What is the projected length of the project

Assignment Help Project Management
Reference no: EM131305114

Part 1

This part of the paper requires you to apply your understanding of project management as a whole through the following scenario.

Scenario

Assume you've started a small, one-person project management consulting firm. Your first two clients asked you similar but different questions. These two clients are friends with each other who want to see how you answer both of their questions. To this end, these clients requested-and you agreed-that you answer their questions by comparing and contrasting your recommendations for using project management in response to the following 2 questions.

Client # 1 (Jack): Do I need to bother with project management if I'm only going to build a single birdhouse to put in my backyard?

Client # 2 (Diane): Do I need to bother with project management if I'm only setting up an additional, new production line for a product we already produce?

Since your clients are busy, they asked-and you, once again, agreed-that your response not exceed 3 double-spaced pages which include any models, diagrams, and/or tables using a 12-point font and finch margins.

Instructions

1. First, review the rubric for this part of the exam which is attached with the exam as well as included as part of the assignment for this part of the exam.

2. Second, answer your clients' question in the manner indicated in the above scenario.

3. Last, post your material using the appropriate link in Blackboard.

Part 2

A third client came to your consulting firm with a different request. Ms. Prynne's company charged her with determining the length of time a new project will take to complete and the "critical path" (which Ms. Prynne does not know what means) the project manager (aka Ms. Prynne) should watch carefully during the execution of the project.

Background

Ms. Prynne was promoted to be the project manager for a project that updates the baggage control system at the local airport. At the present time, Ms. Prynne is interested in learning more about project management and wants to learn the needed skills to properly conduct a time analysis. To this end, Ms. Prynne asked that you complete an AON diagram and accompanying data table which she will study and ask any questions necessary for clarification. The work package predecessors and duration estimates (given in weeks) as listed below are all the details Ms. Prynne has at the moment. [NOTE: This table is duplicated in the MS Excel spreadsheet which accompanies this exam.]

Exam

Instructions

1. First, review the rubric for this part of the exam which is attached with the exam as well as included as part of the assignment for this part of the exam. 2. Second, perform the following tasks and answer the questions as appropriate. a. Open the Excel file named "Final Exam Part

2 start". b. On the one spreadsheet in this file, complete an Activity-on-Node network diagram which reflects the material in the "Data Table". c. Enter the correct information in the remaining columns in the Data Table. Below the Data Table, answer the following questions. d. What is the critical path? e. What is the projected length of the project (in weeks)? f. What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks? 3. Last, post your material using the appropriate link in Blackboard.

Work
Package

Predecessor

Duration
(in weeks)

A

--

2

B

A

2

C

A

3

D

A

4

E

B

2

F

C

3

G

D

6

1-1

E, F

2

I

E, F

5

J

G, I

1

K

H, J

2

Instructions

1. First, review the rubric for this part of the exam which is attached with the exam as well as included as part of the assignment for this part of the exam.

2. Second, perform the following tasks and answer the questions as appropriate.

a. Open the Excel file named "Final Exam Part 2 start".
b. On the one spreadsheet in this file, complete an Activity-on-Node network diagram which reflects the material in the "Data Table".
c. Enter the correct information in the remaining columns in the Data Table. Below the Data Table, answer the following questions.
d. What is the critical path?
e. What is the projected length of the project (in weeks)?
f. What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks?

3. Last, post your material using the appropriate link in Blackboard.

Attachment:- Project_Part_2_Start.xlsx

Reference no: EM131305114

Questions Cloud

Does a market maker have different responsibilities : Does a market maker have different responsibilities than a financial firm that is providing investment advice for clients?
Deal for an investor than a simpler product : Why would a more complex financial product be likely to be a worse deal for an investor than a simpler product?
What is the relevant yield : Alpha Bonds have a coupon rate of 7% with semiannual coupon payments, a face value of $1,000, and 6 years to go until maturity. Gamma Bonds have a coupon rate of 12% with semiannual interest payments, a face value of $1,000,and 20 years to go until m..
Evaluate the impact of contemporary hr practices : Have a clear understanding of, and an ability to critically evaluate HRM and its role within the organisation and the wider the global environment - Be able to critically evaluate the main processes of employee resourcing, development, relations a..
What is the projected length of the project : What is the projected length of the project (in weeks)? What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks?
End inventory level and inventory turnover ratio : Charlie's Cycles Inc. Has $110 million in sales. The company expects that its sales will increase 5% this year. Charlie's CFO uses a simple linear regression to forecast the company's inventory level for a given level of projected sales. Given the es..
Price of call option on the stock that has a strike price : Binomial Model The current price of a stock is $15. In 6 months, the price will be either $20 or $13. The annual risk-free rate is 4%. Find the price of a call option on the stock that has a strike price of $14 and that expires in 6 months.
Write a program that simulates multiple games of blackjack : Blackjack (twenty-one) is a casino game played with cards. The goal of the game is to draw cards that total as close to 21 points as possible without going over. All face cards count as 10 points, aces count as 1 or 11, and all other cards count t..
Call option on the stock that has a strike price : The current price of a stock is $22. In 1 year, the price will be either $28 or $15. The annual risk-free rate is 6%. Find the price of a call option on the stock that has a strike price is of $25 and that expires in 1 year.

Reviews

Write a Review

Project Management Questions & Answers

  Describe role of operations management in organizations

Develop a business model with a sustainable competitive advantage and develop a strategic plan and describe the role of operations management in business organizations.

  What type of targeting strategy is jordans furniture using

What type of targeting strategy is Jordan's Furniture using?- Describe and evaluate the company's target market.

  Prepare a cost analysis

Prepare a cost analysis of the above items relating to the library project so we have hard numbers to work with and have a monetary value for reporting and audit purposes.

  Manufacturer of automobiles in the united kingdom

UK Motors, the largest manufacturer of automobiles in the United Kingdom, has been famous for building reciprocating automobile engines that produce minimal noxious emissions.

  Identify between three and eight primary duties

Identify between three and eight primary duties and responsibilities for the position.- List the primary duties and responsibilities in order of importance.

  Evaluating current npv biased

Is the 14.5% cost of capital a real or nominal rate? Is the current NPV biased, and if so, in which direction?

  How to crash project to keep project on schedule

How would you crash project (which activities would you crash) to keep project on schedule and get original duration, if Activity B actually takes 5 weeks instead of planned 3 weeks?

  What is the theoretical minimum number of workstations

Draw a precedence diagram of this operation. -  Given the demand, what is the cycle time for this operation? - What is the theoretical minimum number of workstations?

  How much testing is enough when launching a new product

How much testing is enough when launching a new product?- How can the interests of multiple stakeholders be balanced?

  Define the feasible region of a graphical lp problem

Explain why solutions to linear programming problems focus on corner points ? Define the feasible region of a graphical LP problem. What is a feasible solution?

  Explain the two types of jurisdiction that a court must have

Explain the two types of jurisdiction that a court must have to hear a case and render a binding decision over the parties.

  Draw a stock control card and discuss the completion process

Draw a stock control card and discuss the completion process

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd