted

After reading Course Lectures 1-4 and completing activities 1.2 - 1.4 in the textbook, compare and contrast the societies of West Africa, Europe, and the Americas at the time when Christopher Columbus made his first voyage to America in 1492. How wer..

  When putting together the communication plan

When putting together the communication plan, think about how you would want the team to communicate with each other, with management, and with stakeholders. What templates and tools would be most helpful? Look through the Project Management Communic..

  How quality is defined

Analyze and evaluate how quality is defined, measured, and reported with regards to the SPO Model- How quality is defined? How quality is measured

  Characteristics of the distributive bargaining

From the first e-Activity, examine the characteristics of the distributive bargaining used in this specific negotiation. Compare and contrast the use of various power tactics in the negotiation. Select the power tactic that you deem to be the most..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd