The project duration and identifies the critical path

Assignment Help Other Subject
Reference no: EM13230751

SerDoc is a company that manufactures customised medical equipment for hospitals and is about to initiate a project for building a new machine for a recent order from a hospital. The project involves the following six phases: initiating, requirements gathering, design, development and testing, documentation, deployment and testing. The project is scheduled to start on 15 October.

The duration and precedence relationships (or sequencing) between the tasks of the project are provided in the table below:

Phase

Task Name

Task ID

Immediate Predecessor

Time (Days)

Initiating

Defining the scope of the project

1


5

Initiating

Analysing the existing product which is being produced by SerDoc

2


10

Requirements Gathering

Preparing the requirements document and a high-level design

3

1, 2

15

Requirements Gathering

Conducting a proof of concept to validate the approach

4

3

7

Requirements Gathering

Signoff of requirements and a high-level design from the customers who have ordered the machine

5

3

4

Design

Design of hardware components

6

5, 4

20

Design

Detailed product specifications

7

5

30

Design

Detailed program design*

8

7

20

Development and Testing

Manufacturing of the shell of the machine

9

7, 8

40

Development and Testing

Assembling of the electronic components of the machine

10

7

10

Development and Testing

Testing of the circuit for accuracy of responses

11

9, 10

40

Development and Testing

Testing of the manufactured machine and calibration to standards

12

11

15

Documentation

Preparing an installation and user manual

13

Finishes with 8, 12

30

Deployment and Testing

Installation of the machine at the hospital

14

12

5

Deployment and Testing

Conducting trials and checking all functionality at the hospital after installation

15

12, 14

10

Deployment and Testing

Getting client signoff

16

13, 15

0

Deployment and Testing

Training hospital technicians for using the machine

17

12

15

Deployment and Testing

Commissioning of the machine at the hospital

18

8

9

Part

On the basis of the above information, use Microsoft Project to create a project plan that lists project tasks, establishes precedence relationships between tasks, sets precedence relationships, calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and deployment and testing.

What is the end date of the project?

Reference no: EM13230751

Questions Cloud

Describe the additional factors that impact global supply : Based on the concept of globalization, many businesses operate and compete in a global environment. Describe the additional factors that affect/impact global supply chains.
Explain the genetic variation : How would the research programs of the two schools have influenced their perceptions about the amount of genetic variation present in the wild?
Estimate the electron and hole drift velocity : Consider an n-Si with doping of 9*10^16cm^-3. In a certain region of this sample, there is an electric field of 1000V/cm. Estimate the electron and hole drift velocity and the total drift current density in that region.
What is the maximum possible output per week for this line : An assembly line with 7 tasks is to be balanced. The longest task is 8 minutes, the shortest task is 2 minutes, and the sum of the task times is 53 minutes. The line will operate for 6 hours per shift, 1 shifts per day, 6 days per week.
The project duration and identifies the critical path : Calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and de..
Compute the molar mass of the unknown gas : Calculate the molar mass of the unknown gas. Remember that the faster the rate of effusion, the shorter the time required for effusion; that is, rate and time are inversely proportional.
Compute the equilibrium carrier concentrations : Compute the equilibrium carrier concentrations and the position of the Fermi level with respect to the conduction band edge for a uniformly doped Si region with N_D=1*10^16 cm^-3 and N_A = 1*10^17 cm^-3 at room temperature.
What is the minimum sales quantity that would justify : What is the minimum sales quantity that would justify the purchase of new equipment?
State standardized against a standard solution of hcl : If 1L of .15M NaOH is unprotected from mmol of CO2, what will be its new molarity when it is standardized agains a standard solution of HCl using

Reviews

Write a Review

Other Subject Questions & Answers

  Study analysis-stanford prison

The Stanford Prison Study done by Philip Zimbardo in the early 1970s. After reading the outcome of the experiment discuss with your classmates how Zimbardo's findings apply to similar real-life events happening today.

  Does the organization explain its goals and objectives

Does the organization explain its goals and objectives clearly? Explain your answer. Are the goals and objectives long term or short term? Are the goals and objectives manifest or latent?

  Measure actual against baseline is the earned value analysis

One tool commonly used to measure actual against baseline is the Earned Value analysis

  Commonly held beliefs regarding poverty

Describe your reactions to his claims and compare what Gorski talks about to commonly held beliefs in our culture regarding poverty.

  Regarding social development

Which of the following is not true regarding social development?

  Find how many total fat kcal are in the pork chop

Three ounces of pork have a total of 275 kcal with 8 grames per ounces. A man consumes 2500 total kcal per day and 110 gram of fat.

  Concept of primary and secondary social group

Define and explain the concept of primary and secondary social group. Additionally, review the correlation it has on the values, norms, and ethics.

  Whether or not andrew was justified in boarding in plane

Discuss whether or not Andrew Speaker was justified in boarding a plane and potentially spreading his turbuclosis disease to others; also consider the actions of the CDC in initially telling Speaker that travel was okay.

  Explain eight elements in communication process

Using eight elements in communication process, examine what went wrong, why it went wrong, and how you might have been able to fix the problem?

  Primary environmental impacts of urban sprawl

What is urban sprawl and why does it occur?  What are the primary environmental impacts of urban sprawl?

  Process and composition influence project team performance

How does work design, composition, context, and process influence project team performance?

  Demographics of hiv-aids patient

Identify the population on which your case study will focus, such as the aging population, patients with a particular chronic disease, children, patients with AIDS, patients requiring long-term care, or emergency management.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd