The reorder point is defined as the lead time demand

Assignment Help Operation Management
Reference no: EM13873213

The reorder point is defined as the lead time demand for an item. In cases of long lead times, the lead time demand and thus the reorder point may exceed the economic order quantity. In such cases, the inventory position will not equal the inventory on hand when an order is placed and the reorder point may be expressed in terms of either the inventory position or the inventory on hand. Consider the economic order quantity model with D=5000 Co = $32 Ch=$2 and 250 working days per year. Identify the reoder point in terms of the inventory position and in terms of the inventory on hard for each of the following lead times.

A 5 days

B 15 days

C 25 days

D 45 days

 

 

Reference no: EM13873213

Kirkpatrick evaluation

Kirkpatrick's Evaluation Why or why not would an organization choose to under go an evaluation process before or after training? Is it a good or bad occurrence if unexpect

Explain what you would dodifferently

Research a company hat has had recent bad customer service and explain what you would dodifferently as the owner of the business.The requirements below must be met for

Select a nation other than the u.s,

Select a nation other than the U.S, and other than one already posted by any of your classmates.(NOTE: This encourages you to begin, and complete, this assignment earlier, rat

Virtual supply chains locate two articles

LP8 Assignment: Virtual Supply Chains Locate two articles on the topic of virtual supply chains. Synthesize each article into a one-page summary using your own words.

Lp8 assignment: virtual supply chains

LP8 Assignment: Virtual Supply Chains Locate two articles on the topic of virtual supply chains. Synthesize each article into a one-page summary using your own words. Include

Use of a grid analysis

Exercise 2: Use of a Grid Analysis (Weighted Scoring Model) to Help Make the North American Plant Location Decision for the RX 330 This exercise illustrates how when deciding

Seaburg construction company, formed

Seaburg Construction Company, formed in 1950by James Seaburg, was initially en­gaged in residential construction in Mobile, Alabama.Later, Mr. Seaburg's business was expanded

A supplier certification program and a supplier development

WHAT IS THE PURPOSE OF A SUPPLIER CERTIFICATION OR QUALIFICATION PROGRAM?What is the difference between a supplier certification program and a supplier development program ? I

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd