What is the normal time for the operation

Assignment Help Project Management
Reference no: EM131258497

Refer to Problem:-

a) If the allowance factor is 15%, what is the standard time for this operation?

b) If the allowance factor is 18% and the performance rating is now 90%, what is the standard time for this operation?

Problem
If Charlene Brewster has times of 8.4, 8.6, 8.3, 8.5, 8.7, and 8.5 and a performance rating of 110%, what is the normal time for this operation? Is she faster or slower than normal?

Reference no: EM131258497

Questions Cloud

Analyze two essential public health care services found : Examine the involvement of both the Environmental Protection Agency (EPA) and the Occupational Safety and Health Agency (OSHA) in health care. Interpret the extent to which the involvement of each agency improves the federal government's response ..
What is the normal time for the operation : If Charlene, the worker in Problem 10.13, has a performance rating of 90%, what is the normal time for the operation?
Freedom-dependency spectrum : Essay: Compare two political candidates of your choice, on different ends of the Freedom vs. Dependency spectrum. Use quotes from the candidates to verify their respective positions.
Identify when people from the given region immigrated : Choose 1 regional group from the list above. Identify when people from this region immigrated. Describe the reasons why they left their home country or countries.
What is the normal time for the operation : If Charlene Brewster has times of 8.4, 8.6, 8.3, 8.5, 8.7, and 8.5 and a performance rating of 110%, what is the normal time for this operation? Is she faster or slower than normal?
Review the 2014 statement of cash flow budget : Review the 2014 Statement of Cash Flow budget. Based on your research, write a report that indicates whether you believe the cash from operations will increase or decrease.
Determine the shear stress distribution from the shear force : The figure shows a thin-walled C-shaped channel section loaded by a downward force P with line of action coinciding with the web of the channel section
Determine the average time and the normal time : Determine the average time, the normal time, and the standard time taken by her, using a performance rating of 95% and a personal allowance of 8%.
Create a program for an automatic teller machine : Write a program for an automatic teller machine that dispenses money. The user should enter the amount desired (a multiple of 10 dollars) and the machine dispenses this amount using the least number of bills.

Reviews

Write a Review

Project Management Questions & Answers

  Conflict managementchannels of communicationgive three

conflict managementchannels of communicationgive three examples of behaviors that indicate the existence of conflict

  Business communication

Business Communication can make or break profitability - Give specific examples of how you could apply the tips and principles to become a better communicator.

  A project can be closed for several reasons.

A project can be closed for several reasons.

  Equivalent units of production for material

What were the equivalent units of production for materials for the month of January?

  Which project seems to have the highest development risk

Which project seems to have the highest development risk? Which project would make it to the market the quickest? Why would a project be concerned about the time it takes to get to the market

  Issues when there is no follow-on projectwhat problems may

issues when there is no follow-on projectwhat problems may occur if the project manager does not have a follow-on

  Develop a work break dawn structure

Develop a work break dawn structure (WBS). Prepare a list of the specific activities that need to be preformed to accomplish the project objectives. For each activity assign the person who will be responsible.

  Discuss relevance of re-work in project management

Discuss relevance of Re-Work in Project Management.

  Fraction defective that can be used in a p chart

If there are 120 total defects from 10 samples, each sample consisting of 10 individual items in a production process, which of the following is the fraction defective that can be used in a "p" chart

  Analyze one piece of project management computer software

Analyze one piece of project management computer software, and develop an extensive SWOT analysis of it. Include how weaknesses and threats can be transformed into strengths.

  The wbs method in project management

Which of the following statement(s) is(are) correct for the WBS method in project management? I. Level 2 project deliverables are called as work packages II. Creating a WBS facilitates the cost and time estimation III. First OBS is created and this i..

  Submit analysis for apple product or service

Submit analysis of the first P (Iphones) for your chosen company's Apple product/service- The central focus of a marketing program will be on a product or service.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd