Problem: Consider a machining work cell consisting of 4 machines and 1 worker. The machining cell manufactures two components: L and M alternatively, that is, the two components are produced in the sequence of LMLMLM. Both components visit the machines in the order of A, B, C, and D.
Suppose each machine needs to be adjusted before it can be used to produce a different component. The setup times (in seconds) of the machines and the times (in seconds) for the machines to process a component are listed in the following table. We assume that it takes a machine the same amount of time to process a unit of different components.
Workstation
Processing time per unit (in seconds)
Setup Time (in seconds)
A
150
25
B
160
30
C
170
50
D
140
28
a. What is the machining cycle time (in seconds) for each of the four machines? For each machine, please provide at least one step of calculation and the correct answer for full credit.
b. Suppose the worker cycle time is 250 seconds. What is the cycle time (in seconds) of this machining cell? Please provide at least one step of calculation and the correct answer for full credit.
Computer upgrades have a nominal time of 80 minutes. Samples of 10 observations each have been taken, and the results are as listed. Historical data show that the standard deviation of the upgrade times is 0.5 minutes.
Product A is assembled from two units of S1 and three units of S2. S1 is made of one unit of C1, four units of C2, and one unit of C3. S2 is made of three units of C2 and two units of C3. How many C3’s are needed to fill an order for 100 A’s? Assume ..
Explain supply chain planning and control process. Analyze initiatives to overcome poor coordination in retail supply chains
Provide two examples for each of the following categories of questions when conducting process flow analysis. A. Flow B. Time C. Quantity D. Quality E. Cost ?
What are the pros and cons of an airline implementing a policy that heavier customers need to buy a second seat? Research an airline and provide their policy on heavier customers and seats. Do you agree or disagree with this policy?
Variance, or variation in the way we present a product is one of our greatest hurdles in quality management. Just consider. If you have a favourite pizza shop, and one time you get a bad one, are you finished doing business with them? The "bad" one m..
what is the probabilty that the project will take less than 30 days?
Which of the following is not listed as one of the value of service characteristics for transportation?
What is the difference between Top-down cost estimating technique and Bottom-up estimating technique? Which one of them is time-intensive and expensive to develop?
What does the title tell you about the topic? Does the title and thesis work together? Explain why or why not. Respond to the author's feedback request. Ask a question either about the topic, the process, researching, or the presentation tool
consists of any form of non-personal communication concerning an organization, product or idea that is paid for by a specific sponsor. The sponsor makes payment for the communication via one or more forms of media (e.g., television, radio, magazin..
The Academic Computing Center has five trainers available in its computer labs to provide training sessions to students. Assume that the design capacity of the system is 1900 students per semester and that effective capacity equals 90% of design capa..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd