What is the expected project length

Assignment Help Operation Management
Reference no: EM131357198

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Activity

Time (in hours)

Immediate Predecessor(s)

A

6.0

-

B

7.2

-

C

5.0

A

D

6.0

B, C

E

4.5

B, C

F

7.7

D

G

4.0

E, F

a) Draw the project network using AON.

b) Identify the critical path.

c) What is the expected project length?

d) Draw a Gantt chart for the project?

Reference no: EM131357198

Questions Cloud

Describe the structure of the ecosystem : Describe the structure of the ecosystem. In your own words, explain or define biogeochemical cycle. Describe the steps in the carbon cycle as an example of one biogeochemical cycle.
Code of conduct memo : You are a manager at a call center. The company frowns upon phone calls and texting during work hours. You have looked the other way a few times, but it has started to get out of hand - Write a memo reminding everyone that private phone and text me..
How easy is it to set up data relationships for the database : Does it appear to be integrated? When you change an item of data in one application, does it carry through to others? (For example, if a customer's billing address is changed, do all existing invoices reflect the change?)
Describe how you will manage waste that cannot be prevented : Describe how you will manage waste that cannot be prevented. Develop a plan to prevent excess wastewater in the face of a growing population. Describe how you will manage wastewater that cannot be prevented.
What is the expected project length : Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Draw the project network using AON. Identify the critical path. What is the expected project length
What are the three steps in decision making : What factors distinguish the types of information required by strategic level managers, by tactical level managers, and by operational level managers?
What are the various responses to a competitors price change : Some marketers feel that the image of the particular channel in which they sell their products does not matter--all that matters is that the right customers shop there and the product is displayed in the right way. Others maintain that channel ima..
How the six pillars of character come into play : When most people think of the careers in education, they default to a classroom teacher. In the past decade, the education arena has broadened to offer a wide array of career opportunities.
What purpose do you think the documentary has : What purpose do you think the documentary has? Did you know anything about this topic before watching the documentary? If yes, what? Is there anything that you really liked or really disliked about documentary? Explain.

Reviews

Write a Review

Operation Management Questions & Answers

  Strategy formulation and strategy implementation

What are the differences between strategy formulation and strategy implementation? In what ways are virtual and learning organizations different from the typical organization?  Explain how the International Monetary Fund and the World Bank support an..

  Consider the stocking level of a single item

Shockingly, demand for this item is 8 per week, with a variance of 60, corresponding to the product Nega BynoMeal

  Failed project should have estimated indirect costs

Using the ITT Tech Virtual Library, select case studies of two construction projects, one that was successful because of correct cost estimation and one that failed because of incorrect cost estimation. On the basis of the case studies, perform the f..

  Social responsibility applies into international logistics

Logistics providers always concern on speed in their business activities. Discuss the importance of speed in the supply chain. How speed be increased within the supply chain. Indicate potential sources and causes of risk in global logistics. How corp..

  Determine out of control conditions in form of extreme point

Suppose that a co-worker has been using Shewhart control charts to analyze a process but has only been using the upper and lower control limits to determine out-of-control conditions in the form of extreme points, without any consideration of the zon..

  Discussion of ethics indicate two societal consequences

What ethical violation did you find (2) Drawing explicitly from our discussion of ethics indicate two societal consequences of the misconduct you have investigated; and (3) Provide two specific things that must be done to prevent this from happin..

  Discuss the anticipated impacts upon operating efficiencies

Discuss the anticipated impacts (both positive and negative) upon operating efficiencies, and recommend solutions to minimize the negative impacts.

  What are the indicators for using regression analysis

What are the indicators for using a regression analysis? Create a research scenario in which it would be correct to use a regression analysis, including the research question, sample size, and dependent and independent variables?

  Constraint satisfying objective function

Now suppose that each can of dog food sales for $1.50. If the required profit per can is at least $0.65, write the constraint satisfying this objective function. You do not need to resolve for the optimal answer.

  What is the implied cost of shortage per quart

A small grocery store sells fresh produce, which it obtains from a local farmer. During the strawberry season, demand for fresh strawberries can be reasonably approximated using a normal distribution with a mean of 44 quarts per day and a standard de..

  Case study on changing business environment

Case Study on changing business environment Similar to many leaders, Marco has a team in place and does not have the luxury of building a new team to adapt to the changing business environment his firm now faces. Use the Team Leadership Model (TL..

  Describe the various risks and the affected stakeholders

For example, should the decision to repair the system be considered in terms of the potential liability risks of failure versus the costs of the repairs?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd