Reference no: EM132199553
Your project has four activities. Below is the current status of each activity.
Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.
Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.
Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.
Activity D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.
Earned Value Calculation
1. What are the SV, CV, SPI, and CPI for the project?
2. Assess the project performance to date. Do you get to have the celebration?