What is the cumulative earned value at the end of week three

Assignment Help Project Management
Reference no: EM13907189

Table 1: Budgeted Costs

 

TBC

Week

 

 

1

2

3

4

5

Task 1

50

25

15

10

 

 

Task 2

80

25

40

15

 

 

Task 3

40

 

 

20

20

 

Task 4

30

 

 

 

15

15

Table 2: Actual Costs

 

 

 

Week

 

 

 

1

2

3

4

5

Task 1

30

20

10

 

 

Task 2

25

45

20

 

 

Task 3

 

 

25

 

 

Task 4

 

 

 

 

 

Table 3: Percentage of Work Complete

 

 

 

Week

 

 

 

1

2

3

4

5

Task 1

50

80

100

 

 

Task 2

25

40

90

 

 

Task 3

 

 

40

 

 

Task 4

 

 

 

 

 

(a) Using data from Tables 1-3, what is the cumulative budgeted cost at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWS.

(b) Using data from Tables 1-3, what is the cumulative actual cost at the end of week 3? For those familiar with the DoD and PMI terminology, this is the ACWP.

(c) What is the cumulative earned value at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWP.

(d) Using data from Tables 1 3, what is the Cost Performance Index at the end of week 3?

(e) Using data from Tables 1-3, what is the Cost Variance and the Schedule Variance at the end of week 3?

(f) Using data from Tables 1-3, what is the Forecasted Cost at Completion (FCAC)? Show two different calculations.

2. (a) Using the figure below, perform resource leveling. Assume that each task can be performed independently of the other tasks.

242_Resource Leveling.png

(b) Using the figure in part (a), perform resource-limited scheduling. Assume that you have only three workers available at any given time. What is the new completion date for the project?

3. For the MX project as described below, the PMO sent a note to the PM indicating that under the current plan, they would miss the project due date so somehow they needed to accelerate the timing for the project plan. The customer wanted the projected completed in 20 weeks and the contract specifies a penalty of $5000 per week late up to 3 weeks and $10,000 per week late if more than 3 weeks. Based on the project time and cost information shown in the table below, what strategy should MX pursue?

Activity

Predecessor

Normal Time (Weeks)

Crash Time (Weeks)

Normal Cost ($)

Crash Cost ($)

Crash?

A

None

4

2

10,000

15,000

 

13

A

6

5

30,000

35,000

 

C

A

2

1

8,000

10,000

 

D

B

4

3

12,000

18,000

 

E

B, C

5

3

20,000

24,000

 

F

D, E

7

4

20,000

29,000

 

Reference no: EM13907189

Questions Cloud

Montel company''s july sales budget calls for sales : Montel Company's July sales budget calls for sales of $ 600,000. The store expects to begin July with $ 50,000 of inventory and to end the month with $ 40,000 of inventory.
Combination of memory technologies : Give an example of how an operating system may use a combination of memory technologies with varying speeds, capacities and costs to achieve overall good performance at acceptable cost.
Calculate the predetermined overhead rate for 2013 : Calculate the predetermined overhead rate for 2013 and the amount of over/under applied overhead applicable to January. Overhead is applied based on direct labor costs. Assume that the actual overhead incurred in the month is $705,000.
Lighthouse company anticipates total sales : Lighthouse Company anticipates total sales for June and July of $ 420,000 and $ 398,000, respectively.
What is the cumulative earned value at the end of week three : What is the cumulative earned value at the end of week 3? For those familiar with the DoD and PMI terminology, this is the BCWP. Using data from Tables 1 3, what is the Cost Performance Index at the end of week 3?
Size of an uncompressed text : Suppose the size of an uncompressed text file is 1 megabyte. How long does it take to download the file over a 32 Kilobit per second modem? How long does it take to take to download the file over a 1 megabit per second modem?
What barriers to success might people with disabilities : What barriers to success might people with disabilities
Should the company accept the special order : Prepare a report to management explaining the findings for the situations described above. Include in the report a description of the steps that the company should the following to make these short term decisions. Explain the importance of develop..
Terms of the difference : A typical password is about 8 characters long (and so can be stored in 8 bytes, or 64 bits). However, a typical key for encryption/decryption is much longer, and a key of 64 bits would not be considered secure. Explain this in terms of the differe..

Reviews

Write a Review

Project Management Questions & Answers

  Draw the framework of the project life cycle

Draw the framework of the Project life cycle and explain it - Prepare a matrix chart allocating people to jobs is essential.

  Building companygeneral ship building has a contract with

building companygeneral ship building has a contract with the department of the navy to build three new aircraft

  How is the project doing

How is the project doing? Is it ahead of schedule or behind schedule and is it under budget or overbudget? Should you alert your senior management and ask for assistance

  Responsibilities of being project manager of a trade

responsibilities of being project manager of a trade showscenarioyour company lrh products is about to attend a major

  Prepare a cms-pm projects on bluesfest music festival

Prepare a CMS/PM Projects on Bluesfest Music Festival. Advertising festival sponsors (1 gold sponsor, 2 silver, and 3 bronze - Gold sponsors pay more and should have a bigger presence.

  Explain what are organizational strengths and weaknesses

Explain what are the organizational strengths and weaknesses and how can management increase its understanding and application of business etiquette and protocol in this new region?

  Show the project complexity

Project complexity - How and why does that organization evaluate project complexity and what factors are typically considered

  Project manager in determining budgets for these tasks

What are the pros and con's of each method and what is the role of the project manager in determining budgets for these tasks?

  Project report on grand wines

you are required to present an initial project report on Grand Wines to the project sponsor that includes the following specific project outputs to show how you propose to implement this project:

  Review of business article on project managementreview an

review of business article on project managementreview an article in the business world as it relates to project

  What are ways to encourage meeting participation

List four methods used for the distribution of end-of-meeting reports to senior management or CEO and list four reasons for reporting end-of- meeting outcomes to senior management within a specific timeline.

  Limitation of researchprojectmany will argue that it is

limitation of researchprojectmany will argue that it is considered a good practice to acknowledge the limitation of

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd