What is the critical path

Assignment Help Operation Management
Reference no: EM13735637

1. Schedule the following activities using CPM:

Activity

IMMEDIATE PREDECESSOR

TIME (WEEKS)

A

-

1

B

A

4

C

A

3

D

B

2

E

C, 0

5

F

D

2

G

F

2

H

E, G

3

a. Draw the network.

b. What is the critical path?

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

2. The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activi­ties, times, and sequences required:

Activity

IMMEDIATE PREDECESSOR

TIME (WEEKS)

A

-

3

B

A

2

C

A

4

D

A

4

E

B

6

F

C. D

6

G

D. F

2

H

D

3

I

E. G. H

3

a. Draw the network diagram.

b. What is the critical path?

c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?

d. What is the new critical path and earliest completion time?

3. The following represents a project that should be scheduled using CPM-

Activity

IMMEDIATE PREDECESSORS

TIMES (DAYS)

a

m

b

A

-

1

3

5

B

-

1

2

3

C

A

1

2

3

D

A

2

3

4

E

B

3

4

11

F

C. D

3

4

5

G

D. E

1

4

6

H

F,G

2

4

5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?

Reference no: EM13735637

Questions Cloud

Entry strategy-technology based-quality based or cost based : Success of a company investing and operating in a foreign country depends on the competitive advantage of the company. The entry strategy could be technology based, quality based, or cost based. Explain and comment.
Compliance with regulatory agency guidelines : As a CMAA in a clinic, you are responsible for ensuring that job performance is in compliance with regulatory agency guidelines. There are many areas of compliance that a CMAA must be familiar with: financial risk, local and state regulations, Occ..
Exit gas streams are at 8 bar and at the same temperature : A gas stream is entering a separator at 1 mole/sec with mole fractions 15% A and 85% B. (Component 1 is A, component 2 is B.) At surface, the gas stream is 8 bar and 350K. Two streams exit the separator, one primarily of A (0.99 A1, 0.01 A2), and one..
Legal establishment of a nuclear family unit : Today, people marry for a variety of reasons, including family obligations, arranged marriages, the legal establishment of a nuclear family unit, the legal protection of children, or the public declaration of commitment. Discuss the following:
What is the critical path : What is the critical path. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten
What is significance of brown and board of education : What was the relationship between consumer culture and the emphasis on family life in the postwar era? What is the significance of the Brown v. Board of Education of Topeka decision?
Construct a b+ tree : Construct a B+ tree for the following set of key value (2,3,5,7,11,19,23,29,31) in ascending order where the pointers that will fit in one node is as follows:A. four B. six C. eight assuming the tree is initially empty and values are in ascending ..
Strategic leaders are concerned with vision and mission : A management consultant said that strategic leaders are concerned with vision and mission, while strategic managers are concerned with strategy.
Prepare a sample portfolio with resume : Each student is required to prepare a sample portfolio with (1) resume, (2) letter of interest, (3) sample thank you letter, (4) memo, and (5) sample interview questions and answers

Reviews

Write a Review

Operation Management Questions & Answers

  The average arrival rate is 82 customers per hour supposing

a grocery store has four check-out counters. the average service rate for each check-out counter is 22 customers per

  What is the optimal weekly profit

Profits for light beer are $2 per bottle, and profits for dark beer are $1 per bottle. What is the optimal weekly profit?

  Discuss liability of each party and potential amount

Upon graduation from college, Bob, Carol, Ted, and Alice formed Kotaku, LP, a limited partnership, to distribute video gaming software over the Internet.

  Many strategic leaders say that they want managers

Many strategic leaders say that they want managers to think strategically. How strategic leader can facilitate a middle manager to "think strategically?

  Explain project cost and the requirements for its

a project has an expected duration of 34 weeks with a critical path variance of 6. suppose the project network is given

  The european and north american freight transportation

Compare and contrast the European and North American freight transportation systems, globalized trade, and global policy implications.

  Distinguish between different classifications of contracts

Distinguish between the different classifications of contracts, including oral and written, express and implied, formal and simple, and entire and divisible.,quasi contracts (implied -in -law contracts)

  Llustrate what does disney do best to connect with its core

llustrate what does Disney do best to connect with its core consumer. Support your answers with a minimum of one source per question.

  Construct a control p-chart and interpret the data

A professor records the number of students who complain each week throughout the semester. If the class size is forty students, what are 3-sigma control limits for this class? Construct a control p-chart and interpret the data. Is the process in c..

  Compute the standard time for this job

Assuming an allowance factor of 15 percent of job time,compute the standard time for this job.

  What are the main points and theories discussed

What are the main points and theories discussed in the interview? Can you give examples from your work life that reflect Wheatley's observations? How do these ideas support or compare with the New Business Realities? Choose 1 Business Reality and ela..

  Offers the prospect of gaining an immediate competitive

offers the prospect of gaining an immediate competitive advantage in the new industry and thus helps ensure that the diversification move will pass the competitive advantage test for building shareholder value.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd