Reference no: EM131365827
Bayside Financial
At Bayside Financial, where you work as a project manager, you have been asked to conduct user training sessions for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses):
• First, confirm arrangements for the training facility you plan to use (3 days).
• After you have confirmed the training facility, two tasks can begin at the same time: you need to send an e-mail message to all department managers announcing the training sessions (1 day) and you can develop the training material (5 days).
• As soon as the training material is complete, you can work on two tasks at once: arrange to have copies of handout material printed (2 days) and develop a set of Power Point slides (5 days).
• When the Power Point slides are ready, you conduct a practice training session with the instructor who will assist you (2 days).
• Finally, when the practice session is over and the handout material is ready, you can conduct the user training sessions ( 4 days).
Tasks
1. Prepare a list showing all tasks and their durations.
2. Analyze the fact situation carefully to determine which tasks are concurrent and which ones are dependent on other tasks.
3. Create a PERT chart that shows the project. Use a format similar to Figure 3-27 on page 110.lf project management software is available, use it to develop the chart.
4. What is the critical path for this project? How do you know?
What are the advantages of crime analysis
: What are the advantages of crime analysis to local law enforcement agencies? Is it worth it to have a crime analysis department in a law enforcement agency? Explain your answers
|
Proofrear the given paper
: Proofrear the given paper.- Make changes and edit the research report.- Correct grammar and good sentence structure .
|
Describe the creating a culture of engagement
: When employees feel engaged and motivated, they are often more committed to an organization. Organizational commitment is broadly defined as an employee's intent to stay with the organization. Nurse managers can have significant influence on an or..
|
Analysis of your internet data packets
: Based on the required reading assignment for this week, address the following: Do you think "a brief, one-second" analysis of your Internet data packets" violates your Fourth Amendment rights? Explain your answer
|
What is the critical path for this project
: As soon as the training material is complete, you can work on two tasks at once: arrange to have copies of handout material printed (2 days) and develop a set of Power Point slides (5 days).
|
Describe the technology including its uses and its purpose
: Address the following: Describe the technology, including its uses and its purpose. Explain why you chose this technology, and explain the long-range benefits of this technology for your department
|
How did you test that your stack implementation were correct
: CPS 350- How did you test that your stack implementations were correct? What did you enjoy about this assignment? What did you not enjoy? What could you have done better?
|
Identify strengths that karen has for progress in personal
: Karen is a 25-year-old white woman who lives alone in an apartment with her dog. Karen has been divorced for 2 years and is taking Prozac prescribed by her psychiatrist for depression. Karen and her boyfriend had been discussing marriage until he..
|
Create a gantt chart that shows the wbs
: When the building is assembled, start two tasks at once: finish the interior work (5 days) and set up an appointment for the final building inspection
|