What is the critical path for this network

Assignment Help Operation Management
Reference no: EM13759610

Hamilton County Parks is planning to develop a new park and recreational area on a re- cently purchased 100-acre tract. Project development activities include clearing play- ground and picnic areas, constructing roads, constructing a shelter house, purchasing picnic equipment, and so on. The following network and activity times (in weeks) are being used in the planning, scheduling, and controlling of this project:

Activity A B C D E F G H I

Time    9 6 6 3  0  3 2 6 3

a. What is the critical path for this network?

b. Show the activity schedule for this project.

c. The park commissioner would like to open the park to the public within six months from the time the work on the project is started. Does this opening date appear to be feasible? Explain.

Reference no: EM13759610

Questions Cloud

Network consultation proposal and consultation presentation : This assignment contains two (2) Sections: Network Consultation Proposal and Network Consultation Presentation. You must submit both sections as separate files In order to complete this assignment.
Learning curves show : Learning curves show:
Charged with violations of the false claims act : You are the Compliance Officer of a 230-bed teaching hospital. You have just read a newspaper article reporting that a physician on the hospital's medical staff has been charged with violations of the False Claims Act in his private practice.
Write essay on your experience studying american literature : Write a reflective essay of 250 words (one page) about your experience studying American literature this term. Important: Your paper must have a well developed introduction, body, and conclusion.
What is the critical path for this network : Hamilton County Parks is planning to develop a new park and recreational area on a re- cently purchased 100-acre tract. Project development activities include clearing play- ground and picnic areas, constructing roads, constructing a shelter house, p..
What is the maximum authorized router inventory : Lous Bakery has established that JIT should be used for chocolate chips due to the high probability of the kitchen heat melting the chips. The average demand is 130 cups of chocolate chips per week. The average setup and processing time is day. Each ..
Weather anomalies : Write about the above weather anomaliesthat can change global weather and climate.
What is optimal number of orders per year-annual total cost : Joe's Camera shop has a favorite model that has annual sales of 145. The cost to place an order to replenish inventory is $25 per order, and annual inventory costs are $20. Assume the store is open 350 days per year.  What is the optimal number of or..
Decided that concession sales will support themselves : As a manager of the St. Cloud Theatre Company, you have decided that concession sales will support themselves. The following table provides the information you have been able to put together thus far:

Reviews

Write a Review

 

Operation Management Questions & Answers

  How many copies of joy should be printed

Every four years, Blockbuster Publishers revises its textbooks. It has been three years since the best-selling book, The Joy of OR, has been revised.

  Relations be renormalized to form physical

List three common situations that suggest that relations be renormalized to form physical records.

  What are the major options for appraisal of employees

What are the major options for appraisal of employees? Discuss each option, identifying the one that you think is best and why you chose that option.

  Technology impacted the verbal and nonverbal cues

Analyze how the use of technology has impacted organizational communication both positively and negatively. How has technology impacted the verbal and nonverbal cues used in interpreting messages

  Communicate the status of quality during a project

While cost and time are critical components of projects, how would you define the quality of a project? Provide some examples of project reporting metrics a project manager could use to measure and communicate the status of quality during a projec..

  Application of a taguchi experimental design

John Douglass and Shirley Coleman presented a case study of the application of a Taguchi experimental design at industrial Statistics in Action 2000. The specifications tolerance for static pressure was 2.7 to 3.5 bar and at tomes reject levels appro..

  Advantages & disadvantages of flexible staffing in workforce

What are some considerations that (you) could take in developing and implementing an accident prevention program for plant personnel?

  Explain the importance of managers and management

What does this story illustrate about the importance of managers and management. Do you think this relationship would be just as important in other types of businesses i.e., non-fast-food businesses. Explain.

  Organizing function of management

Research on the topic of logistics management or other aspect of management that exemplifies the organizing function of management. See if you can find an interesting case/example to present to the class.

  What is the value creation frontier

What is the value creation frontier? How does each of the four generic business models allow a company to reach this frontier?

  Forecasting the outcome of risk schedule

One of the most important aspects of managing risk for a project is to accurately define the size of the project. Determine the criteria that must be considered to perform the project sizing and create one conditional factor with rationale.

  List some advantages and disadvantages associated with

list some advantages and disadvantages associated with booking a trip yourself as well as using a travel agent. what do

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd