Unimed is a manufacturer of specialty medidcal equipment. For one particular variety of equipment offered:

average daily demand is 25 units, with a standard deviation of 6 units

replenishment lead time is 15 days, with a standard deviation of 4 days

find the safety stock required at 1 standard deviation under conditions of demand and replenishment cycle uncertainties (rounded to the nearest whole number):

A 103 units

B 34 units

c 14 units

d 68 units

Reference no: EM1381173

Questions Cloud

Create an overloaded constructor : Create the statements to make an overloaded constructor for the class named Car. The constructors should support 0, 1, or 2 arguments. The 1st argument will denote engine size and contain an Integer.
How many orders will boboux usa need to place to the parent : How many orders will Boboux Usa need to place to the parent company in New Zealand? Borboux USA sells New Zealand hand made leather balloons to American Customers. For one of their more popular lines, the manager estimates that
Question about communication : Communication is valuable; a main part of this is the ability to provide management the information they required, when they require it.
Calculate a standard error for sample mean production rate : Calculate a standard error for the sample mean production rate for the new method and what is the standard error of the $1600 estimate?
Unimed is a manufacturer of specialty medidcal equipment : Unimed is a manufacturer of specialty medidcal equipment. For one particular variety of equipment offered: average daily demand is 25 units, with a standard deviation of 6 units
Macpack products orders materials from its suppliers : MacPack Products orders materials from its suppliers 26 times per year, at a re-ordering cost of $350 (per order).
Primary steps to database design : We explored the 2-primary steps to database design - conceptual design and physical design. We discussed importance of having representatives from all key stakeholders in conceptual design to ensure accuracy of the design.
Your company has an average annual inventory : Your company has an average annual inventory of $70 million. Its annual cost of goods sold (COGS) is $560 million. Order costs are $195 per order
What is the average number of customers in the system : What is the average number of customers in the system? (Do not round intermediate calculations. What is the average number of customers that are in service? (Do not round intermediate calculations.

Reviews

Write a Review

 

Project Management Questions & Answers

  Question in project management overview

Identify the types of professional environments where you would expect to find project management techniques being used. Choose one environment you are familiar with and describe how a project manager has led effectively.

  Determining expected time and variance for activity

Determine the expected time and variance for each activity.

  Mid-level employee for a procurement office

Seeking a mid-level employee for a procurement office - the supervisor of an eight-person procurement office for a manufacturing company.

  Concept of change management process in a project

Concept of Change Management Process in a Project - Explain the concept of the change management process within a project.

  Evaluate the total cost of plan

Operations Management-Aggregate production planning - Evaluate the total cost of this plan.

  Lowest ratio mixed assembly planning

Lowest Ratio Mixed Assembly Planning - For that mixture what is the lowest ratio mixed model assembly sequence

  Information system for project management purposes

Discuss and explain the need for an integrated information system for project management purposes.

  Puropse of work breakdown structure

How will the work breakdown structure be used to accomplish each of the above steps and would you agree or disagree that the more levels the WBS contains

  Risks introduced by change in plans

What are the risks (adverse effect) that are introduced by this change in plans?

  Project management earned value calculation

Evaluate the earned value completed and the total planned cost for the project at completion

  Situation in which pert estimation technique be used

In what situations should the PERT estimation technique be used?

  Health care administration-related questions

Why is using Bayes' theorem important to help answer health care administration-related questions

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd