What is the new critical path and earliest completion time

Assignment Help Operation Management
Reference no: EM13221248

The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:

Activity Immed Pred. Time (weeks)
A 3
B A 2
C A 4
D A 4
E B 6
F C, D 6
G D, F 2
H D 3
I E, G, H 3
a. Draw the network diagram.
b. What is the critical path?
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
d. What is the new critical path and earliest completion time?

Reference no: EM13221248

Questions Cloud

What is your overall interpretation of this result : A sales project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances, the CPI, and the SPI. What is your overall interpretation of this result?
Describe the overall trends in crime rates in the us : Describe the overall trends in crime rates in the US over the last 50 years. Discuss some of the possible causes of any major increases or decreases in the crime rate, and discuss for which of your causes there is strong evidence for or against.
whAt is your overall interpretation of this result : Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. What is your overall interpretation of this result?
Does the day diary include sufficient information : Read the accompanying article on a day in the work life of Bill Ryan. Then write a job description for the job of customer service agent. Use the exhibits in this chapter to guide you in deciding what information in the story is relevant for job a..
What is the new critical path and earliest completion time : Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
Evaluation of team and selection process : Evaluate Palmer and his decision to create a new venture capital fund?
Efficient business processes key to maximizing value : What is a business process and why do businesses use them? Why are efficient business processes key to maximizing value and what are some of the ways that IT can accomplish job
Explain aluminum metal are reacted with excess hcl : If 45.8 grams of aluminum metal are reacted with excess HCl, what volume of H2 gas would be generated at 23.0 ºC and 1.00 atm pressure?
Rental revenues and rental expenses represent : Rental Revenues and Rental Expenses represent Cash transactions

Reviews

Write a Review

 

Operation Management Questions & Answers

  Describing change management approach

Describing change management approach and recommended action steps you would advise for minimizing adverse impact on organization and its people.

  Successful human resource organizations comprehend

Successful human resource organizations comprehend that giving intangible recognition to those organizational members' delivering tangible products to various types of internal and external customers with shifting needs is an effective approach.

  Determine the total charge under each plan

determine the total charge under each plan for this case: 120 minutes of days calls and 40 minutes of evening calls in a week -prepare a graph that shows total weekly cost for each plan versus daytime call minutes

  Bringing technology to poor families

Discuss this point below,Substantiate your discussion by providing an example from your own work/college experience or from current news.

  Describe process velocity also efficiency for the clinic

Oakwood Outpatient Clinic is analyzing its operation in an effort to improve performance. Describe process velocity also efficiency for the clinic.

  Discuss the known liability that biovail has incurred

Establishing a worst-case scenario, discuss the known liability that Biovail has incurred for deceiving its investors. Perform a comparative financial analysis of Biovail

  Compute the optimum ordering quantity for this item

Compute the optimum ordering quantity for this item. Explain how many units of the item should be maintained as safety stock for 99% protection against stock outs during an order cycle.

  Sound systems will embark on a companywide

Sound Systems will embark on a companywide cost control program in an attempt to improve its profits. One of the areas to be scrutinized closely for possible cost savings is inventory procurement.

  Relationship between creativity and intrapreneurship

What is the relationship between creativity, intrapreneurship, and innovation? Why are these elements vital to building a knowledge creating organization?

  What are the differences between mnes

What are the differences between MNEs and global organizations? How do organization types affect HR management?

  How many defectives do you need to find in a sample

How many defectives do you need to find (or more) in a sample of 20 so that you will shut down the line. You want to be 95% sure that there is a real problem beyond random noise before you shut down the line.

  Describe explicitly the optimal inventory system

Demand for the DeskPro computer at BestBuy is 1,000 units per month. BestBuy incurs a fixed order placement, transportation, and receiving cost of $4,000 each time an order is placed.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd