1. In a strong matrix structure, employees take daily direction from:

  1. Project manager only
  2. Both, but the project manager has greater influence
  3. Both, but the functional manager has greater influence
  4. Functional manager only

2. If the schedule variance is positive and the cost variance is negative, the project's status is:

  1. Over budget and behind schedule
  2. Under budget and ahead of schedule
  3. Over budget and ahead of schedule
  4. Under budget and behind schedule

3. Which category of projects would involve a large number of functional units where the workers may be assigned either part-time or full-time?

  1. Special
  2. Individual
  3. Staff
  4. Matrixed

4. Which type of chart provides the least "predictive" value?

  1. PDM
  2. ADM
  3. PERT
  4. Bar chart

5. Scope creep is generally the result of:

  1. Too much detail in the specifications
  2. Having too many levels in the WBS
  3. Poorly defined SOW
  4. Having the wrong people assigned to the project

6. Which of the following is the role of the PM rather than the role of the functional manager?

  1. Where it will be done
  2. How the work will be done
  3. Who will do it
  4. What work will be done

7. The balance between quality and cost is called:

  1. Produceability
  2. Salability
  3. Availability
  4. Operability

8. The EVMS term that represents the value of work actually accomplished is:

  1. BAC
  2. AC
  3. EV
  4. PV

9. Which of the following would be the first item to be discussed in the initial kickoff meeting for a project?

  1. Understanding of the budget
  2. Understanding of the schedule
  3. Understanding of the requirements
  4. Understanding of the plan

10. Quality is defined by the:

  1. Project team
  2. customer
  3. Project manager
  4. Project sponsor

11. Which of the following people has the greatest influence on how much authority a project manager will possess on a given project?

  1. The project sponsor
  2. The customer
  3. The project manager's line manager
  4. The project manager himself / herself

12. A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by:

  1. Customer
  2. Subject matter experts
  3. Project manager
  4. Project sponsor

13. In which project life cycle phase does quality begin?

  1. Initiation / planning
  2. Monitoring & control
  3. Closure
  4. Implementation

14. Project management restructuring allowed companies to manage projects that _____.

  1. Had undefined objectives
  2. Could not be handled by the traditional organization
  3. Did not require effective cost control
  4. Require little functional integration

15. Risk constitutes a lack of knowledge _____.

  1. Of future events
  2. About the estimates
  3. About the customer's requirements
  4. About the environment

16. The two primary components of a risk are:

  1. The probability and the impact
  2. The impact and the event
  3. The impact and the amount at stake
  4. The event and the probability

17. Which of the following standard project estimating techniques is usually accomplished in weeks?

  1. Engineering
  2. Parametric
  3. Analogy
  4. Grassroots

18. The hardest part in creating a best practices library is:

  1. Storage
  2. Classification
  3. Evaluation
  4. Knowledge transfer

19. A typical project office (not to be confused with a project management office) responsible for the management of a large project includes the project manager and the:

  1. Project sponsor and assistant project managers
  2. Assistant project managers
  3. Assistant project managers and functional managers
  4. Project sponsor

20. Industries that have _____ tasks and operate in a _____ environment demonstrated the greatest need for project management.

  1. Complex; Dynamic
  2. Simple; Static
  3. Complex; Static
  4. Simple; Dynamic

21. Pricing out the construction cost of a home by a cost per square foot would be representative of a(n) _____ estimate.

  1. Grassroots
  2. Parametric
  3. Engineering
  4. Analogy

22. The collective term for the formal quality activities and processes is called:

  1. Quality control
  2. Quality visions
  3. Quality assurance
  4. Quality policies

23. The difference between the cost baseline and the contracted cost is the:

  1. Profit
  2. Management reserve
  3. Cost of scope changes
  4. Cost at completion

24. Plans such as the cost plan, schedule plan and quality plan are referred to as:

  1. Subsidiary plans
  2. Specialized plans
  3. Integration plans
  4. Functional plans

25. Companies can become reasonably mature in project management by designing the right support systems. In general, how much time usually elapses after maturity before a company becomes excellent in project management execution?

  1. 2 years
  2. 1 year
  3. 5 years
  4. 10 years

26. The best source of revenue for a customer-requested scope change is:

  1. A customer-funded contract amendment
  2. Profits
  3. Management reserve
  4. Undistributed budget

27. During the 1970s and 1980s, formal project management practices were put in place because the constraints were _____ and _____ boundaries had to be crossed

  1. Tight; few
  2. Tight; several
  3. Loose; few
  4. Loose; several

28. A charting technique designed to illustrate the inductive and deductive reasoning necessary to achieve some objective is called a _____ Diagram / network

  1. Descriptive
  2. Intuition
  3. Gantt
  4. Logic

29. Which of the following is often overlooked when planning and budgeting a project?

  1. Customer's milestones
  2. Timing of the deliverables
  3. Number of meetings with the customer
  4. Cost and size of contractual documentation

30. What is the project sponsor's responsibility with regard to the WBS preparation?

  1. The sponsor should not be involved in WBS development.
  2. Make sure all work packages are well-defined.
  3. Make sure that the management levels of the WBS are correct.
  4. Make sure that the technical levels of the WBS are correct.

Reference no: EM13822998

Questions Cloud

Explain judith butler concept of gender performativity : Objective: Explain Judith Butler's concept of gender performativity. Social constructionism is the notion that people's understanding of reality is partially, if not entirely, socially situated
Describes the structures of experience : What research method describes the structures of experience (AKA meanings) as they present themselves to consciousness, without recourse to theory, deduction, or assumptions from other disciplines?
A rental car manager estimates the number of full-size sedan : A rental car manager estimates the number of full-size sedans rented per week so that she can maintain adequate number of cars in the lot. Data for the past 10 weeks are shown here
Describe the four layers of earth''s atmosphere : Explain why Earth's temperature changes with latitude and with the seasons. Describe the four layers of Earth's atmosphere.
What is the project sponsors responsibility : What is the project sponsor's responsibility with regard to the WBS preparation? Which of the following is often overlooked when planning and budgeting a project? Which of the following standard project estimating techniques is usually accomplished i..
Data collection methods and preliminary findings. : Based on content requirements of your project 4, post a brief (4-5 slides) PowerPoint presentation describing your project 4.  Tell us about the organization (maintaining confidentiality), the focal problem you are investigating, causes of the proble..
Discuss the various ways that hazardous chemicals can enter : Discuss the various ways that hazardous chemicals can enter the human body. Discuss safe practices that can be used for working with chemicals in laboratories
What economic theory states and predicts about the issue : Discuss the model or economic theory that relates to the issue presented in the news article. Discuss what economic theory states and predicts about the issue presented in the news article.
Define the term innovation : Define the term innovation. Then, research what you think is an example of an innovative product or service. Include the following within your discussion: What is your product, and why do you feel the product you have selected is innovative within ..

Reviews

Write a Review

Project Management Questions & Answers

  Q1a describe and compute the followingbull designed

q1a describe and compute the followingbull designed capacitybull effective capacitybull actual outputbull

  First step in the project management cycle

What is the first step in the project management "cycle"?

  Show the example of poor communication

Prepare a scenario that outlines an example of poor communication in a medical office setting to resolve an issue among co-workers

  Project management

Do you think by informing the customer that you need more time for a project or the quality of the system would be diminished, they will give you more time?

  Accounting project - financial analysis real life

accounting project - financial analysis real life decisionwe must come up with a real life financial situation and

  Operations management - production facility locationwhere a

operations management - production facility locationwhere a production facility is located can have a significant

  Research to find two metrics along with the affiliated

Research to find two metrics along with the affiliated measure used by the company and two project key performance indicators used by a particular industry or company. Describe the metrics and indicators identified.

  Presentation for senior management outlining

Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan

  Calculate the project duration

Prepare a network diagram for activities using Microsoft Project and calculate the Project Duration.

  Find break-even point and dollar sales volume

What is the break-even point in units for the company and what is the dollar sales volume the firm must achieve to reach the break-even point

  Concentrate this modules area of research on microsofts

concentrate this modules area of research on microsofts risk management approach. write a 1-2 pages apa style paper

  A software project requires a complex set of actions and

a software project requires a complex set of actions and people interactions with diverse skills and knowledge. as also

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd