What are the critical path and duration of the project

Assignment Help Project Management
Reference no: EM1343261

Important information about PERT/CPM with optimistic, most likely, and pessimistic times

A project has the following activities, precedence relationships, and time estimates in days:

Activity Predecessor Optimistic Most likely Pessimistic
Activities Time Time Time
A -- 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15
F C 9 9 13
G C 7 7 7
H D 4 6 8
I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6

Compute the earliest start, earliest finish, latest start, latest finish, and slack for each activity

What are the critical path and duration of the project?

What is the probability that the project will take longer than 38 days?

Reference no: EM1343261

Questions Cloud

Evaluate the optimal production size for fertilizer : Evaluate the optimal production size for the fertilizer and evaluate the maximum inventory level
Project management - contracting and procurement : Contracting and Procurement - What kind of contract will you pursue for each of the following purchases related to this project?
Concept of change management process in a project : Concept of Change Management Process in a Project - Explain the concept of the change management process within a project.
Manage risks in project management : Describe how risk has impacted a project that you have been associated with as a team member or project leader and give at least two examples where surprise events impacted the project.
What are the critical path and duration of the project : Evaluate the earliest start, earliest finish, latest start, latest finish, and slack for each activity and what are the critical path and duration of the project?
Project management for acme development corporation : Project Management for ACME Development Corporation: Procurement process
Paper about southwest airlines organizational culture : Prepare a paper about Southwest Airlines organizational culture, the role that cost accounting plays as par to of that culture and the cost accountants potential impact on that culture.
Request for proposals : Request for Proposals - What is an RFP, and how do analysts use one to gather information about hardware and system software?
Explain participative management style : Production manager Alberto Perez has been successful in his U.S. assignment using a participative management style.

Reviews

Write a Review

Project Management Questions & Answers

  Risks introduced by change in plans

What are the risks (adverse effect) that are introduced by this change in plans?

  Identifying situations that can cause project to fail

Risk management is a matter of identifying the situations that could cause your project to fail.

  Goal of increasing capacity for passengers in hong kong area

Given the goal of increasing capacity for passengers and cargo in the Hong Kong area, what options were available?

  Work breakdown structure differ from the project network

How does the Work Breakdown Structure differ from the Project Network (Diagram)?

  Major risks to organization when implementing and using it

What are the major risks to the organization when implementing and using IT?

  Percentage of-sales approach to advertising budgeting

American Express marketers say they do not use the percentage-of-sales approach to advertising budgeting because if sales decrease in the segment, so will their budget.

  Identifying the critical path for project network

Determine the early and late start and finish times and the slack times for the activities. Identify the critical path.

  Project scope statement to define end result of project

A project scope statement is used to define the end result of a project. Its purpose is to define as clearly as possible what the project will deliver to the customer.

  Compute the designed capacity and effective capacity

Describe and compute the Designed Capacity and Effective Capacity - Find out and interpret the significance of each three elements in a project

  Process involved in building the wbs

Is there the same kind of team process involved as in building the WBS?

  Distinguishing capital project funds and debt service funds

Distinguish between capital project funds and debt service funds. How are they related and how are they different?

  Monitor and control project progress

Monitoring and Controlling Project Progress and what are some of the ways that a project manager can use budgeting plans to track and compare actual data on project progress?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd